The table below lists the specific site components that are specific to [[Glossary#I|infiltration]] practices. Not included in this table are those cost items that are common to all construction projects, such as mobilization, traffic control, [[Glossary#E|erosion]] and [[Glossary#S|sediment]] control, permitting, etc.
 
The table below lists the specific site components that are specific to [[Glossary#I|infiltration]] practices. Not included in this table are those cost items that are common to all construction projects, such as mobilization, traffic control, [[Glossary#E|erosion]] and [[Glossary#S|sediment]] control, permitting, etc.
  
{{:Infiltration basin cost estimate worksheet}}
+
{{:Infiltration practices cost components}}

Revision as of 00:34, 24 March 2013

The section on integrated stormwater management outlines a cost estimation method which site planners could use to compare the relative construction and maintenance costs for structural best management practices. These curves are excellent for purposes of comparison; however, it is recommended that construction and maintenance budgets should be based on site specific information. Utilizing the table below and the cost estimation worksheet, will allow designers to avoid over or under estimation of fixed costs.

The design infiltration rates

The table below lists the specific site components that are specific to infiltration practices. Not included in this table are those cost items that are common to all construction projects, such as mobilization, traffic control, erosion and sediment control, permitting, etc.

Summary of infiltration practices cost components.
Link to this table

Implementation Stage Primary Cost Components Basic Cost Estimate Other Considerations
Site Preparation Tree & plant protection Protection Cost ($/acre) * Affected Area (acre) Removal of existing structures, topsoil removal and stockpiling
Infiltration area protection Silt fence cost ($/’foot) * Perimeter of infiltration area
Clearing & grubbing Clearing Cost ($/acre) * Affected Area (acre)
Topsoil salvage Salvage Cost ($/acre) * Affected Area
Site Formation Excavation / grading X-ft Depth Excavation Cost ($/acre) * Area (acre) Soil & rock fill material, tunneling
Hauling material offsite Excavation Cost * (% of Material to be hauled away)
Structural Components Vault structure (for underground infiltration) ($/structure) Pipes, catchbasins, manholes, valves, vaults
Media (for infiltration trenches) Media cost ($/cubic yard) * filter volume (cubic yard)
Geotextile Geotextile cost ($/cy) * area of trench, including walls
inlet structure ($/structure)
Overflow structure ($/structure)
Observation well ($/structure)
Site Restoration Soil preparation Topsoil or amendment cost ($/acre) * Area (acre) Tree protection, soil amendments, seed bed preparation, trails
Seeding Seeding Cost ($/acre) * Seeded Area (acre)
Filter strip Sod cost ($/square foot) * filter strip area
Planting / transplanting Planting Cost ($/acre) * Planted Area (acre)
Annual Operation, Maintenance, and Inspection Sediment removal Removal Cost ($/acre) * Area (acre) * Frequency (1 time per 5 years) Vegetation maintenance, cleaning of structures
Debris removal Removal Cost ($/acre) * Area (acre) * Frequency (2 time per year)
Inspection Inspection Cost ($) * Inspection Frequency (6 times per year)
Mowing (for some vegetative filters) Mowing Cost ($) * Mowing Frequency (6 times per year)