General [[Process for selecting Best Management Practices#Using cost factors to select BMPs|cost etimation]] methods can be used by site planners to compare the relative construction and maintenance costs for structural BMPs. However, it is recommended that construction and maintenance budgets should be based on site specific information. Once the construction plans are created, designers could use the table below and the cost estimation worksheet. The table below lists the site components that are specific to bioretention practices. Not included in this table are those cost items that are common to all construction projects, such as mobilization, traffic control, erosion and sediment control, permitting, etc. | General [[Process for selecting Best Management Practices#Using cost factors to select BMPs|cost etimation]] methods can be used by site planners to compare the relative construction and maintenance costs for structural BMPs. However, it is recommended that construction and maintenance budgets should be based on site specific information. Once the construction plans are created, designers could use the table below and the cost estimation worksheet. The table below lists the site components that are specific to bioretention practices. Not included in this table are those cost items that are common to all construction projects, such as mobilization, traffic control, erosion and sediment control, permitting, etc. | ||
− | {{: | + | {{:Cost components for bioretention practices}} |
General cost etimation methods can be used by site planners to compare the relative construction and maintenance costs for structural BMPs. However, it is recommended that construction and maintenance budgets should be based on site specific information. Once the construction plans are created, designers could use the table below and the cost estimation worksheet. The table below lists the site components that are specific to bioretention practices. Not included in this table are those cost items that are common to all construction projects, such as mobilization, traffic control, erosion and sediment control, permitting, etc.
This table shows cost Components for Bioretention Practices
(Link to this table)
Implementation Stage | Primary Cost Components | Basic Cost Estimate | Other Considerations |
---|---|---|---|
Site Preparation | Tree & plant protection | Protection Cost ($/area) x Affected Area | Removal of existing structures, topsoil removal and stockpiling |
Clearing & grubbing | Clearing Cost ($/area) x Affected Area | Removal of existing structures, topsoil removal and stockpiling | |
Topsoil salvage | Clearing Cost ($/area) x Affected Area | Removal of existing structures, topsoil removal and stockpiling | |
Site Formation | Excavation / grading | 4-ft Depth Excavation Cost ($/acre) x Area (acre) | Soil & rock fill material, tunneling |
Hauling material offsite | Excavation Cost x (% of Material to be hauled away) | Soil & rock fill material, tunneling | |
Structural Components | Under-drains | Under-drain cost ($/lineal foot) x length of device | Pipes, catch-basins, manholes, valves |
Inlet structure | ($/structure) or ($/curb cut) | Pipes, catch-basins, manholes, valves | |
Outlet structure | ($/structure) | Pipes, catch-basins, manholes, valves | |
Liner | Liner cost ($/square yard) x area of device) | Pipes, catch-basins, manholes, valves | |
Site Restoration | Filter strip | Sod cost ($/square foot) x filter strip area | Tree protection, soil amendments, seed bed preparation, trails |
Soil preparation | Topsoil or amendment cost ($/acre) x Area (acre) | Tree protection, soil amendments, seed bed preparation, trails | |
Seeding | Seeding Cost ($/acre) x Seeded Area (acre) | Tree protection, soil amendments, seed bed preparation, trails | |
Planting / transplanting | Planting Cost ($/acre) x Planted Area (acre) | Tree protection, soil amendments, seed bed preparation, trails | |
Annual Operation, Maintenance, and Inspection | Debris removal | Removal Cost ($/acre) x Area (acre) x Frequency | Vegetation maintenance, cleaning of structures |
Sediment removal | Removal Cost ($/acre) x Area (acre) x Frequency | Vegetation maintenance, cleaning of structures | |
Weed control | Labor cost ($/hour) x Hours per visit x Frequency | Vegetation maintenance, cleaning of structures | |
Inspection | Inspection Cost ($) x Inspection Frequency | Vegetation maintenance, cleaning of structures | |
Mowing | Mowing Cost ($) x Mowing Frequency | Vegetation maintenance, cleaning of structures |