m |
m |
||
(One intermediate revision by the same user not shown) | |||
Line 18: | Line 18: | ||
*Level 3: [https://stormwaterbook.safl.umn.edu/assessment-programs/synthetic-runoff-testing Synthetic Runoff Testing] for infiltration and filtration practices. Synthetic runoff test results can be used to develop an accurate characterization of pollutant retention or removal, but can be limited by the need for an available water volume and discharge. | *Level 3: [https://stormwaterbook.safl.umn.edu/assessment-programs/synthetic-runoff-testing Synthetic Runoff Testing] for infiltration and filtration practices. Synthetic runoff test results can be used to develop an accurate characterization of pollutant retention or removal, but can be limited by the need for an available water volume and discharge. | ||
*Level 4: [https://stormwaterbook.safl.umn.edu/assessment-programs/monitoring Monitoring for infiltration] or filtration practices | *Level 4: [https://stormwaterbook.safl.umn.edu/assessment-programs/monitoring Monitoring for infiltration] or filtration practices | ||
+ | |||
+ | The adjacent table summarizes the four levels of assessment. | ||
+ | |||
+ | {{:Levels of assessment for stormwater best management practices (stormwater control measures)}} | ||
Level 1 activities do not produce numerical performance data that could be used to obtain a stormwater management <span title="The stormwater runoff volume or pollutant reduction achieved toward meeting a runoff volume or water quality goal."> [https://stormwater.pca.state.mn.us/index.php?title=Overview_of_stormwater_credits '''credit (stormwater credit)''']</span>. BMP owners and operators who are interested in using data obtained from Levels 2 and 3 should consult with the MPCA or other regulatory agency to determine if the results are appropriate for credit calculations. Level 4, monitoring, is the method most frequently used for assessment of the performance of a BMP. | Level 1 activities do not produce numerical performance data that could be used to obtain a stormwater management <span title="The stormwater runoff volume or pollutant reduction achieved toward meeting a runoff volume or water quality goal."> [https://stormwater.pca.state.mn.us/index.php?title=Overview_of_stormwater_credits '''credit (stormwater credit)''']</span>. BMP owners and operators who are interested in using data obtained from Levels 2 and 3 should consult with the MPCA or other regulatory agency to determine if the results are appropriate for credit calculations. Level 4, monitoring, is the method most frequently used for assessment of the performance of a BMP. | ||
Line 59: | Line 63: | ||
[[Category:Level 3 - Best management practices/Specifications and details/Assessing performance]] | [[Category:Level 3 - Best management practices/Specifications and details/Assessing performance]] | ||
− | |||
[[Category:Level 3 - Best management practices/Structural practices/Permeable pavement]] | [[Category:Level 3 - Best management practices/Structural practices/Permeable pavement]] | ||
</noinclude> | </noinclude> |
Assessing the performance of permeable pavement includes a review of its condition and performance. A spring maintenance inspection is recommended and cleanup conducted as needed. The following are recommended annual maintenance inspection points for permeable pavements.
An online manual for assessing BMP treatment performance was developed in 2010 by Andrew Erickson, Peter Weiss, and John Gulliver from the University of Minnesota and St. Anthony Falls Hydraulic Laboratory. The manual advises on a four-level process to assess the performance of a Best Management Practice.
The adjacent table summarizes the four levels of assessment.
Levels of assessment for stormwater best management practices (stormwater control measures)
Link to this table
Level | Title | Objectives | Relative | Typical elapsed time | Advantages | Disadvantages |
---|---|---|---|---|---|---|
1 | Visual Inspection | Determine if stormwater BMP is malfunctioning | 1 | 1 day | Quick, inexpensive | Limited knowledge gained |
2 | Capacity testing | Determine infiltration or sedimentation capacity and rates | 10 | 1 week | Less expensive, no equipment left in field | Limited to infiltration and sedimentation capacity/rates, uncertainties can be substantial |
3 | Simulated runoff testing | Determine infiltration rates, capacity, and pollutant removal performance | 10-100 | 1 week to 1 month | Controlled experiments, more accurate with fewer tests required for statistical significance as compared to monitoring, no equipment left in field | Cannot be used without sufficient water supply, limited scope |
4 | Monitoring | Determine infiltration rates, capacity, and pollutant removal performance | 400 | 14 months | Most comprehensive. Assess stormwater BMP within watershed without modeling | Uncertainty in results due to lack of control and number of variables, equipment left in field |
Level 1 activities do not produce numerical performance data that could be used to obtain a stormwater management credit (stormwater credit). BMP owners and operators who are interested in using data obtained from Levels 2 and 3 should consult with the MPCA or other regulatory agency to determine if the results are appropriate for credit calculations. Level 4, monitoring, is the method most frequently used for assessment of the performance of a BMP.
Use these links to obtain detailed information on the following topics related to BMP performance monitoring:
Additional information on designing a monitoring network and performing field monitoring are found at this link.