The general stormwater permit for construction activity contains many requirements that must be considered during the planning phase of a construction project. Decisions made during planning may make the difference between the project requiring a more onerous individual permit instead of the general permit. | The general stormwater permit for construction activity contains many requirements that must be considered during the planning phase of a construction project. Decisions made during planning may make the difference between the project requiring a more onerous individual permit instead of the general permit. | ||
− | + | *[https://www.pca.state.mn.us/sites/default/files/wq-strm2-68a.pdf Minnesota NPDES/SDS Construction Stormwater General Permit] | |
====Step 5. Identify waters that have the potential to receive a discharge of stormwater runoff or discharge from a permanent stormwater management system==== | ====Step 5. Identify waters that have the potential to receive a discharge of stormwater runoff or discharge from a permanent stormwater management system==== | ||
− | # | + | #Are Special Waters," as identified in Appendix A of the General Stormwater Permit for Construction Activity (MNR100001), located within one mile of the construction site? Use the Special Waters Search map system or the Special Waters Document and a quad map to identify your construction site and prepare a list of all the special waters located '''within one mile of the site boundary.''' |
##"[https://stormwater.pca.state.mn.us/index.php?title=Guidance_for_using_the_Stormwater_Special_and_impaired_waters_search_tool Special Waters Search]: This is an electronic map tool using Geographic Information Systems (GIS) technology. Find the construction site location, draw the site boundaries and create a list of special waters. (Note: This is best viewed using Internet Explorer 5.0 or higher or Netscape 6.0 or higher, with pop-up blockers disabled and screen resolution set to 1024x768 or higher.) | ##"[https://stormwater.pca.state.mn.us/index.php?title=Guidance_for_using_the_Stormwater_Special_and_impaired_waters_search_tool Special Waters Search]: This is an electronic map tool using Geographic Information Systems (GIS) technology. Find the construction site location, draw the site boundaries and create a list of special waters. (Note: This is best viewed using Internet Explorer 5.0 or higher or Netscape 6.0 or higher, with pop-up blockers disabled and screen resolution set to 1024x768 or higher.) | ||
##[https://www.pca.state.mn.us/sites/default/files/wq-strm1-05.pdf Special Waters Document] | ##[https://www.pca.state.mn.us/sites/default/files/wq-strm1-05.pdf Special Waters Document] | ||
Line 52: | Line 52: | ||
##[https://www3.epa.gov/npdes/pubs/cgp2012_appendixe.pdf EPA Appendix E – Historic Property Screening Process] | ##[https://www3.epa.gov/npdes/pubs/cgp2012_appendixe.pdf EPA Appendix E – Historic Property Screening Process] | ||
#MPCA Calcareous fens. Calcareous fens are a very rare and unique type of wetland that can contain a number of rare wetland plant species. These fens are dependent upon water chemistry and hydrologic conditions. Minnesota rules protect these unique and fragile wetland resources. If runoff from the site discharges to a calcareous fen as listed in Minn. R. 7050.0180, subp. 6.b., additional permit requirements apply. Use the Special Waters Search and quad map to identify your construction site and prepare a list of all the calcareous fens that have the potential to be impacted by discharges from the site. | #MPCA Calcareous fens. Calcareous fens are a very rare and unique type of wetland that can contain a number of rare wetland plant species. These fens are dependent upon water chemistry and hydrologic conditions. Minnesota rules protect these unique and fragile wetland resources. If runoff from the site discharges to a calcareous fen as listed in Minn. R. 7050.0180, subp. 6.b., additional permit requirements apply. Use the Special Waters Search and quad map to identify your construction site and prepare a list of all the calcareous fens that have the potential to be impacted by discharges from the site. | ||
− | ##[ | + | ##[https://stormwater.pca.state.mn.us/index.php?title=Guidance_for_using_the_Stormwater_Special_and_impaired_waters_search_tool Special Waters Search]: This is an electronic map tool using Geographic Information Systems (GIS) technology. Use this tool to identify your construction site and prepare a list of all the calcareous fens that have the potential to be impacted by discharges from the site. (Note: This is best viewed using Internet Explorer 5.0 or higher or Netscape 6.0 or higher, with pop-up blockers disabled and screen resolution set to 1024x768 or higher.) |
#DNR Calcareous Fens. The Minnesota Department of Natural Resources (DNR) works closely with counties and citizens to identify sensitive and rare habitat resources. Calcareous fens identified through these efforts are compiled on the DNR List of Known Calcareous Fen Sites. The DNR Calcareous Fens are fens that appear on this list but are not yet listed by the MPCA as Outstanding Resource Value Waters. Construction that results in a discharge to this category of fen is covered under the general NPDES/SDS Construction Stormwater Permit, but must also meet the Wetland Conservation Act and wetland protection rules administered by the DNR. | #DNR Calcareous Fens. The Minnesota Department of Natural Resources (DNR) works closely with counties and citizens to identify sensitive and rare habitat resources. Calcareous fens identified through these efforts are compiled on the DNR List of Known Calcareous Fen Sites. The DNR Calcareous Fens are fens that appear on this list but are not yet listed by the MPCA as Outstanding Resource Value Waters. Construction that results in a discharge to this category of fen is covered under the general NPDES/SDS Construction Stormwater Permit, but must also meet the Wetland Conservation Act and wetland protection rules administered by the DNR. | ||
− | ##[ | + | ##[https://stormwater.pca.state.mn.us/index.php?title=Guidance_for_using_the_Stormwater_Special_and_impaired_waters_search_tool Special Waters Search] This is an electronic map tool using Geographic Information Systems (GIS) technology. Use this tool to identify your construction site and prepare a list of all the calcareous fens that have the potential to be impacted by discharges from the site. Calcareous fens are identified on the Special Waters Search by the section in which the fen is located. |
###Note: This is best viewed using Internet Explorer 5.0 or higher or Netscape 6.0 or higher, with pop-up blockers disabled and screen resolution set to 1024x768 or higher. | ###Note: This is best viewed using Internet Explorer 5.0 or higher or Netscape 6.0 or higher, with pop-up blockers disabled and screen resolution set to 1024x768 or higher. | ||
##For a more detailed location, see Office spreadsheet icon List of Known Calcareous Fen Sites or | ##For a more detailed location, see Office spreadsheet icon List of Known Calcareous Fen Sites or | ||
##Contact the appropriate DNR Regional Hydrologists: | ##Contact the appropriate DNR Regional Hydrologists: | ||
− | ### | + | ###Northwest Region (Becker, Beltrami, Cass, Clay, Clearwater, Douglas, Grant, Hubbard, Kittson, Lake of the Woods, Mahnomen, Marshall, Norman, Otter Tail, Pennington, Polk, Pope, Red Lake, Roseau, Stevens, Traverse, Todd, Wadena and Wilkin counties) Larry Kramka 218-755-3973. |
###Northeast Region (Aitkin, Carlton , Cook, Crow Wing, Itasca , Koochiching, Lake , Pine and St. Louis counties) Dan Retka 218-327-4416. | ###Northeast Region (Aitkin, Carlton , Cook, Crow Wing, Itasca , Koochiching, Lake , Pine and St. Louis counties) Dan Retka 218-327-4416. | ||
###Central Region (Anoka, Benton, Carver, Chisago, Dakota, Hennepin, Isanti, Kanabec, Mille Lacs, Morrison, Ramsey, Scott, Sherburne, Stearns, Washington and Wright counties) Dale Homuth 651-772-7910. | ###Central Region (Anoka, Benton, Carver, Chisago, Dakota, Hennepin, Isanti, Kanabec, Mille Lacs, Morrison, Ramsey, Scott, Sherburne, Stearns, Washington and Wright counties) Dale Homuth 651-772-7910. | ||
###Southern Region (Big Stone, Blue Earth, Brown, Chippewa, Cottonwood, Dodge, Faribault, Fillmore, Freeborn, Goodhue, Houston, Jackson, Kandiyohi, Lac Qui Parle, Le Sueur, Lincoln, Lyon, Martin, McLeod, Meeker, Mower, Murray, Nicollet, Nobles, Olmsted, Pipestone, Redwood, Renville, Rice, Rock, Sibley, Steele, Swift, Wabasha, Waseca, Watonwan, Winona and Yellow Medicine counties) Dave Leuthe 507-359-6053. | ###Southern Region (Big Stone, Blue Earth, Brown, Chippewa, Cottonwood, Dodge, Faribault, Fillmore, Freeborn, Goodhue, Houston, Jackson, Kandiyohi, Lac Qui Parle, Le Sueur, Lincoln, Lyon, Martin, McLeod, Meeker, Mower, Murray, Nicollet, Nobles, Olmsted, Pipestone, Redwood, Renville, Rice, Rock, Sibley, Steele, Swift, Wabasha, Waseca, Watonwan, Winona and Yellow Medicine counties) Dave Leuthe 507-359-6053. | ||
− | # | + | #For more information on the Wetland Conservation Act requirements, contact the [https://bwsr.state.mn.us/ Board of Water and Soil Conservation] 651-296-3767. |
#[http://www.dnr.state.mn.us/waters/watermgmt_section/pwpermits/applications.html DNR permits and the Wetland Conservation Act information] | #[http://www.dnr.state.mn.us/waters/watermgmt_section/pwpermits/applications.html DNR permits and the Wetland Conservation Act information] | ||
Line 83: | Line 83: | ||
An impaired water for phosphorus, turbidity, dissolved oxygen, or biotic impairment: | An impaired water for phosphorus, turbidity, dissolved oxygen, or biotic impairment: | ||
− | # | + | #will receive a discharge as a result of the construction project '''and''' |
##has an approved TMDL with an Approved Waste Load Allocation '''or''' | ##has an approved TMDL with an Approved Waste Load Allocation '''or''' | ||
##has no approved TMDL or has an approved TMDL but no Waste Load Allocation? | ##has no approved TMDL or has an approved TMDL but no Waste Load Allocation? | ||
Line 93: | Line 93: | ||
[https://rsp.pca.state.mn.us/TEMPO_RSP/Orchestrate.do?initiate=true Online Stormwater Permit Application]. Gather the following information before entering MPCA Online Services to apply for a construction stormwater permit. Incomplete applications cannot be saved or processed. | [https://rsp.pca.state.mn.us/TEMPO_RSP/Orchestrate.do?initiate=true Online Stormwater Permit Application]. Gather the following information before entering MPCA Online Services to apply for a construction stormwater permit. Incomplete applications cannot be saved or processed. | ||
− | *Owner/Permittee Information | + | *Owner/Permittee Information |
+ | **Firm name | ||
**Business type | **Business type | ||
**Full name | **Full name | ||
Line 103: | Line 104: | ||
**Email address | **Email address | ||
**Business phone | **Business phone | ||
− | *Contractor/Permittee Information | + | *Contractor/Permittee Information |
+ | **Firm name | ||
**Business type | **Business type | ||
**Full name | **Full name | ||
Line 109: | Line 111: | ||
**Business phone | **Business phone | ||
**Complete mailing address | **Complete mailing address | ||
− | *Routine Contact for Contractor/Permittee Information | + | *Routine Contact for Contractor/Permittee Information |
+ | **Full name | ||
**Email address | **Email address | ||
**Business phone | **Business phone | ||
− | *Third Party/Permittee Information | + | *Third Party/Permittee Information |
+ | **Firm name | ||
**Business type | **Business type | ||
**Full name | **Full name | ||
Line 133: | Line 137: | ||
**Existing area of impervious surface | **Existing area of impervious surface | ||
**Post construction area or impervious surface | **Post construction area or impervious surface | ||
− | *Permanent Stormwater Management | + | *Permanent Stormwater Management |
+ | **Exempt/Not feasible, Exempt/Proximity, Exempt/Right of Way, Infiltration/Filtration, Regional Ponding or Wet Sedimentation | ||
*Water Bodies (within one mile of project) | *Water Bodies (within one mile of project) | ||
**Water body ID | **Water body ID | ||
Line 156: | Line 161: | ||
For projects that will disturb 50 acres or more and have a discharge point on the project that is within one mile of, and flows to, as special or impaired, or applicants that do not have internet access: | For projects that will disturb 50 acres or more and have a discharge point on the project that is within one mile of, and flows to, as special or impaired, or applicants that do not have internet access: | ||
− | Call the MPCA at 651-757-2119 or 800-657-3804 or email csw.pca@state.mn.us to obtain a Submittal Number and obtain a copy of the permit application. | + | Call the MPCA at 651-757-2119 or 800-657-3804 or email csw.pca@state.mn.us to obtain a Submittal Number and obtain a copy of the permit application. ''If the Submittal Number is not included with the paper permit application, the application will be considered incomplete.'' |
====Step 11. Submit completed application form along with the $400 application fee to the MPCA.==== | ====Step 11. Submit completed application form along with the $400 application fee to the MPCA.==== | ||
Submittal deadlines: | Submittal deadlines: | ||
− | + | *Projects requiring an individual NPDES/SDS Construction Stormwater Permit - 180 days before the construction start date. | |
− | + | *Projects disturbing 50 acres or more and have a discharge point on the project that is within one mile of, and flows to, a special water or an impaired water - 30 days before the construction start date submit application and SWPPP. | |
− | + | *All other projects - 7 days before the construction start date. | |
====Step 12. Begin construction.==== | ====Step 12. Begin construction.==== | ||
When is permit coverage granted and construction can begin? | When is permit coverage granted and construction can begin? | ||
− | + | *Projects disturbing 50 acres or more and have a discharge point on the project that is within one mile of, and flows to, a special water or an impaired water - 30 days after the postmarked date of the completed application unless notified in writing that the SWPPP does not meet the general permit requirements. | |
− | + | *Projects requiring an individual NPDES/SDS construction stormwater permit - After process including permit development, public input, and permit issuance has been completed. | |
− | + | *All other projects - 7 days after submitting the complete online application or 7 days after the postmarked date of the completed application form. | |
[[Category:Level 2 - Regulatory/Construction (CSW)]] | [[Category:Level 2 - Regulatory/Construction (CSW)]] |
Owners/operators of construction activity must complete several steps before completing a permit application and beginning construction. These steps also help owners/operators determine their eligibility for coverage under the general permit.
If you have comments, feedback and/or questions, please see the list of construction stormwater program contacts.
Where will the construction occur and what will the project involve? Identifying the construction site boundaries is important to determining which environmental resources may be at risk of being impacted by the project. Identify opportunities to phase the project so that vegetation will remain in those areas that will not have construction activity at the start of the project. Construction phasing can minimize or eliminate negative environmental impacts from the project.
The latitude and longitude can be obtained with Bing Maps during the online application process, a GPS unit, using a USGS topographic map (provide scale), or by using any of a number of mobile phone applications.
Contact other state and federal agencies and local units of government to determine what permits are required in addition to the National Pollutant Discharge Elimination System (NPDES) and State Disposal System (SDS) permit issued by the Minnesota Pollution Control Agency (MPCA).
Contact the Minnesota Environmental Quality Board, the appropriate state agency or local unit of government to determine if the proposed project meets or exceeds the thresholds outlined in the state environmental review rules (MN. Rules Chapter 4410.) Development of an Environmental Assessment Worksheet (EAW) may be required for the project prior to the issuance of any permits and before construction activity can begin.
The general stormwater permit for construction activity contains many requirements that must be considered during the planning phase of a construction project. Decisions made during planning may make the difference between the project requiring a more onerous individual permit instead of the general permit.
The following list identifies protected resources in Minnesota.
Develop a SWPPP following the requirements of the permit. All waters located within one mile (aerial radius measurement) of the construction site that have the potential to receive a discharge from the site must be identified on the site map component of the SWPPP. Be sure to include any additional requirements needed for discharges to special waters.
Check waters list in Steps 5A-C and 6C to determine which special waters, impaired waters and calcareous fens have a potential to receive a discharge after considering water flow and modifications to the construction plans made for the purpose of preventing water resource impacts. Discharges of concern for calcareous fens are direct discharges or an indirect discharge to the fen from the construction site within one mile.
Keep the list of waters that will receive discharges from the construction site. This information is required on the permit application form.
If special waters will receive a discharge within one mile of the construction site (identified in Steps 5A and 8) and the requirements (located in Appendix A of the general permit) for these discharges will not be fulfilled.
You will need an individual NPDES/SDS Construction Stormwater Permit. Contact the front desk (651-296-6300 or 800-657-3864) and ask for the Stormwater Policy and Technical Assistance Unit Lead.
An impaired water for phosphorus, turbidity, dissolved oxygen, or biotic impairment:
If yes - you must apply for an individual permit. Contact the front desk (651-296-6300 or 800-657-3864) and ask for the Stormwater Policy and Technical Assistance Unit Lead.
Online Stormwater Permit Application. Gather the following information before entering MPCA Online Services to apply for a construction stormwater permit. Incomplete applications cannot be saved or processed.
For projects that will disturb 50 acres or more and have a discharge point on the project that is within one mile of, and flows to, as special or impaired, or applicants that do not have internet access:
Call the MPCA at 651-757-2119 or 800-657-3804 or email csw.pca@state.mn.us to obtain a Submittal Number and obtain a copy of the permit application. If the Submittal Number is not included with the paper permit application, the application will be considered incomplete.
Submittal deadlines:
When is permit coverage granted and construction can begin?