m |
m |
||
Line 21: | Line 21: | ||
STEP 5: Enter the reporting year by using the drop down menu in column D. Columns A through C autofill. | STEP 5: Enter the reporting year by using the drop down menu in column D. Columns A through C autofill. | ||
[[file:City_a_activities1.PNG|thumb|left|alt=city_a_activities1|Step 5]] | [[file:City_a_activities1.PNG|thumb|left|alt=city_a_activities1|Step 5]] | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
STEP 6: In Column E, enter your first BMP, selecting the appropriate category from the dropdown box. Complete Column F (dropdown) if desired. For guidance, click [[Guidance for completing the TMDL reporting form#Columns Q and beyond – TMDL Project with TMDL WLAs|here]]. | STEP 6: In Column E, enter your first BMP, selecting the appropriate category from the dropdown box. Complete Column F (dropdown) if desired. For guidance, click [[Guidance for completing the TMDL reporting form#Columns Q and beyond – TMDL Project with TMDL WLAs|here]]. | ||
[[file:City_a_activities2.PNG|thumb|left|alt=city_a_activities2|Step 6]] | [[file:City_a_activities2.PNG|thumb|left|alt=city_a_activities2|Step 6]] | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
STEP 7: Complete columns H, I, J, and K if they did not autofill. These are ID number and locational coordinates for the rain garden (INF1). For guidance, click [[Guidance for completing the TMDL reporting form#Column H – BMP ID|here]]. | STEP 7: Complete columns H, I, J, and K if they did not autofill. These are ID number and locational coordinates for the rain garden (INF1). For guidance, click [[Guidance for completing the TMDL reporting form#Column H – BMP ID|here]]. | ||
[[file:City_a_activities3.PNG|thumb|left|alt=city_a_activities1|Step 7]] | [[file:City_a_activities3.PNG|thumb|left|alt=city_a_activities1|Step 7]] | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
STEP 8: Complete Columns L and M. From the dropdown in Column L select the owner/operator of the BMP. Column M autofills if you are the owner, otherwise enter the name of the owner/operator of the BMP. For guidance, click [[Guidance for completing the TMDL reporting form#Column L – Who Owns this BMP/Activity?|here]]. | STEP 8: Complete Columns L and M. From the dropdown in Column L select the owner/operator of the BMP. Column M autofills if you are the owner, otherwise enter the name of the owner/operator of the BMP. For guidance, click [[Guidance for completing the TMDL reporting form#Column L – Who Owns this BMP/Activity?|here]]. | ||
[[file:City_a_activities4.PNG|thumb|left|alt=city_a_activities1|Step 8]] | [[file:City_a_activities4.PNG|thumb|left|alt=city_a_activities1|Step 8]] | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
STEP 9: Complete Columns N and O if desired. This rain garden was installed and was operational in 2010. City A enters “2010” in Column N. No comments are added to Column O. | STEP 9: Complete Columns N and O if desired. This rain garden was installed and was operational in 2010. City A enters “2010” in Column N. No comments are added to Column O. | ||
[[file:City_a_activities5.PNG|thumb|left|alt=city_a_activities1|Step 9]] | [[file:City_a_activities5.PNG|thumb|left|alt=city_a_activities1|Step 9]] | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
STEP 10: Associate the BMP with TMDLs. City A determines that the rain garden is reducing pollutants draining to the Lake 2 Phosphorous TMDL. City A indicates this with an “X” in Column Q. For guidance, click [[Guidance for completing the TMDL reporting form#Columns Q and beyond – TMDL Project with TMDL WLAs|here]]. | STEP 10: Associate the BMP with TMDLs. City A determines that the rain garden is reducing pollutants draining to the Lake 2 Phosphorous TMDL. City A indicates this with an “X” in Column Q. For guidance, click [[Guidance for completing the TMDL reporting form#Columns Q and beyond – TMDL Project with TMDL WLAs|here]]. | ||
[[file:City_a_activities6.PNG|thumb|left|alt=city_a_activities1|Step 10]] | [[file:City_a_activities6.PNG|thumb|left|alt=city_a_activities1|Step 10]] | ||
+ | |||
+ | [[Category:Level 3 - Regulatory/Municipal (MS4)/TMDLs]] | ||
+ | [[Category:Level 2 - Regulatory/Municipal (MS4)]] |
The following is a quick guide to complete the BMPs-Activities completed tab.
STEP 1: Inventory BMPs that
STEP 2: Identify the location of your MS4 in relation to watershed boundaries and the TMDL study area
STEP 3: Plot the location of inventoried BMPs for which you have geographic locations
STEP 4: Determine from which TMDL the BMPs reduce pollutants
Example data shown for a rain garden in City A, for more details see examples.
STEP 5: Enter the reporting year by using the drop down menu in column D. Columns A through C autofill.
STEP 6: In Column E, enter your first BMP, selecting the appropriate category from the dropdown box. Complete Column F (dropdown) if desired. For guidance, click here.
STEP 7: Complete columns H, I, J, and K if they did not autofill. These are ID number and locational coordinates for the rain garden (INF1). For guidance, click here.
STEP 8: Complete Columns L and M. From the dropdown in Column L select the owner/operator of the BMP. Column M autofills if you are the owner, otherwise enter the name of the owner/operator of the BMP. For guidance, click here.
STEP 9: Complete Columns N and O if desired. This rain garden was installed and was operational in 2010. City A enters “2010” in Column N. No comments are added to Column O.
STEP 10: Associate the BMP with TMDLs. City A determines that the rain garden is reducing pollutants draining to the Lake 2 Phosphorous TMDL. City A indicates this with an “X” in Column Q. For guidance, click here.