+ | [[file:Examples of filtration practices 2.png|thumb|200px|alt=excample schematics of filtration practices|<font size=3>Example filtration practices having underdrains: a) biofiltration; b) permeable pavement; c) sand filter. (Source: CDM Smith).</font size>]] | ||
+ | |||
The following are ''RECOMMENDED'' for infiltration practices with <span title="An underground drain or trench with openings through which the water may percolate from the soil or ground above"> '''underdrains'''</span>. | The following are ''RECOMMENDED'' for infiltration practices with <span title="An underground drain or trench with openings through which the water may percolate from the soil or ground above"> '''underdrains'''</span>. | ||
*The minimum pipe diameter is 4 inches. | *The minimum pipe diameter is 4 inches. | ||
Line 16: | Line 18: | ||
The procedure to size underdrains is typically determined by the project engineer. An example for sizing underdrains is found in the [https://deq.nc.gov/about/divisions/energy-mineral-and-land-resources/stormwater/stormwater-program/stormwater-design North Carolina Department of Environment and Natural Resources Stormwater BMP Manual]. Underdrain spacing can be calculated using the following spreadsheet, which utilizes the vanSchilfgaarde Equation. The spreadsheet includes an example calculation. | The procedure to size underdrains is typically determined by the project engineer. An example for sizing underdrains is found in the [https://deq.nc.gov/about/divisions/energy-mineral-and-land-resources/stormwater/stormwater-program/stormwater-design North Carolina Department of Environment and Natural Resources Stormwater BMP Manual]. Underdrain spacing can be calculated using the following spreadsheet, which utilizes the vanSchilfgaarde Equation. The spreadsheet includes an example calculation. | ||
[[file:Underdrain spacing calculation.xlsx]] | [[file:Underdrain spacing calculation.xlsx]] | ||
+ | |||
+ | [[Category:Level 3 - Best management practices/Structural practices/Infiltration (trench/basin)]] | ||
+ | [[Category:Level 3 - Best management practices/Specifications and details/Design criteria]] |
The following are RECOMMENDED for infiltration practices with underdrains.
The procedure to size underdrains is typically determined by the project engineer. An example for sizing underdrains is found in the North Carolina Department of Environment and Natural Resources Stormwater BMP Manual. Underdrain spacing can be calculated using the following spreadsheet, which utilizes the vanSchilfgaarde Equation. The spreadsheet includes an example calculation. File:Underdrain spacing calculation.xlsx