Green roof construction can be complex and involve many different trades working in a small space. The following construction sequence is recommended. | Green roof construction can be complex and involve many different trades working in a small space. The following construction sequence is recommended. | ||
− | + | ||
A pre-construction meeting is recommended prior to beginning any construction on the roof to ensure construction sequencing will maximize efficiency and minimize conflicts between the various trades that need to access the roof. The meeting should include all green roof related installers and designers. Installers present at the meeting should include, for example, all of the following that are relevant to the green roof project, as well any others involved in the green roof project: roofing, green roof, irrigation, leak detection, lightning protection, electrical, glaziers, mechanical, and general contractor. Designers should include, for example, all of the following that are relevant to the green roof project, as well any others involved in the green roof project: roofing consultant, green roof designer, irrigation designer, electrical and mechanical engineers. | A pre-construction meeting is recommended prior to beginning any construction on the roof to ensure construction sequencing will maximize efficiency and minimize conflicts between the various trades that need to access the roof. The meeting should include all green roof related installers and designers. Installers present at the meeting should include, for example, all of the following that are relevant to the green roof project, as well any others involved in the green roof project: roofing, green roof, irrigation, leak detection, lightning protection, electrical, glaziers, mechanical, and general contractor. Designers should include, for example, all of the following that are relevant to the green roof project, as well any others involved in the green roof project: roofing consultant, green roof designer, irrigation designer, electrical and mechanical engineers. | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
Key factors in determining construction sequencing include the following | Key factors in determining construction sequencing include the following | ||
*Do not begin installation until required submittals are approved. | *Do not begin installation until required submittals are approved. |
Green roof construction can be complex and involve many different trades working in a small space. The following construction sequence is recommended.
A pre-construction meeting is recommended prior to beginning any construction on the roof to ensure construction sequencing will maximize efficiency and minimize conflicts between the various trades that need to access the roof. The meeting should include all green roof related installers and designers. Installers present at the meeting should include, for example, all of the following that are relevant to the green roof project, as well any others involved in the green roof project: roofing, green roof, irrigation, leak detection, lightning protection, electrical, glaziers, mechanical, and general contractor. Designers should include, for example, all of the following that are relevant to the green roof project, as well any others involved in the green roof project: roofing consultant, green roof designer, irrigation designer, electrical and mechanical engineers.
Key factors in determining construction sequencing include the following