The post-construction stormwater management program should include: | The post-construction stormwater management program should include: | ||
− | :*A regulatory mechanism that requires proposers of construction activity to submit site plans with post-construction stormwater management best management practices (BMPs) | + | :*A regulatory mechanism that requires proposers of construction activity to submit site plans with post-construction stormwater management best management practices (BMPs). |
:*A regulatory mechanism that requires the use of green infrastructure. | :*A regulatory mechanism that requires the use of green infrastructure. | ||
:*A regulatory mechanism that specifies that there will be no net increase in stormwater volume, total suspended solids (TSS), and total phosphorus (TP) from new development projects; and a net decrease in volume, TSS, and TP for redevelopment projects. See [https://www.pca.state.mn.us/sites/default/files/wq-strm4-59e.pdf MPCA this fact sheet] for the different methodologies to employ to meet this requirement. | :*A regulatory mechanism that specifies that there will be no net increase in stormwater volume, total suspended solids (TSS), and total phosphorus (TP) from new development projects; and a net decrease in volume, TSS, and TP for redevelopment projects. See [https://www.pca.state.mn.us/sites/default/files/wq-strm4-59e.pdf MPCA this fact sheet] for the different methodologies to employ to meet this requirement. |
Paved surfaces exacerbate the negative impacts to stormwater, including a increasing the stormwater discharge volume and pollutants in stormwater. Managing stormwater onsite post-construction is the more effective way to mitigate these impacts. Minimum Control Measure (MCM) 5 of the municipal seperate storm sewer system (MS4) General Permit requires permittees to have and enforce a post-construction stormwater management program that prevents or reduces stormwater pollution in new- and re- development projects.
The post-construction stormwater management program should include:
Click on the blue links above in the "Requirements" section to get more information and resources specific to those permit requirements. In addition, all resources related to MCM 5 are below.