Comparison of Four Levels of Assessment (adapted from Erickson et. al, 2013)
Link to this table

Title Objectives Relative effort Typical elapsed time
Visual inspection Determine if stormwater BMP is malfunctioning 1 1 day
Capacity testing Determine infiltration or sedimentation capacity and rates 10 1 week
Synthetic runoff testing Determine infiltration rates, capacity, and pollutant removal performance 10-100 1 week to 1 month
Monitoring Determine infiltration rates, capacity, and pollutant removal performance 400 14 months