m |
m |
||
Line 59: | Line 59: | ||
STEP 8: Complete Columns L and M. From the dropdown in Column L select the owner/operator of the BMP. Column M autofills if you are the owner, otherwise enter the name of the owner/operator of the BMP. For guidance, click [[Guidance for completing the TMDL reporting form#Column L – Who Owns this BMP/Activity?|here]]. | STEP 8: Complete Columns L and M. From the dropdown in Column L select the owner/operator of the BMP. Column M autofills if you are the owner, otherwise enter the name of the owner/operator of the BMP. For guidance, click [[Guidance for completing the TMDL reporting form#Column L – Who Owns this BMP/Activity?|here]]. | ||
+ | [[file:City_a_activities4.PNG|thumb|left|alt=city_a_activities1|Step 8]] | ||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | |||
+ | STEP 9: Complete Columns N and O if desired. This rain garden was installed and was operational in 2010. City A enters “2010” in Column N. No comments are added to Column O. |
The following is a quick guide to complete the BMPs-Activities completed tab.
STEP 1: Inventory BMPs that
STEP 2: Identify the location of your MS4 in relation to watershed boundaries and the TMDL study area STEP 3: Plot the location of inventoried BMPs for which you have geographic locations STEP 4: Determine from which TMDL the BMPs reduce pollutants
Example data shown for a rain garden in City A, for more details see examples.
STEP 5: Enter the reporting year by using the drop down menu in column D. Columns A through C autofill.
STEP 6: In Column E, enter your first BMP, selecting the appropriate category from the dropdown box. Complete Column F (dropdown) if desired. For guidance, click here.
STEP 7: Complete columns H, I, J, and K if they did not autofill. These are ID number and locational coordinates for the rain garden (INF1). For guidance, click here.
STEP 8: Complete Columns L and M. From the dropdown in Column L select the owner/operator of the BMP. Column M autofills if you are the owner, otherwise enter the name of the owner/operator of the BMP. For guidance, click here.
STEP 9: Complete Columns N and O if desired. This rain garden was installed and was operational in 2010. City A enters “2010” in Column N. No comments are added to Column O.