m (→1.5) |
m (2023 permit) |
||
(14 intermediate revisions by 2 users not shown) | |||
Line 1: | Line 1: | ||
− | |||
− | |||
==SECTION 1 PERMIT COVERAGE== | ==SECTION 1 PERMIT COVERAGE== | ||
===1.1=== | ===1.1=== | ||
− | <big>Permit Coverage. | + | <big>Permit Coverage.</big> |
===1.2=== | ===1.2=== | ||
− | <big>This permit is required for [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.6 construction activity] that results in land disturbance of equal to or greater than one (1) acre or if a project is part of a [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.5 common plan of development or sale] that ultimately will disturb greater than one (1) acre, and authorizes, subject to the terms and conditions of this permit, the discharge of stormwater associated with construction activity. | + | <big>This permit is required for [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.6 construction activity] that results in land disturbance of equal to or greater than one (1) acre or if a [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.24 project] is part of a [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.5 common plan of development or sale] that ultimately will disturb greater than one (1) acre, and authorizes, subject to the terms and conditions of this permit, the discharge of [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.31 stormwater] associated with construction activity.</big> |
===1.3=== | ===1.3=== | ||
− | <big>Construction activity covered by this permit cannot commence until coverage under this permit is effective as described in item [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_3_Application_and_Coverage_Effective_Date#3.3 3.3] through [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_3_Application_and_Coverage_Effective_Date#3.4 3.4] or, if applicable, until the Minnesota Pollution Control Agency (MPCA) has issued an individual National Pollutant Discharge Elimination System (NPDES)/State Disposal System (SDS) construction stormwater permit for the project. | + | <big>Construction activity covered by this permit cannot commence until coverage under this permit is effective as described in item [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_3_Application_and_Coverage_Effective_Date#3.3 3.3] through [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_3_Application_and_Coverage_Effective_Date#3.4 3.4] or, if applicable, until the Minnesota Pollution Control Agency (MPCA) has issued an individual National Pollutant Discharge Elimination System ([https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.16 NPDES])/State Disposal System (SDS) construction stormwater permit for the project.</big> |
===1.4=== | ===1.4=== | ||
− | <big>This permit covers all areas of the State of Minnesota except land wholly within the boundaries of a federally recognized Indian Reservation owned by a tribe or a tribal member or land held in trust by the federal government for a tribe or tribal member. | + | <big>This permit covers all areas of the State of Minnesota except land wholly within the boundaries of a federally recognized Indian Reservation owned by a tribe or a tribal member or land held in trust by the federal government for a tribe or tribal member.</big> |
===1.5=== | ===1.5=== | ||
− | <big>Coverage under this permit is not required when all stormwater from construction activity is routed directly to and treated by a "treatment works," as defined in [https://www.revisor.mn.gov/statutes/cite/115.01 Minn. Stat. Sect. 115.01, subd. 21], operated under an individual NPDES/SDS permit with a Total Suspended Solids (TSS) effluent limit. | + | <big>Coverage under this permit is not required when all stormwater from construction activity is routed directly to and treated by a "treatment works," as defined in [https://www.revisor.mn.gov/statutes/cite/115.01 Minn. Stat. Sect. 115.01, subd. 21], operated under an individual NPDES/SDS permit with a Total Suspended Solids (TSS) effluent limit. </big> |
===1.6=== | ===1.6=== | ||
− | <big>This permit covers ongoing projects covered under any previous construction stormwater permit that are not complete on the issuance date of this permit. Permittees must either remain in compliance with the previous permit and terminate coverage within 18 months of the issuance date of this permit or comply with this permit, including updating the Stormwater Pollution Prevention Plan (SWPPP), within the 18-month period. Permittees of previously permitted projects are not required to incorporate any additional requirements regarding the permanent stormwater treatment system included in this reissued permit. | + | <big>This permit covers ongoing projects covered under any previous construction stormwater permit that are not complete on the issuance date of this permit. [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.23 Permittees] must either remain in compliance with the previous permit and terminate coverage within 18 months of the issuance date of this permit or comply with this permit, including updating the [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.33 Stormwater Pollution Prevention Plan (SWPPP)], within the 18-month period. Permittees of previously permitted projects are not required to incorporate any additional requirements regarding the permanent stormwater treatment system included in this reissued permit.</big> |
− | </big> | ||
===1.7=== | ===1.7=== | ||
− | <big>Coverage for projects that extend beyond the expiration date of this permit remains effective for a grace period | + | <big>Coverage for projects that extend beyond the expiration date of this permit remains effective for a grace period of 18 months. If Permittees cannot complete projects during the grace period, the MPCA will extend coverage under the next permit and permittees must comply with the requirements of the new permit including updating the SWPPP. Permittees are not required to follow changes to the permanent stormwater treatment section of the next permit.</big> |
+ | |||
+ | <noinclude> | ||
+ | [[Category:Level 2 - Regulatory/Construction (CSW)]] | ||
+ | </noinclude> |
Permit Coverage.
This permit is required for construction activity that results in land disturbance of equal to or greater than one (1) acre or if a project is part of a common plan of development or sale that ultimately will disturb greater than one (1) acre, and authorizes, subject to the terms and conditions of this permit, the discharge of stormwater associated with construction activity.
Construction activity covered by this permit cannot commence until coverage under this permit is effective as described in item 3.3 through 3.4 or, if applicable, until the Minnesota Pollution Control Agency (MPCA) has issued an individual National Pollutant Discharge Elimination System (NPDES)/State Disposal System (SDS) construction stormwater permit for the project.
This permit covers all areas of the State of Minnesota except land wholly within the boundaries of a federally recognized Indian Reservation owned by a tribe or a tribal member or land held in trust by the federal government for a tribe or tribal member.
Coverage under this permit is not required when all stormwater from construction activity is routed directly to and treated by a "treatment works," as defined in Minn. Stat. Sect. 115.01, subd. 21, operated under an individual NPDES/SDS permit with a Total Suspended Solids (TSS) effluent limit.
This permit covers ongoing projects covered under any previous construction stormwater permit that are not complete on the issuance date of this permit. Permittees must either remain in compliance with the previous permit and terminate coverage within 18 months of the issuance date of this permit or comply with this permit, including updating the Stormwater Pollution Prevention Plan (SWPPP), within the 18-month period. Permittees of previously permitted projects are not required to incorporate any additional requirements regarding the permanent stormwater treatment system included in this reissued permit.
Coverage for projects that extend beyond the expiration date of this permit remains effective for a grace period of 18 months. If Permittees cannot complete projects during the grace period, the MPCA will extend coverage under the next permit and permittees must comply with the requirements of the new permit including updating the SWPPP. Permittees are not required to follow changes to the permanent stormwater treatment section of the next permit.
This page was last edited on 2 August 2023, at 20:59.