− | See [https://websoilsurvey.sc.egov.usda.gov/App/HomePage.htm NRCS Web Soil Survey] for hydrologic soil descriptions for the swale location. [[Design infiltration rates|A and B soils]] are potentially suitable for an infiltration swale. The maximum allowed field-measured infiltration rate shall not exceed 8.3 inches per hour. | + | See [https://websoilsurvey.sc.egov.usda.gov/App/HomePage.htm NRCS Web Soil Survey] for hydrologic soil descriptions for the swale location. [[Design infiltration rates|A and B soils]] are potentially suitable for an infiltration swale. The maximum allowed field-measured infiltration rate shall not exceed 8.3 inches per hour for an infiltration swale. |
This page provides a discussion of design elements and design steps for dry swales, which are often called grass swales. The following discussion includes dry swales used as filtration or infiltration practices, with the distinction being the presence of an underdrain for filtration practices.
The following terminology is used throughout this design page.
HIGHLY RECOMMENDED - Indicates design guidance that is extremely beneficial or necessary for proper functioning of the practice, but not specifically required by the MPCA CGP.
RECOMMENDED - Indicates design guidance that is helpful for practice performance but not critical to the design.
Use this link to access .pdf diagrams of CADD drawings. To see all filtration CADD images in a combined pdf, click here.
Before deciding to use a dry swale practice for stormwater management, it is helpful to consider several items that bear on the feasibility of using such a device at a given location. This section describes considerations in making an initial judgment as to whether or not a dry swale is the appropriate BMP for the site.
The following links provide additional information on specific constraints to infiltration. The Construction Stormwater General Permit prohibits infiltration under certain conditions, which are summarized and discussed in detail at this link.
The RECOMMENDED maximum drainage area is typically 5 acres, although in practicality it is difficult to control the contributing drainage area to a swale.
Unless slope stability calculations demonstrate otherwise (see [1], [2], [3]), it is HIGHLY RECOMMENDED that swales be located a minimum horizontal distance of 200 feet from down-gradient slopes greater than 20 percent, and that slopes in contributing drainage areas be limited to 15 percent
If the swale is constructed as an infiltration practice, the following table summarizes horizontal and vertical setback distances for required and recommended minimum distances from an infiltration practice to an above-ground or underground structure. It will be necessary to consult local ordinances for further guidance on siting infiltration practices.
.
Required and recommended minimum vertical and horizontal separation distances. This represents the minimum distance from the infiltration practice to the structure of concern. If the structure is above-ground, the distance is measured from the edge of the BMP to the structure. If the structure is underground, the vertical separation distance represents the distance from the point of infiltration through the bottom of the system to the structure, while the horizontal separation (often called setback) distance is the shortest distance from the edge of the system to the structure.
Link to this table
Structure | Distance (feet) | Requirement or recommendation | Note(s) | |
---|---|---|---|---|
Vertical | Saturated soil | 3 | Requirement1 | |
Bedrock | 3 | Requirement1 | ||
Horizontal | Public supply well | 100 for sensitive wells; 50 for others3 | Requirement | |
Building/structure/property line2 | 10 | Recommended | ||
Surface water | none unless local requirements exist | If nearby stream is impaired for chloride, see [4] | ||
Septic system | 35 | Recommended | ||
Contaminated soil/groundwater | No specific distance. Infiltration must not mobilize contaminants. | |||
Slope | 200 | Recommended | from toe of slope >= 20% | |
Karst | 1000 up-gradient 100 down-gradient | Requirement1 | active karst |
1 Required under the Construction Stormwater General Permit
2 Minimum with slopes directed away from the building
3If treating an average of 10,000 gallons per day; otherwise separation distance is 300 feet
A separation distance of at least 3 feet is REQUIRED under the MPCA CGP between the bottom elevation of infiltration swales and the elevation of the seasonally high water table. Shallow bedrock areas should be avoided for dry swales with a minimum separation distance of 3 feet.
A field soil properties investigation is HIGHLY RECOMMENDED.
It is HIGHLY RECOMMENDED that infiltration practices not be used in active karst formations without adequate geotechnical testing.
See stormwater and wellhead protection for guidance and recommendations for determining the appropriateness of infiltrating stormwater in a Drinking Water Supply Management Area (DWSMA). For more information on source water protection see Minnesota Department of Health.
See NRCS Web Soil Survey for hydrologic soil descriptions for the swale location. A and B soils are potentially suitable for an infiltration swale. The maximum allowed field-measured infiltration rate shall not exceed 8.3 inches per hour for an infiltration swale.