<font size="1">*Note: The ED Shallow Wetland design guidance does not meet the MPCA requirements for permanent volume. The guidance may be applied in a stormwater retrofit situation where area requirements preclude the use of a Shallow Wetland</font size> | <font size="1">*Note: The ED Shallow Wetland design guidance does not meet the MPCA requirements for permanent volume. The guidance may be applied in a stormwater retrofit situation where area requirements preclude the use of a Shallow Wetland</font size> | ||
− | <noinclude>[[ | + | <noinclude> |
+ | [[Category:Level 3 - General information, reference, tables, images, and archives/Tables/Ponds and wetlands (constructed)]] | ||
+ | </noinclude> |
Summary of wetland design criteria
Link to this table
Design Criteria | Shallow Wetland | Pond/Wetland | ED Shallow Wetland* |
---|---|---|---|
Wetland/Watershed Ratio (Ac/Ac) | 0.2 | 0.1 | 0.1 |
Minimum Drainage Area (Ac) | 25 | 10 | 25 |
Length to Width Ratio (minimum)(ft/ft) | 2:1 | 2:1 | 2:1 |
Extended Detention (ED) | No | Optional | Yes |
Allocation of Vwq (pool/marsh/ED) in % | 25/75/0 | 70/30/0(includes pond volume) | 25/25/50 |
Allocation of Surface Area (deepwater/low marsh/high marsh/semi-wet) in % | 20/35/40/5 | 45/25/25/5 (includes pond surface area) | 10/35/45/10 |
Forebay | Required | Required | Required |
Micropool | Required | Required | Required |
Outlet Configuration | Reverse-slope pipe or hooded broad-crested weir | Reverse-slope pipe or hooded broad-crested weir | Reverse-slope pipe or hooded broad-crested weir |
*Note: The ED Shallow Wetland design guidance does not meet the MPCA requirements for permanent volume. The guidance may be applied in a stormwater retrofit situation where area requirements preclude the use of a Shallow Wetland