Line 19: Line 19:
  
 
The Near Northside neighborhood of Minneapolis was originally developed in the late 19th century on land characterized by low-lying swamps, tributary springs, upland seepage and surface runoff areas associated with Bassett Creek. Several generations built low-income housing on wetland and floodplain areas that had been filled and drained in the early 20th century. The early single-family structures failed due to these unstable conditions and were replaced by higher-density rowhouses in public housing projects. These also experienced differential settling of structures, utilities, streets and sidewalks over time due to the poor soil conditions.
 
The Near Northside neighborhood of Minneapolis was originally developed in the late 19th century on land characterized by low-lying swamps, tributary springs, upland seepage and surface runoff areas associated with Bassett Creek. Several generations built low-income housing on wetland and floodplain areas that had been filled and drained in the early 20th century. The early single-family structures failed due to these unstable conditions and were replaced by higher-density rowhouses in public housing projects. These also experienced differential settling of structures, utilities, streets and sidewalks over time due to the poor soil conditions.
 +
 +
Stormwater management at the time consisted of directing surface water runoff (including Bassett Creek) through a large underground tunnel system to reduce flooding problems in the area. This tunnel system discharged directly to the Mississippi River. The originally constructed tunnel was replaced in 1992 in a new alignment several blocks to the south to handle the considerably higher runoff volume resulting from suburban and freeway development, leaving the old tunnel in place for local conveyance.
 +
 +
In 1992, the public housing developments occupying the site were the target of a lawsuit charging segregation and isolation of public housing residents. The lawsuit was settled in 1995 through a Decree to determine a re-use plan for the site through a community-based focus group process. The Action Plan developed from these recommendations called for reconnecting the site to surrounding neighborhoods and amenities, demolishing the public housing units, and replacing them with mixed-income housing (25 percent public housing), and a system of parks and open space. The Action Plan was approved in federal court in 1997 and was followed by a Master Plan approved in 2000. The Master Plan called for 900 new mixed-income homes, a combination of rental and for-sale, affordable to families at all income levels. The first units were occupied in November, 2000 and construction is still under way on the remainder.
 +
 +
====BMP development====
 +
 +
Stormwater infrastructure for Heritage Park was based on a design that includes a combination of engineered and natural systems set within the development’s park and open space amenities. These serve not only as an effective stormwater treatment system but also restore a sense of place to the traditionally low-income, amenity-poor neighborhood. The stormwater infrastructure for the site treats runoff and non-point source pollution from the 143-acre redevelopment area as well as neighboring residential, commercial, and industrial areas for a total treatment area of roughly 400 acres. The stormwater treatment system is the core of the park and open space component of the project, merging upland and wetland native plant communities with filtration-based processes to remove pollutants. Larger pond systems anchor the park areas while smaller ponds, wetlands and filtration systems are blended into the The general stormwater “treatment train” design used for the Heritage Park project area; each step of the process incrementally cleanses the water further. Rainwater running off the streets and park areas carries sediments and pollutants. The runoff generally enters the system through typical urban catch basins and storm sewers and passes through either grit chambers or into trench forebays for initial removal of large particles. Using a level spreader mechanism, water is then routed to filtration basins planted with wet meadow or wet prairie plant communities. The basins, or galleries, use the cleansing ability of the plantings and soil profiles, reduce velocity, and reduce quantity of stormwater through infiltration and evapotranspiration. Water passes over rock weirs as it moves from one basin to the next, then into ponds for further treatment, as well as enjoyment of the open water amenities. Discharge from the ponds is conveyed downstream through a tunnel to the Mississippi River.
 +
 +
===Description===
 +
 +
====Pre-Treatment systems====
 +
 +
'''Swirl Chamber''': Swirl chambers, also called hydrodynamic separators, are designed to remove large particles and debris from stormwater. Sixteen hydrodynamic separators were installed at Heritage Park. Stormwater is diverted from the conveyance system into the chamber using a flow splitter, through an inlet and across a stainless steel screen whose size was based on site-specific performance standards. The unit has a system bypass that allows excessive stormwater flows to continue downstream via the storm sewer system.
 +
 +
'''Trench Forebays''': Trench forebays are located upslope from filtration basins and are engineered pre-treatment systems that act both as flow spreaders, which reduce the velocity of water before it enters the filtration basin, and sediment collectors. Water then discharges to a filtration basin, either by overtopping the forebay or through drain tile.
 +
 +
'''Level Spreaders''': Level spreaders are located upslope from filtration basins at the transition point between short grass prairie and wetland community to promote even, low-velocity sheet flow into the filtration basins, preventing erosion and enhancing filtration.

Revision as of 14:25, 1 July 2015

This site is currently undergoing revision. For more information, open this link.
This site is under construction. Anticipated completion date is July, 2015.

Treatment Train Case Studies

Heritage Park, Minneapolis

In the ultra-urban setting of Minneapolis, space for stormwater infrastructure is at a premium in urban retrofit projects such as Heritage Park due to demand for affordable housing intensity and physical constraints. Stormwater from the site before redevelopment was collected through a large underground tunnel system and discharged without pre-treatment directly to the Mississippi River. The challenge at this 145-acre redevelopment site was to incorporate stormwater amenities into the overall site design and best utilize the limited space available.

Project summary

  • Location: Minneapolis
  • Landscape Setting: Urban
  • Drainage Area: ~400 acres
  • Project Area: 145 acres
  • Project Timeline: 2001 to 2007
  • Project Cost: $225 million ($75 million infrastructure; $150 million housing)
  • More Information: City of Minneapolis

Background

The Near Northside neighborhood of Minneapolis was originally developed in the late 19th century on land characterized by low-lying swamps, tributary springs, upland seepage and surface runoff areas associated with Bassett Creek. Several generations built low-income housing on wetland and floodplain areas that had been filled and drained in the early 20th century. The early single-family structures failed due to these unstable conditions and were replaced by higher-density rowhouses in public housing projects. These also experienced differential settling of structures, utilities, streets and sidewalks over time due to the poor soil conditions.

Stormwater management at the time consisted of directing surface water runoff (including Bassett Creek) through a large underground tunnel system to reduce flooding problems in the area. This tunnel system discharged directly to the Mississippi River. The originally constructed tunnel was replaced in 1992 in a new alignment several blocks to the south to handle the considerably higher runoff volume resulting from suburban and freeway development, leaving the old tunnel in place for local conveyance.

In 1992, the public housing developments occupying the site were the target of a lawsuit charging segregation and isolation of public housing residents. The lawsuit was settled in 1995 through a Decree to determine a re-use plan for the site through a community-based focus group process. The Action Plan developed from these recommendations called for reconnecting the site to surrounding neighborhoods and amenities, demolishing the public housing units, and replacing them with mixed-income housing (25 percent public housing), and a system of parks and open space. The Action Plan was approved in federal court in 1997 and was followed by a Master Plan approved in 2000. The Master Plan called for 900 new mixed-income homes, a combination of rental and for-sale, affordable to families at all income levels. The first units were occupied in November, 2000 and construction is still under way on the remainder.

BMP development

Stormwater infrastructure for Heritage Park was based on a design that includes a combination of engineered and natural systems set within the development’s park and open space amenities. These serve not only as an effective stormwater treatment system but also restore a sense of place to the traditionally low-income, amenity-poor neighborhood. The stormwater infrastructure for the site treats runoff and non-point source pollution from the 143-acre redevelopment area as well as neighboring residential, commercial, and industrial areas for a total treatment area of roughly 400 acres. The stormwater treatment system is the core of the park and open space component of the project, merging upland and wetland native plant communities with filtration-based processes to remove pollutants. Larger pond systems anchor the park areas while smaller ponds, wetlands and filtration systems are blended into the The general stormwater “treatment train” design used for the Heritage Park project area; each step of the process incrementally cleanses the water further. Rainwater running off the streets and park areas carries sediments and pollutants. The runoff generally enters the system through typical urban catch basins and storm sewers and passes through either grit chambers or into trench forebays for initial removal of large particles. Using a level spreader mechanism, water is then routed to filtration basins planted with wet meadow or wet prairie plant communities. The basins, or galleries, use the cleansing ability of the plantings and soil profiles, reduce velocity, and reduce quantity of stormwater through infiltration and evapotranspiration. Water passes over rock weirs as it moves from one basin to the next, then into ponds for further treatment, as well as enjoyment of the open water amenities. Discharge from the ponds is conveyed downstream through a tunnel to the Mississippi River.

Description

Pre-Treatment systems

Swirl Chamber: Swirl chambers, also called hydrodynamic separators, are designed to remove large particles and debris from stormwater. Sixteen hydrodynamic separators were installed at Heritage Park. Stormwater is diverted from the conveyance system into the chamber using a flow splitter, through an inlet and across a stainless steel screen whose size was based on site-specific performance standards. The unit has a system bypass that allows excessive stormwater flows to continue downstream via the storm sewer system.

Trench Forebays: Trench forebays are located upslope from filtration basins and are engineered pre-treatment systems that act both as flow spreaders, which reduce the velocity of water before it enters the filtration basin, and sediment collectors. Water then discharges to a filtration basin, either by overtopping the forebay or through drain tile.

Level Spreaders: Level spreaders are located upslope from filtration basins at the transition point between short grass prairie and wetland community to promote even, low-velocity sheet flow into the filtration basins, preventing erosion and enhancing filtration.