m
 
(15 intermediate revisions by 2 users not shown)
Line 1: Line 1:
 
==Appendix B. Schedules==
 
==Appendix B. Schedules==
==='''Table 3:<br/>New Permittees - Schedule of permit requirements'''===
+
===<span style="color: black">'''Table 2:<br/>Existing Permittees - Schedule of permit requirements'''===
 
{| class="wikitable" style = "background: transparent;"
 
{| class="wikitable" style = "background: transparent;"
 
|-
 
|-
! style="text-align: left; background: transparent;"|'''<i>Permit requirement</i>''' !! style="text-align: left; background: transparent;"|'''<i>Schedule</i>'''
+
!style="text-align: left; background: transparent;"|'''<i>Permit requirement</i> !!style="text-align: left; background: transparent;"|'''<i>Schedule</i>
 
|-
 
|-
| '''Section 12. Stormwater Pollution Prevention Program (SWPPP)<br/>Document'''  
+
| '''Section 12. Stormwater Pollution Prevention Program (SWPPP)<br/>Document.'''
*<i>Submit the SWPPP Document completed in accordance withn<br/>Section 12<i/>
+
*<i>Submit the SWPPP Document completed in accordance with<br/>Section 12
|style= "vertical-align:bottom"|
+
|  
 
*Within 150 days after General Permit issuance<br/>date.
 
*Within 150 days after General Permit issuance<br/>date.
 
|-
 
|-
|style= "vertical-align:top"| '''Section 13. Stormwater Pollution Prevention Program (SWPPP)'''  
+
|'''Section 13. Stormwater Pollution Prevention Program (SWPPP)'''
*<i>Complete revisions to incorporate the new requirements of<br/>Sections 14 - 23 into current SWPPP.<i/>
+
*<i>Complete revisions to incorporate the new requirements of<br/>Sections 14 - 23 into current SWPPP.
|style= "vertical-align:bottom"|
+
|
 
*Within 12 months of the date General Permit<br/>coverage is extended, unless other timelines have<br/>been specifically established in the General Permit<br/>and identified below.
 
*Within 12 months of the date General Permit<br/>coverage is extended, unless other timelines have<br/>been specifically established in the General Permit<br/>and identified below.
 
|-
 
|-
| style= "vertical-align:top"| '''Section 19. Construction Site Stormwater Runoff Control'''  
+
|'''Section 19. Construction Site Stormwater Runoff Control'''
*<i>Complete revisions to Construction Site Stormwater Runoff<br/>Control program, including revisions to regulatory mechanism(s),><br/>if necessary<i/>
+
*<i>Complete revisions to Construction Site Stormwater Runoff<br/>Control program, including revisions to regulatory mechanism(s),<br/>if necessary.
*<i>When the CSW Permit is reissued, revise regulatory<br/>mechanism(s), if necessary, to be at least as stringent as the<br/>requirements for erosion, sediment, and waste controls described<br/>in the CSW Permit.<i/>
+
*<i>When the CSW Permit is reissued, revise regulatory<br/>mechanism(s), if necessary, to be at least as stringent as the<br/>requirements for erosion, sediment, and waste controls described<br/>in the CSW Permit.  
|style= "vertical-align:bottom"|
+
|
*Within 12 months of the date General Permit<br/>coverage is extended, unless other timelines have<br/>been specifically established in the General Permit<br/>and identified below.
+
*Within 12 months of the date General Permit<br/>coverage is extended.
 +
*Within 12 months of the issuance date of the CSW<br/>Permit (expected issuance date of the CSW Permit<br/>is August 1, 2023).
 +
|-
 +
|'''Section 21. Pollution Prevention/Good Housekeeping for<br/>Municipal Operations'''
 +
*<i>Conduct structural stormwater best management practice (BMP)<br/>inspections.
 +
*<i>Conduct pond and outfall inspections
 +
|
 +
*Each calendar year.
 +
*Prior to the expiration date of the General Permit.
 
|-
 
|-
| Example || Example
+
|'''Section 22. Discharges to Impaired Waters with a USEPA-<br/>Approved TMDL that includes an Applicable WLA'''
 +
*<i>Submit all information required in item 22.2.
 +
*<i>Meet requirements for applicable WLAs for bacteria, chloride,<br/>and temperature in Section 22.
 +
|
 +
*With each annual report.
 +
*Within 12 months of the date General Permit<br/>coverage is extended.
 
|-
 
|-
| Example || Example
+
|'''Section 25. Annual Assessment, Annual Reporting, and<br/>Recordkeeping'''
 +
*<i>Conduct assessment of the SWPPP.
 +
*<i>On a form provided by the Agency, submit an annual report.
 +
|
 +
*Prior to completion of each annual report.
 +
*By June 30th of each calendar year.
 +
|}
 +
 
 +
===<span style="color: black">'''Table 3:<br/>New Permittees - Schedule of permit requirements'''===
 +
{| class="wikitable" style = "background: transparent;"
 
|-
 
|-
| Example || Example
+
!style="text-align: left; background: transparent;"|'''<i>Permit requirement</i> !!style="text-align: left; background: transparent;"|'''<i>Schedule</i>
 
|-
 
|-
| Example || Example
+
| '''Section 10. New Permittee Applicants'''
 +
*<i>Submit Part 1, and Part 2 of the permit application as required<br/>by Section 12.
 +
|  
 +
*Within 18 months of written notification from the<br/>Commissioner that the MS4 meets the criteria in Minn.<br/>R. 7090.1010, subp. 1.A. or B. and General Permit coverage is<br/>required.
 
|-
 
|-
| Example || Example
+
|'''Section 13. Stormwater Pollution Prevention Program (SWPPP)'''
 +
*<i>Complete all requirements of Sections 14 - 23.
 +
|
 +
*Within 36 months of the date General Permit coverage is<br/>extended, unless other timelines have been specifically<br/>established in the General Permit and identified below; or
 +
*Within timelines established by the Commissioner in item 8.3
 
|-
 
|-
| Example || Example
+
|'''Section 14. Mapping'''
 +
*<i>Develop a storm sewer system map.
 +
|
 +
*Within 24 months of the date General Permit coverage is<br/>extended.
 
|-
 
|-
| Example || Example
+
|'''Section 18. Illicit Discharge Detection and Elimination'''
 +
*<i>Develop, implement, and enforce an Illicit Discharge Detection<br/>and Elimination Program.
 +
|
 +
*Within 12 months of the date General Permit coverage is<br/>extended.
 
|-
 
|-
| Example || Example
+
|'''Section 19. Construction Site Stormwater Runoff Control'''
 +
*<i>Develop, implement, and enforce a Construction Site<br/>Stormwater Runoff Control Program.
 +
*<i>When the CSW Permit is reissued, revise regulatory<br/>mechanism(s), if necessary, to be at least as stringent as the<br/>requirements for erosion, sediment, and waste controls described<br/>in the CSW Permit.
 +
|
 +
*Within 12 months of the date General Permit coverage is<br/>extended.
 +
*Within 12 months of the issuance date of the CSW Permit<br/>(expected issuance date of the CSW Permit is August 1, 2023).
 
|-
 
|-
| Example || Example
+
|'''Section 20. Post-Construction Stormwater Management'''
 +
*<i>Develop, implement, and enforce a Post-Construction <br/>Stormwater Management program.
 +
|
 +
*Within 24 months of the date General Permit<br/>coverage is extended.
 
|-
 
|-
| Example || Example
+
|'''Section 21. Pollution Prevention/Good Housekeeping for<br/>Municipal Operations'''
 +
*<i>Conduct structural stormwater BMP inspections.
 +
*<i>Conduct pond and outfall inspections.
 +
|
 +
*Each calendar year
 +
*Prior to the expiration date of the General Permit.
 
|-
 
|-
| Example || Example
+
|'''Section 22. Discharges to Impaired Waters with a USEPA-<br/>Approved TMDL that includes an Applicable WLA'''
 +
*<i>Submit all information required in item 22.2.
 +
*<i>Meet requirements for applicable WLAs for bacteria, chloride,<br/>and temperature in Section 22.
 +
|
 +
*With each annual report.
 +
*Within 12 months of the date General Permit coverage is<br/>extended.
 
|-
 
|-
| Example || Example
+
|'''Section 23. Alum or Ferric Chloride Phosphorus Treatment<br/>Systems (if applicable)'''
 +
*<i>Meet requirements for treatment systems in Section 23
 +
|
 +
*Within 12 months of the date General Permit coverage is<br/>extended.
 
|-
 
|-
| Example || Example
+
|'''Section 25. Annual Assessment, Annual Reporting, and<br/>Recordkeeping'''
 +
*<i>Conduct assessment of the SWPPP.
 +
*<i>On a form provided by the Agency, submit an annual report.
 +
|
 +
*Prior to completion of each annual report.
 +
*By June 30<sup>th</sup> of each calendar year.
 
|}
 
|}
 +
 +
<noinclude>
 +
[[Category:Level 2 - Regulatory/Municipal (MS4)]]
 +
</noinclude>

Latest revision as of 16:45, 22 November 2022

Appendix B. Schedules

Table 2:
Existing Permittees - Schedule of permit requirements

Permit requirement Schedule
Section 12. Stormwater Pollution Prevention Program (SWPPP)
Document.
  • Submit the SWPPP Document completed in accordance with
    Section 12
  • Within 150 days after General Permit issuance
    date.
Section 13. Stormwater Pollution Prevention Program (SWPPP)
  • Complete revisions to incorporate the new requirements of
    Sections 14 - 23 into current SWPPP.
  • Within 12 months of the date General Permit
    coverage is extended, unless other timelines have
    been specifically established in the General Permit
    and identified below.
Section 19. Construction Site Stormwater Runoff Control
  • Complete revisions to Construction Site Stormwater Runoff
    Control program, including revisions to regulatory mechanism(s),
    if necessary.
  • When the CSW Permit is reissued, revise regulatory
    mechanism(s), if necessary, to be at least as stringent as the
    requirements for erosion, sediment, and waste controls described
    in the CSW Permit.
  • Within 12 months of the date General Permit
    coverage is extended.
  • Within 12 months of the issuance date of the CSW
    Permit (expected issuance date of the CSW Permit
    is August 1, 2023).
Section 21. Pollution Prevention/Good Housekeeping for
Municipal Operations
  • Conduct structural stormwater best management practice (BMP)
    inspections.
  • Conduct pond and outfall inspections
  • Each calendar year.
  • Prior to the expiration date of the General Permit.
Section 22. Discharges to Impaired Waters with a USEPA-
Approved TMDL that includes an Applicable WLA
  • Submit all information required in item 22.2.
  • Meet requirements for applicable WLAs for bacteria, chloride,
    and temperature in Section 22.
  • With each annual report.
  • Within 12 months of the date General Permit
    coverage is extended.
Section 25. Annual Assessment, Annual Reporting, and
Recordkeeping
  • Conduct assessment of the SWPPP.
  • On a form provided by the Agency, submit an annual report.
  • Prior to completion of each annual report.
  • By June 30th of each calendar year.

Table 3:
New Permittees - Schedule of permit requirements

Permit requirement Schedule
Section 10. New Permittee Applicants
  • Submit Part 1, and Part 2 of the permit application as required
    by Section 12.
  • Within 18 months of written notification from the
    Commissioner that the MS4 meets the criteria in Minn.
    R. 7090.1010, subp. 1.A. or B. and General Permit coverage is
    required.
Section 13. Stormwater Pollution Prevention Program (SWPPP)
  • Complete all requirements of Sections 14 - 23.
  • Within 36 months of the date General Permit coverage is
    extended, unless other timelines have been specifically
    established in the General Permit and identified below; or
  • Within timelines established by the Commissioner in item 8.3
Section 14. Mapping
  • Develop a storm sewer system map.
  • Within 24 months of the date General Permit coverage is
    extended.
Section 18. Illicit Discharge Detection and Elimination
  • Develop, implement, and enforce an Illicit Discharge Detection
    and Elimination Program.
  • Within 12 months of the date General Permit coverage is
    extended.
Section 19. Construction Site Stormwater Runoff Control
  • Develop, implement, and enforce a Construction Site
    Stormwater Runoff Control Program.
  • When the CSW Permit is reissued, revise regulatory
    mechanism(s), if necessary, to be at least as stringent as the
    requirements for erosion, sediment, and waste controls described
    in the CSW Permit.
  • Within 12 months of the date General Permit coverage is
    extended.
  • Within 12 months of the issuance date of the CSW Permit
    (expected issuance date of the CSW Permit is August 1, 2023).
Section 20. Post-Construction Stormwater Management
  • Develop, implement, and enforce a Post-Construction
    Stormwater Management program.
  • Within 24 months of the date General Permit
    coverage is extended.
Section 21. Pollution Prevention/Good Housekeeping for
Municipal Operations
  • Conduct structural stormwater BMP inspections.
  • Conduct pond and outfall inspections.
  • Each calendar year
  • Prior to the expiration date of the General Permit.
Section 22. Discharges to Impaired Waters with a USEPA-
Approved TMDL that includes an Applicable WLA
  • Submit all information required in item 22.2.
  • Meet requirements for applicable WLAs for bacteria, chloride,
    and temperature in Section 22.
  • With each annual report.
  • Within 12 months of the date General Permit coverage is
    extended.
Section 23. Alum or Ferric Chloride Phosphorus Treatment
Systems (if applicable)
  • Meet requirements for treatment systems in Section 23
  • Within 12 months of the date General Permit coverage is
    extended.
Section 25. Annual Assessment, Annual Reporting, and
Recordkeeping
  • Conduct assessment of the SWPPP.
  • On a form provided by the Agency, submit an annual report.
  • Prior to completion of each annual report.
  • By June 30th of each calendar year.

This page was last edited on 22 November 2022, at 16:45.