Line 113: | Line 113: | ||
===Use of temporary sediment basins, if applicable=== | ===Use of temporary sediment basins, if applicable=== | ||
− | * Use of temporary sediment basin if 10 or more acres of disturbed soil drain to one place, or 5 acres if the discharge point is within one mile of a special or impaired water<br> | + | {| class="wikitable floatright" |
− | * Documented live storage volume from each acre drained<br> | + | |- |
− | * Design that: | + | ! Temporary sediment basin live storage: |
− | ** prevents short-circuiting & floating debris discharge<br> | + | |- |
− | ** allows for complete basin drawdown <br> | + | | If the live storage volume is calculated, it must accommodate a 2-year, 24 hour flood event, but cannot be less than 1,800 cubic ft |
− | ** has a stabilized emergency overflow<br> | + | |- |
− | ** withdraws water from the surface<br> | + | | If live storage is not calculated, then the basin must accommodate 3,600 cubic ft of live storage |
− | ** includes energy dissipation for the basin outlet<br> | + | |} |
− | ** is outside of surface waters <br> | + | *Use of temporary sediment basin if 10 or more acres of disturbed soil drain to one place, or 5 acres if the discharge point is within one mile of a special or impaired water<br> |
− | ** avoids draining to wetlands<br> | + | *Documented live storage volume from each acre drained<br> |
− | ** is operational before construction starts<br> | + | *Design that: |
+ | **prevents short-circuiting & floating debris discharge<br> | ||
+ | **allows for complete basin drawdown <br> | ||
+ | **has a stabilized emergency overflow<br> | ||
+ | **withdraws water from the surface<br> | ||
+ | **includes energy dissipation for the basin outlet<br> | ||
+ | **is outside of surface waters <br> | ||
+ | **avoids draining to wetlands<br> | ||
+ | **is operational before construction starts<br> | ||
===Post-construction stormwater management=== | ===Post-construction stormwater management=== |
This document provides guidance on how to comply with the site plan review process in the Minnesota Pollution Control Agency’s (MPCA) Authorization to Discharge Stormwater Associated with Small Municipal Separate Storm Sewer Systems (MS4) under the National Pollutant Discharge Elimination System/State Disposal System (NPDES/SDS) Permit Program (MS4 Permit). The MS4 Permit requires you, the permittee, to perform and document site plan reviews for construction projects that disturb one acre or more of land to ensure active and post-construction requirements of your regulatory mechanism (e.g. code, ordinance, law) are met. The MS4 Permit requires your regulatory mechanism to be as stringent as the Authorization to Discharge Stormwater Associated with Construction Activity under the NPDES/SDS Program general permit (MNR100001/Construction Stormwater Permit).
The items identified below are the minimum that must be evaluated during your stormwater site plan review under the MS4 and Construction Stormwater Permits. For each site plan review performed, you must document the project name, location, total acreage to be disturbed, owner and operator of the proposed construction activity, and any stormwater related comments used to approve or deny the project. If you’d like to conduct a more comprehensive review, please see the MPCA’s SWPPP Checklist. During the site plan review, you must verify that site plans include (an) acceptable:
Stabilization schedule must be no less than: |
---|
14 days for all exposed soils |
7 days if a discharge point is within one mile of a special or impaired water |
24 hours for areas within 200 ft of a public water during fish spawning times |
24 hours for areas of ditches and swales within 200 ft of the property edge or surface water discharge point and 14 days for remainder |
Insepction schedule must be no less than: |
---|
Every 7 days during active construction |
Within 24 hours after a 0.5 inch rain event |
If work is suspended due to frozen ground, inspections must begin within 24 hours after runoff occurs or construction starts |
For parts of the site with permanent cover but work is ongoing elsewhere, inspections can be once per month |
If the entire site has permanaent cover and there is no active construction, inspections can be once per month for twelve months |
BMP maintenance schedule must be no less than: |
---|
End of next business day for nonfunctioning BMPs |
End of next business day or as soon as conditions allow for nonfunctioning perimeter control |
72 hours or as soon as conditions allow for draining sedimentation basins |
24 hours for tracked sediment |
7 days for removing deltas and sediment from surface water and restabiliztion |
Washout operations specifications: |
---|
Washout wastes must not contact the ground |
Washout operations must not result in runoff |
Temporary sediment basin live storage: |
---|
If the live storage volume is calculated, it must accommodate a 2-year, 24 hour flood event, but cannot be less than 1,800 cubic ft |
If live storage is not calculated, then the basin must accommodate 3,600 cubic ft of live storage |