Unit costs related to sediment traps and basins
Link to this table

Bid item Item description Units Average price
2573602/00010 Temporary sediment trap each $605.00
2106501/00010 Excavation – common cubic yards $5.60
2106607/00020 Excavation – subgrade cubic yards $9.59
2106523/00060 Common embankment (CV) cubic yards $2.18
2106521/00070 Granular embankment (CV) cubic yards $8.51