m
m
 
(3 intermediate revisions by the same user not shown)
Line 1: Line 1:
<font size=3>'''Unit costs related to [https://stormwater.pca.state.mn.us/index.php?title=Unit_costs_related_to_sediment_traps_and_basins  sediment traps and basins]'''</font size><br>
+
<font size=3>'''Unit costs related to sediment traps and basins'''</font size><br>
 
Link to this [[Unit costs related to sediment traps and basins|table]]
 
Link to this [[Unit costs related to sediment traps and basins|table]]
  
Line 41: Line 41:
 
</table>
 
</table>
  
[[category:table]]
+
<noinclude>
 +
[[Category:Level 3 - General information, reference, tables, images, and archives/Tables/Sediment control]]
 +
</noinclude>

Latest revision as of 18:17, 27 December 2022

Unit costs related to sediment traps and basins
Link to this table

Bid item Item description Units Average price
2573602/00010 Temporary sediment trap each $605.00
2106501/00010 Excavation – common cubic yards $5.60
2106607/00020 Excavation – subgrade cubic yards $9.59
2106523/00060 Common embankment (CV) cubic yards $2.18
2106521/00070 Granular embankment (CV) cubic yards $8.51

This page was last edited on 27 December 2022, at 18:17.