m (1 revision) |
|
(No difference)
|
Maintenance is necessary for a stormwater pond to operate as designed on a long-term basis. The pollutant removal, channel protection, and flood control capabilities of ponds will decrease if:
Pond maintenance activities range in terms of the level of effort and expertise required to perform them. Routine pond and wetland maintenance, such as mowing and removing debris or trash, is needed multiple times each year. Owners may consider an “adopt-a-pond” program in which properly trained citizen volunteers perform basic landscape maintenance activities (the City of Plymouth, for example, has instituted such a program). More significant maintenance such as removing accumulated sediment is needed less frequently, but requires more skilled labor and special equipment. Inspection and repair of critical structural features such as embankments and risers, needs to be performed by a qualified professional (e.g., structural engineer) that has experience in the construction, inspection, and repair of these features.
Implicit in the design guidance in the previous sections, many design elements of pond systems can minimize the maintenance burden and maintain pollutant removal efficiency. Key maintenance considerations are providing access for inspection and maintenance, and designing all outlets and the principal spillway to minimize clogging. Providing easy access (typically 8 feet wide) to all pond components for routine maintenance is Required.
Stormwater ponds can be designed, constructed and maintained to minimize the likelihood of being desirable habitat for mosquito populations. Designs that incorporate constant inflows and outflows, habitat for natural predators, and constant permanent pool elevations limit the conditions typical of mosquito breeding habitat (see also Chapter 6 discussion on mosquito control).
The construction phase is another critical step where O&M issues can be minimized or avoided.
Inspections during construction are needed to ensure that the practice is built in accordance with the approved design standards and specifications. Detailed inspection checklists should be used that include sign-offs by qualified individuals at critical stages of construction, to ensure that the contractor’s interpretation of the plan is acceptable to the professional designer. An example construction phase inspection checklist is provided in Appendix D.
It is Highly Recommended that the O&M plan include a provision to lower the level of the permanent pool in the late fall, to provide additional retention storage for snowmelt runoff and ensure that some permanent pool storage is available above the ice (the permanent pool should not be completely eliminated nor allowed to freeze through completely).
Some important post construction maintenance considerations are provided below. A more detailed checklist of maintenance activities and associated schedules is provided in Appendix D. More detailed maintenance guidance can be found in the Pond and Wetland Maintenance Guidebook (CWP, 2004).
The next section in the chapter addressing stormwater ponds is Monitoring. To proceed to that section, click here.
To return to the previous section, click here.