Line 39: | Line 39: | ||
*Channel slope cannot be greater than 4 percent or less than 0.5 percent. | *Channel slope cannot be greater than 4 percent or less than 0.5 percent. | ||
*Infiltration rates of the underlying soils are restricted to a maximum of 1.63 inches/hour. | *Infiltration rates of the underlying soils are restricted to a maximum of 1.63 inches/hour. | ||
− | *The water underneath the underdrain must meet the drawdown time requirement specified. The drawdown time requirement is checked by comparing the user defined drawdown time with the calculated drawdown time(DDT<sub>calc</sub>) | + | *The water underneath the underdrain must meet the drawdown time requirement specified. The drawdown time requirement is checked by comparing the user defined drawdown time with the calculated drawdown time (DDT<sub>calc</sub>), given by |
<math>DDT_{calc} = D_U / (I_R / 12)</math> | <math>DDT_{calc} = D_U / (I_R / 12)</math> |
A swale main channel with an underdrain behaves similar to a bioretention BMP with an underdrain. Volume retention is achieved through infiltration of water stored in the pore spaces of engineered media between the invert of an elevated underdrain and the native soils. If the underdrain is not elevated above the native soils then volume reduction is achieved through infiltration below the underdrain. Volume retention also occurs by evapotranspiration through the vegetation in the swale. If runoff to the main channel flows over a side slope through sheet flow, a swale side slope BMP should be used in combination with the swale main channel BMP. All pollutants in infiltrated water are removed, while pollutants are removed through filtration for the water that flows through an underdrain.
For a swale main channel with underdrain system, the user must input the following parameters to calculate the volume and pollutant load reductions associated with the BMP.
If a swale side slope is routed to this BMP, do not include the side slope watershed areas for the swale main channel since this would be double counting the contributing area.
The following are requirements for inputs into the MIDS calculator. If the following are not meet an error message will inform the user to change the input to meet the requirement.
\(DDT_{calc} = D_U / (I_R / 12)\)
Where
If the DDTcalc is greater than the user defined required drawdown time then the user will be prompted to enter a new depth below the underdrain or infiltration rate of the native soils.
“Required treatment volume,” or the volume of stormwater runoff delivered to the BMP, equals the performance goal (1.1 inches or user-specified performance goal) times the impervious area draining to the BMP. This stormwater is delivered to the BMP instantaneously following the Kerplunk method.
The volume reduction achieved by a BMP compares the capacity of the BMP to the required treatment volume. The “Volume reduction capacity of BMP [V]” is calculated using BMP inputs provided by the user. For this BMP, the volume reduction credit methodology is determined by the location of the underdrain.
Underdrain located at BMP bottom: If the underdrain is located at the bottom of the BMP, then the “Volume reduction capacity of BMP [V]” is determined based on infiltration into the bottom of the BMP (Vinf_b) and evapotranspiration in the planting media above the underdrain (VET).
Even with an underdrain present, under saturated media conditions some water will infiltrate through the bottom soils as water in the basin draws down. The volume of water lost through the bottom (Vinf_b) of the BMP equals the following
\(V_{Inf_B} = I_R * (DDT) * W_B * L_C/(12in/ft)\)
Where
The default infiltration rate is set at 0.06 inches per hour to represent a D soil. This rate was selected because it is assumed most of the stormwater will pass through the underdrain before it can infiltrate through the bottom of the BMP. This may be a conservative assumption if underdrains are small, spaced far apart, and the underlying soil has an infiltration rate greater than 0.06 inches per hour. Conversely, more closely spaced or larger underdrains may allow the basin to drain in less than the required drawdown time, resulting in a slight overestimation of infiltration loss through the basin bottom. If the user specifies that an impermeable liner is present at the bottom of the BMP, then no credit is given for infiltration into the bottom soils.
In addition to the credit given for the infiltration below the underdrain, a swale main channel BMP can also achieve stormwater volume reduction through evapotranspiration (VET). The volume of water lost through evapotranspiration (VET) is the smaller of two calculated values, potential ET and measured ET.
\(ET_pot=((D_M-D_U )*(L_C*W_B)*(FC-WP))\)
Where
\(ET_{mea} = L_C * W_B * 0.2 in/day * 0.5 *3 days / 12 in/ft \)
Measured ET and potential ET are compared and the volume lost to ET is the smaller of the two values.
Elevated Underdrain: If the underdrain is elevated above the bottom of the BMP, then the volume reduction credit is determined based on the storage capacity in the media between the underdrain and the native soils and evapotranspiration in the planting media above the underdrain (VET).
The volume captured below the underdrain (V) is given by
\(V = L_C * W_B * n * D_U\)
Where
The stored water must drain within the specified drawdown time. The underlying soil controls the infiltration rate. The user must input the soil with the most restrictive hydraulic conductivity in the 3 feet directly below the basin (i.e. below the bottom of the engineered media).
In addition to the credit given for the storage capacity below the underdrain, a swale main channel system with an elevated underdrain also receives volume reduction credit for evapotranspiration. Credit is given following the same methods described when the underdrain is located at the bottom of the BMP (see discussion above).
The “Volume of retention provided by BMP” is the amount of volume credit the BMP provides toward the performance goal. This value is equal to the “Volume reduction capacity of BMP [V]”, calculated using the above method, as long as the volume reduction capacity is less than or equal to the “Required treatment volume.” If “Volume reduction capacity of BMP [V]” is greater than “Required treatment volume”, then the BMP volume credit is equal to “Required treatment volume.” This check makes sure the BMP is not getting more credit than the amount of water it receives. For example, if the BMP is oversized the user will only receive credit for “Required treatment volume” routed to the BMP.
Pollutant load reductions are calculated on an annual basis. Therefore, the first step in calculating annual pollutant load reductions is converting “Volume reduction capacity of BMP,” which is an instantaneous volume reduction, to an annual volume reduction percentage. This is accomplished through the use of performance curves developed from multiple modeling scenarios. The performance curves use “Volume reduction capacity of BMP [V]”, the infiltration rate of the underlying soils, the contributing watershed percent impervious area, and the size of the contributing watershed to calculate a percent annual volume reduction. While oversizing a BMP above “Required treatment volume” will not provide additional credit towards the performance goal volume, it may provide additional pollutant reduction.
A 100 percent removal is credited for all pollutants associated with the reduced volume of stormwater. Stormwater captured by the swale system but not infiltrated or consumed through ET is assumed to flow through the filter media and out the underdrain. A constant 68 percent removal rate is applied to the filtered stormwater for TSS reduction. The removal rates of the filtered stormwater for annual particulate phosphorus and dissolved phosphorus depend on the answers given to the three user inputs: “Planting media mix”, “Is the P content of the media less than 30 mg/kg?” and “Is a soil amendment used to attenuate phosphorus?”
Particulate Phosphorus: The particulate phosphorus credit given is either 0 percent or 45 percent depending on the media mix used and the P content of the media.
Dissolved Phosphorus: The dissolved phosphorus credit given is between 0 percent and 60 percent depending on the media mix, the media P content, and if the media was amended to attenuate phosphorus.
\(credit = 20% * ((D_M - D_U)) / (2 ft)\)
where (DM - DU) represents the media depth above the underdrain. The credit is calculated as a percent reduction with a maximum value of 20 percent for media depths above the underdrain greater than 2 feet. If the media depth above the underdrain is less than 2 feet the credit is reduced equivalently.
The removal rates of the filtered stormwater for annual particulate phosphorus and dissolved phosphorus is summarized in the following table.
NOTE: The user can modify event mean concentrations (EMCs) on the Site Information tab in the calculator. Default concentrations are 54.5 milligrams per liter for total suspended solids (TSS) and 0.3 milligrams per liter for total phosphorus (particulate plus dissolved). The calculator will notify the user if the default is changed. Changing the default EMC will result in changes to the total pounds of pollutant reduced.
Overflow from a swale main channel with an underdrain can be routed to any other BMP, except for a green roof and a swale side slope or any BMP in a stormwater treatment sequence that would cause stormwater to be rerouted back to the swale main channel already in the treatment sequence. All BMPs can be routed to the swale main channel
The following general assumption applies in calculating the credit for a swale main channel with an underdrain. If this assumption is not followed the volume and pollutant reduction credits cannot be applied.
The runoff from a 1.4 acre parking lot surrounded by 0.359 acres of pervious turf area flows through sheet flow over one of the side slopes of a swale and into a swale main channel. The soils across the area have a unified soils classification of SW (HSG type A soil). A second side slope associated with the main channel does not receive runoff from impervious surfaces. Each of the swale side slopes are 800 feet long by 10 feet wide with a side slope of 5H:1V. The main channel of the swale is 800 feet long by 4 feet wide with a 2 percent slope. The swale main channel does not have an underdrain, bioretention base or check dams. The maintenance on the swale calls for mowing once a year. The following steps detail how this system would be set up in the MIDS calculator.
Step 1: Determine the watershed characteristics of your entire site. For this example we have a 2.2 acre site with 1.4 acres of impervious area (parking lot) and 0.8 acres of pervious area in type A soils. The pervious area includes the turf area and the area of the swale side slopes and main channel.
Step 2: Fill in the site specific information into the Site Information tab. This includes entering a Zip Code (55414 for this example) and the watershed information from Step 1. The Managed Turf area includes the turf area, the area of the side slopes and the area of the main channel. Zip code and impervious area must be filled in or an error message will be generated. Other fields on this screen are optional.
Step 3: Go to the Schematic tab and drag and drop a “Swale Side Slope” and a “Swale Main Channel” icon into the “Schematic Window”
Step 4: Determine the watershed characteristic for each of the BMP components. For this example the swale side slope watershed includes 1.4 acres of impervious area and 0.543 acre of pervious area (0.359 acre of turf area plus 0.184 acre of swale side slope). The watershed of the swale main channel includes the pervious area of the main channel (0.073 acre) and the pervious area of the other swale side slope (0.184 acre) for a total pervious area of 0.257 acre. Since no impervious area is being routed to the second swale side slope, the area can be included in the direct watershed area of the main channel. However, the second swale side slope could be placed in the calculator as an additional BMP. Including it as a separate BMP provides a slightly greater annual volume reduction and more closely represents the true system.
Step 5: Open the BMP properties for the swale side slope by right clicking on the Swale Side Slope icon and selecting Edit BMP properties, or by double clicking on the Swale Side Slope icon.
Step 6: Click on the Minnesota Stormwater Manual Wiki link or the Help button to review input parameter specifications and calculation specific to the Swale Side Slope BMP.
Step 7: Fill in the specific BMP watershed information (1.4 acres of impervious and 0.543 acre of Managed Turf on A Soils. Route the side slope BMP to the main channel BMP.
Step 8: Enter in the BMP design parameters into the BMP parameters tab. Swale Side Slope requires the following entries.
Schematic of Schematic tab wet swale example
Schematic showing Summary results for Swale Main Channel. Corresponds with Step 15 in the example.Schematic of BMP Summary tab wet swale example side slope
Schematic of Schematic tab wet swale example<
Step 9: Click on BMP Summary tab to view results for this BMP.
Step 10: Click on the OK button to exit the BMP properties screen. An arrow will appear showing that the swale side slope has been routed to the swale main channel.
Step 11: Open the BMP properties window for the swale main channel by right clicking on the Swale main channel icon and selecting Edit BMP properties, or by double clicking on the “Swale main channel” icon. Step 12: Click on the Minnesota Stormwater Manual Wiki link or the Help button to review input parameter specifications and calculation specific to the Swale main channel BMP.
Step 13: Enter in the watershed information for the swale main channel in the Watershed tab (0.257 acre for Pervious Turf on A Soil which includes the area of the main channel and the other side slope).
Step 14: Enter in the BMP design parameters into the BMP parameters tab. Swale main channel requires the following entries.
Step 15: Click on BMP Summary tab to view results for this BMP.
Step 16: Click on the OK button to exit the BMP properties screen.
Step 17: Click on Results tab to see overall results for the site.