Line 147: Line 147:
  
 
Sediment basins are used for to capture stormwater runoff from the site and allow sediment to settle prior to discharge. If the site is using a temporary sediment basin, the SWPPP must describe the following.  
 
Sediment basins are used for to capture stormwater runoff from the site and allow sediment to settle prior to discharge. If the site is using a temporary sediment basin, the SWPPP must describe the following.  
*Use of temporary sediment basin if 10 or more acres of disturbed soil drain to one place, or 5 acres if the discharge point is within one mile of a special or impaired water<br>
+
*Use of temporary sediment basin if 10 or more acres of disturbed soil drain to one place, or 5 acres if the discharge point is within one mile of a [https://stormwater.pca.state.mn.us/index.php?title=Special_waters_and_other_sensitive_receiving_waters special or impaired water]
 
*Documented live storage volume from each acre drained
 
*Documented live storage volume from each acre drained
 
*Design that:
 
*Design that:

Revision as of 18:23, 27 July 2017

This site is currently undergoing final review. For more information, open this link.
This page is under review

The Municipal Separate Storm Sewer System (MS4) permit requires the permittee to conduct site plan reviews. Permittees must perform and document site plan reviews for construction projects that disturb one acre or more of land. The site plan review ensures active and post-construction requirements of a permittee's regulatory mechanism (e.g. code, ordinance, law) are met. The MS4 Permit requires the regulatory mechanism to be as stringent as the MNR100001/Construction Stormwater Permit.

This permit requirement is somewhat vague and has led to people not realizing that they need to review plans for specific items. The items identified below are the minimum that must be evaluated during a stormwater site plan review under the MS4 and Construction Stormwater Permits. For each site plan review performed, permittees must document the project name, location, total acreage to be disturbed, owner and operator of the proposed construction activity, and any stormwater related comments used to approve or deny the project. If you’d like to conduct a more comprehensive review, please see the MPCA’s SWPPP Checklist. During the site plan review, you must verify that site plans include the information listed on this page.

Here's a PDF version of this page

Best Management Practices (BMPs) to minimize erosion

Stabilization schedule must be no less than:
14 days for all exposed soils
7 days if a discharge point is within one mile of a special or impaired water
24 hours for areas within 200 ft of a public water during fish spawning times
24 hours for areas of ditches and swales within 200 ft of the property edge or surface water discharge point and 14 days for remainder

BMPs to minimize erosion are the first line of defense for protecting stormwater from sediment running off your site. Soil without proper erosion control, such as blanket, mulch, or vegetation is prone to erosion. When reviewing site plans, ensure effective erosion control methods are described and located in the appropriate areas.

BMPs to minimize the discharge of sediment and other pollutants

photo silt fence
Photo of a well-constructed silt fence, which is a perimeter control practice.

Properly installed and maintained sediment control BMPs, such as silt fence or bioroll, prevent sediment from discharging from your site. They allow stormwater to pass through, but filter out sediment. When reviewing site plans, ensure that sediment controls to be used will be effective for the scale of the site.

Site inspections and rainfall records

Insepction schedule must be no less than:
Every 7 days during active construction
Within 24 hours after a 0.5 inch rain event
If work is suspended due to frozen ground, inspections must begin within 24 hours after runoff occurs or construction starts
For parts of the site with permanent cover but work is ongoing elsewhere, inspections can be once per month
If the entire site has permanaent cover and there is no active construction, inspections can be once per month for twelve months

Site inspections must be conducted by a trained person every seven days and 24 hours after a half inch rainfall event. The Construction Stormwater stormwater pollution prevention plan (SWPPP) should document the person responsible for site inspections and any modified inspection frequency.

  • Schedule for inspecting and recording inspections
  • Documentation of inspections, including:
    • date and time of inspection
    • inspector name
    • inspection findings and corrective actions
    • recent rainfall events of 0.5 inches in 24 hours
    • observed discharge and discharge points
    • proposed amendments to the site plan

Link to a construction stormwater inspection checklist

BMPs for dewatering activities

When done correctly, dewatering activities will only discharge clear water. Therefore, when applicable, SWPPPs should include the following.

  • A plan to discharge sediment-laden water to a sedimentation basin
  • A plan for dewatering to prevent discharge of sediment laden water, erosion, and downstream impacts

BMP maintenance

BMP maintenance schedule must be no less than:
End of next business day for nonfunctioning BMPs
End of next business day or as soon as conditions allow for nonfunctioning perimeter control
72 hours or as soon as conditions allow for draining sedimentation basins
24 hours for tracked sediment
7 days for removing deltas and sediment from surface water and restabiliztion

Sediment control devices are only effective if properly maintained. Ensure SWPPPs note the following schedules and procedures.

  • Schedule and procedure to repair and replace adjusted and non-functioning BMPs or perimeter control devices when sediment reaches ½ the device height
  • Schedule to inspect surface waters and streets
  • Schedule and procedure to maintain sediment basins
  • Procedure to remove tracked sediment
  • Schedule to inspect infiltration areas

For information on specific construction BMPs go to the Inspection and maintenance section for individual Erosion prevention practices or Sediment control practices.

Management of solid and hazardous waste

Washout operations specifications:
Washout wastes must not contact the ground
Washout operations must not result in runoff

Properly storing, handling, and disposing of chemicals and building materials protects stormwater. SWPPPs must include methods to prevent chemicals from coming in contact with stormwater.

  • Cover on building products, pesticides, herbicides, insecticides, fertilizers, chemicals, and landscape materials
  • Plan for properly storing and disposing of waste
  • Securing portable toilets
  • Process for containing washout wastes
  • Defined limited area for vehicle washing, fueling, and maintenance and a plan to contain washing runoff
  • Prohibition of engine degreasing onsite

For more information link here.

Final stabilization when construction is complete

Final stabilization will provide long-term protection from sediment loss. SWPPPs must provide a final stabilzation plan.

Use of temporary sediment basins, if applicable

Temporary sediment basin live storage:
If the live storage volume is calculated, it must accommodate a 2-year, 24 hour flood event, but cannot be less than 1,800 cubic ft
If live storage is not calculated, then the basin must accommodate 3,600 cubic ft of live storage

Sediment basins are used for to capture stormwater runoff from the site and allow sediment to settle prior to discharge. If the site is using a temporary sediment basin, the SWPPP must describe the following.

  • Use of temporary sediment basin if 10 or more acres of disturbed soil drain to one place, or 5 acres if the discharge point is within one mile of a special or impaired water
  • Documented live storage volume from each acre drained
  • Design that:
    • prevents short-circuiting & floating debris discharge
    • allows for complete basin drawdown
    • has a stabilized emergency overflow
    • withdraws water from the surface
    • includes energy dissipation for the basin outlet
    • is outside of surface waters
    • avoids draining to wetlands
    • is operational before construction starts

Post-construction stormwater management

Infiltration prohibitions and limitations:
Infiltration is prohibited where: industrial facilities cannot under an NPDES Industrial Stormwater permit, vehicle fueling/maintenance occurs,
there is less than 3 ft between the infiltration device and bedrock/seasonably saturated soils, and high levels of contaminants will be mobilized
Infiltration is limited within: clay soils, 1,000 ft upgradient or 100 ft downgradient of active karsts, a Drinking Water Supply Management Area, or
areas with infiltration rates of >8.3 inches/hour

Permanent stormwater management systems, like infiltration basins, vegetated filter strips, stormwater ponds, etc., must be designed, constructed, and maintained correctly in order to function properly. SWPPPs must describe these systems and design them to meet the following permit requirements.

  • Preference for Green Infrastructure techniques
  • No net increase (new development) or net decrease (redevelopment) in
  • Provide the reason infiltration is not allowed, if applicable, and describe the alternative treatment system