m
m
 
(10 intermediate revisions by 2 users not shown)
Line 1: Line 1:
 +
#REDIRECT [[Construction specifications for infiltration ]]
 +
 
CADD based details for pond systems are contained in the section on [[CADD images for individual best management practices|drawings]]. The following details, with specifications, have been created for infiltration systems:
 
CADD based details for pond systems are contained in the section on [[CADD images for individual best management practices|drawings]]. The following details, with specifications, have been created for infiltration systems:
 
*infiltration basin
 
*infiltration basin
Line 28: Line 30:
 
*Weed control
 
*Weed control
 
*Watering of plant material
 
*Watering of plant material
{{alert|It is REQUIRED that infiltration systems not be excavated to final grade until the contributing drainage area has been constructed and fully stabilized.|alert-caution}}
+
{{alert|It is REQUIRED that infiltration systems not be excavated to final grade until the contributing drainage area has been constructed and fully stabilized.|alert-danger}}
  
 
===Construction sequence scheduling===
 
===Construction sequence scheduling===
Line 47: Line 49:
 
*Adherence to construction documents
 
*Adherence to construction documents
 
*Verification of physical site conditions
 
*Verification of physical site conditions
*[[Glossary#E|Erosion]] control measures installed appropriately
+
*Erosion control measures installed appropriately
 +
 
 +
<noinclude>
 +
==Related pages==
 +
*[[Overview for Infiltration trench]]
 +
*[[Types of Infiltration trench]]
 +
*[[Design criteria for Infiltration trench]]
 +
*[[Construction specifications for Infiltration trench]]
 +
*[[Operation and maintenance of Infiltration trench]]
 +
*[[Assessing the performance of infiltration trenches and basins]]
 +
*[[Cost-benefit considerations for Infiltration trench]]
 +
*[[External resources for Infiltration trench ]]
 +
*[[References for infiltration]]
 +
 
 +
[[Category:Level 3 - Best management practices/Specifications and details/Construction specifications]]
 +
</noinclude>

Latest revision as of 14:46, 11 December 2022

CADD based details for pond systems are contained in the section on drawings. The following details, with specifications, have been created for infiltration systems:

  • infiltration basin
  • infiltration trench
  • subsurface infiltration system
  • inlet/outlet structures

Construction specifications

Given that the construction of infiltration practices incorporates techniques or steps which may be considered non-standard, it is RECOMMENDED that the construction specifications include the following format and information.

Temporary erosion control

  • Installation prior to site disturbance
  • Catch basin/inlet protection
  • Use of BMP as temporary sedimentation basin

Excavation, backfill and grading

  • Timing of grading of infiltration practices (relative to total site development)
  • Use of low-impact, earth moving equipment
  • Controls to ensure site is not over-excavated
  • Restoration in the event of sediment accumulation during construction of practice
  • Gravel backfill specifications
  • Gravel filter specifications
  • Filter fabric specifications
  • Observation well specifications

Native plants, planting and transplanting

  • Site preparation of planting areas
  • Timing of native seeding and native planting
  • Weed control
  • Watering of plant material
Warning: It is REQUIRED that infiltration systems not be excavated to final grade until the contributing drainage area has been constructed and fully stabilized.

Construction sequence scheduling

  • Temporary construction access
  • Location of silt fence installation to protect BMPs and downgradient receiving waters
  • Removal and storage of excavated material
  • Installation of underground utilities
  • Rough grading
  • Seeding and mulching disturbed areas
  • Road construction
  • Final grading
  • Site stabilization
  • Installation of semi-permanent and permanent erosion control measures
  • Silt fence removal (often forgotten but an essential step)

Construction observation

  • Adherence to construction documents
  • Verification of physical site conditions
  • Erosion control measures installed appropriately