This table shows cost Components for Bioretention Practices
(Link to this table)
Implementation Stage | Primary Cost Components | Basic Cost Estimate | Other Considerations |
---|---|---|---|
Site Preparation | Tree & plant protection | Protection Cost ($/area) x Affected Area | Removal of existing structures, topsoil removal and stockpiling |
Clearing & grubbing | Clearing Cost ($/area) x Affected Area | Removal of existing structures, topsoil removal and stockpiling | |
Topsoil salvage | Clearing Cost ($/area) x Affected Area | Removal of existing structures, topsoil removal and stockpiling | |
Site Formation | Excavation / grading | 4-ft Depth Excavation Cost ($/acre) x Area (acre) | Soil & rock fill material, tunneling |
Hauling material offsite | Excavation Cost x (% of Material to be hauled away) | Soil & rock fill material, tunneling | |
Structural Components | Under-drains | Under-drain cost ($/lineal foot) x length of device | Pipes, catch-basins, manholes, valves |
Inlet structure | ($/structure) or ($/curb cut) | Pipes, catch-basins, manholes, valves | |
Outlet structure | ($/structure) | Pipes, catch-basins, manholes, valves | |
Liner | Liner cost ($/square yard) x area of device) | Pipes, catch-basins, manholes, valves | |
Site Restoration | Filter strip | Sod cost ($/square foot) x filter strip area | Tree protection, soil amendments, seed bed preparation, trails |
Soil preparation | Topsoil or amendment cost ($/acre) x Area (acre) | Tree protection, soil amendments, seed bed preparation, trails | |
Seeding | Seeding Cost ($/acre) x Seeded Area (acre) | Tree protection, soil amendments, seed bed preparation, trails | |
Planting / transplanting | Planting Cost ($/acre) x Planted Area (acre) | Tree protection, soil amendments, seed bed preparation, trails | |
Annual Operation, Maintenance, and Inspection | Debris removal | Removal Cost ($/acre) x Area (acre) x Frequency | Vegetation maintenance, cleaning of structures |
Sediment removal | Removal Cost ($/acre) x Area (acre) x Frequency | Vegetation maintenance, cleaning of structures | |
Weed control | Labor cost ($/hour) x Hours per visit x Frequency | Vegetation maintenance, cleaning of structures | |
Inspection | Inspection Cost ($) x Inspection Frequency | Vegetation maintenance, cleaning of structures | |
Mowing | Mowing Cost ($) x Mowing Frequency | Vegetation maintenance, cleaning of structures |