m |
m |
||
(3 intermediate revisions by the same user not shown) | |||
Line 107: | Line 107: | ||
<td></td> | <td></td> | ||
<td></td> | <td></td> | ||
− | <tr> | + | </tr> |
<tr> | <tr> | ||
<th colspan=3>3. Structural Components</th> | <th colspan=3>3. Structural Components</th> | ||
Line 203: | Line 203: | ||
<noinclude> | <noinclude> | ||
− | [[ | + | [[Category:Level 3 - General information, reference, tables, images, and archives/Tables/Checklist]] |
+ | [[Category:Level 3 - General information, reference, tables, images, and archives/Tables/Bioretention]] | ||
</noinclude> | </noinclude> |
Infiltration practices construction inspection checklist.
Link to this table
To access an Excel version of form (for field use), click here.
Project: | ||
Location: | ||
Site Status: | ||
Date: | ||
Time: | ||
Inspector: | ||
Construction Sequence | Satisfactory / Unsatisfactory | Comments |
---|---|---|
1. Pre-Construction | ||
Pre-construction meeting | ||
Runoff diverted (Note type of bypass) | ||
Facility area cleared | ||
Soil tested for permeability | ||
Soil tested for phosphorus content (include test method) | ||
Verify site was not overdug | ||
Project benchmark near site | ||
Facility location staked out | ||
Temporary erosion and sediment protection properly installed | ||
2. Excavation | ||
Lateral slopes completely level | ||
Soils not compacted during excavation | ||
Longitudinal slopes within design range | ||
Stockpile location not adjacent to excavation area and stabilized with vegetation and/ or silt fence | ||
Verify stockpile is not causing compaction and that it is not eroding | ||
Was underlying soil ripped or loosened | ||
3. Structural Components | ||
Stone diaphragm installed per plans | ||
Outlets installed pre plans | ||
Underdrain installed to grade | ||
Pretreatment devices installed per plans | ||
Soil bed composition and texture conforms to specifications | ||
4. Vegetation | ||
Complies with planting specs | ||
Topsoil complies with specs in composition and placement | ||
Soil properly stabilized for permanent erosion control | ||
5. Final Inspection | ||
Dimensions per plans | ||
Pre-treatment operational | ||
Inlet/outlet operational | ||
Soil/ filter bed permeability verified | ||
Effective stand of vegetation stabilized | ||
Construction generated sediments removed | ||
Contributing watershed stabilized before flow is diverted to the practice | ||
Comments: | ||
Actions to be taken: |
This page was last edited on 4 August 2022, at 17:21.