Line 96: | Line 96: | ||
====Best Management Practices==== | ====Best Management Practices==== | ||
− | ====Erosion prevention practices | + | ====Erosion prevention practices==== |
*Erosion prevention practices must be selected, installed, and maintained according to the manufacturers specifications and accepted engineering practices. Regulated parties choose which practices are best for specific sites. In addition, efforts must be made to minimize erosion through use of construction phasing. | *Erosion prevention practices must be selected, installed, and maintained according to the manufacturers specifications and accepted engineering practices. Regulated parties choose which practices are best for specific sites. In addition, efforts must be made to minimize erosion through use of construction phasing. | ||
Line 110: | Line 110: | ||
*erosion blankets | *erosion blankets | ||
*rip rap | *rip rap | ||
+ | *sod | ||
+ | |||
+ | Other required erosion prevention practices: | ||
+ | *Conveyance channels must be used to route water around exposed soil areas unless infeasible. | ||
+ | *Velocity dissipation devices, such as check dams, sediment traps, or rip rap must be used in conveyance channels and at any outlet to reduce flow velocity. | ||
+ | *The last 200 feet of normal wetted perimeters of ditches or swales must be stabilized within 24 hours of connecting to a property edge or point of discharge. The remainder of the ditch or swale must be stabilized within the 14 day time frame. Acceptable methods for stabilizing ditches and swales include the following: | ||
+ | **erosion control blankets or mats | ||
+ | **rip rap | ||
+ | **other material suitable for concentrated flow areas | ||
+ | **mulch, hydromulch, tackifier, polyacrylamide or similar erosion prevention practice is not an acceptable stabilization method in these areas. | ||
+ | *Pipe outlets require energy dissipation, such as rip rap, splash pads or other suitable material to prevent scour and must be installed within 24 hours of connection to a surface water. | ||
+ | *An effort must be made to direct stormwater runoff to vegetated areas of the site. | ||
+ | |||
+ | ====Sediment control practices==== | ||
+ | |||
+ | Sediment control practices must minimize sediment from entering surface waters, curb and gutter systems, and storm sewer inlets. Regulated parties choose which practices are best for specific sites and practices must be installed according to permit timelines. Sediment controls to be used at the site include: | ||
+ | Down gradient perimeter control established below the planned land disturbance and up gradient of vegetative buffers before work begins. Floating curtains are not an acceptable method of perimeter control near surface waters unless the work is on the shoreline or below the water line prohibiting the use of standard perimeter control and the floating curtain is located in the water as close to the shore as possible. | ||
+ | *Storm drain inlet protection. | ||
+ | *Sediment controls installed at the perimeter of temporary soil stockpiles. | ||
+ | *BMPs, such as stone pads or wash racks installed at construction exits to prevent vehicle tracking. | ||
+ | *Temporary sediment basins where ten or more acres of exposed soil drain to a common point on the site. | ||
+ | *Methods to minimize soil compaction. | ||
+ | *Maintaining a 50 foot natural buffer down gradient of the site or redundant sediment controls if buffer is not feasible, when the construction is within 50 feet of a surface water. | ||
+ | *Use of sediment treatment chemicals, such as flocculants and polymers, must comply with the following: | ||
+ | **The chemical may only be applied to a sediment control system that provides filtration or settlement prior to discharge. | ||
+ | **The chemical must be selected based on soil type. | ||
+ | **The chemical must be used according to the manufacturer specifications and accepted engineering practices. | ||
+ | |||
+ | '''For sites within one mile of special or impaired waters, additional BMPs are required.''' | ||
+ | |||
+ | Additional BMPs are listed in Appendix A for the specific water of concern. Dependent upon the water listed these BMPs may include: |
A technical summary of Minnesota’s NPDES permit
This fact sheet provides summary information. Please review the NPDES/SDS Construction Stormwater General Permit for more detailed information. Ecological harm
By following the terms and conditions of the construction stormwater permit, Minnesota’s construction workers reduce the environmental pressure of earth-moving activities on Minnesota’s water.
In days or weeks, land disturbing activities at construction sites has the potential to contribute more sediment to streams than is deposited naturally over several decades. The environmental damage is severe and often permanent. Polluted runoff clouds streams, harming or killing fish and other aquatic organisms. Sediment deposits accelerate filling-of lakes. Sediment also carries nutrients that cause excessive plant growth and algae that contribute to the eutrophication process. Increased volume of runoff caused by the creation of new impervious surfaces can cause severe erosion in receiving waters and may change the contours of a river and wipe out valuable habitats like gravel stream beds which are necessary for fish spawning. Other pollutants at construction sites such as concrete wash water, petroleum products, chemicals, construction materials and sewage may pose a risk to both surface and groundwater and need to be properly handled and stored.
Minnesota’s construction stormwater permit is an extension of the National Pollutant Discharge Elimination System (NPDES) Stormwater Program, which is part of the Federal Clean Water Act.
The NPDES Stormwater Program is a comprehensive national program for addressing polluted runoff. The U.S. Environmental Protection Agency (EPA) is ultimately responsible for the quality of the nation’s water, but in Minnesota, the Minnesota Pollution Control Agency (MPCA) administers this federal program as well as the related State Disposal System (SDS) permit program. The states combined NPDES/SDS construction stormwater permit fulfills federal and state requirements by requiring permittees to control runoff.
The federal government requires NPDES permit coverage of construction sites that disturb one or more acres. Sites that lack permit coverage and/or fail to meet permit terms and conditions will be subject to MPCA enforcement action, civil penalties and/or criminal charges. Owners and operators of construction activity that fail to obtain permit coverage are open to third-party civil suits.
Prior to submitting an application, regulated parties must develop a complete and accurate Stormwater Pollution Prevention Plan (SWPPP) in accordance with the stormwater discharge design requirements in Part III and Part IV of the permit. The construction stormwater permit application must be submitted using the MPCA Online Services system along with electronic payment of the $400 application fee.
The application fee can be submitted online via credit card or e-check. Instructions for completing the application process can be found at the Steps to Construction site. Permit coverage is effective seven calendar days after submitting a complete application. An authorized party, such as a consultant or legal counsel, may complete the application for the project owner. Both the owner and the contractor must be listed on the application.
If the applicant is unable to apply online due to lack of internet access or other reasons, the MPCA can be contacted at 651-757-2119 or 800-657-3804 for assistance to receive a waiver and instructions for obtaining a paper application form.
Projects that are not eligible for permit issuance within seven days for sites disturbing 50 acres or more where stormwater will discharge within a mile to special waters or to impaired waters, the application and SWPPP must be submitted for review at least 30 days prior to construction.
Special waters are described in Appendix A part B of the permit and are Outstanding Resource Value Waters (ORVW), including calcareous fens, trout lakes and trout streams. The permit also describes impaired waters as those waters identified as impaired under section 303 (d) of the Federal Clean Water Act and are impaired for at least one of four construction related impairments of phosphorus (nutrient eutrophication biological indicators), turbidity, dissolved oxygen or aquatic biota (fish bioassessment, aquatic plant bioassessment and aquatic macroinvertebrate bioassessment).
The MPCA has an online map tool that can be used to determine if the site is within one mile of a special or impaired water. The distance is measured using a straight line (aerial radius measurement) not the flow distance from the closest project discharge point to the nearest edge of the water body.
Your SWPPP must meet all terms and conditions of Part III and IV in the permit including a description of all erosion prevention and sediment control Best Management Practices (BMPs) to be utilized on the site to control sediment and other pollutant discharges from the site. The SWPPP must be prepared by an individual who is knowledgeable and trained in the preparation of SWPPPs. The SWPPP must be a combination of narrative, plan sheets and standard details that include the following components:
Amendments to your SWPPP are required when:
When a project replaces vegetation or other pervious surfaces with one or more acres of cumulative impervious surface, one inch of runoff from the new impervious surfaces must be retained on site through infiltration or other volume reduction methods.
If infiltration is not allowed due to wet soils, bedrock, industrial contaminates, karst or other prohibitions listed in Part III.D.1.k. of the permit, then other methods of volume reduction must be considered and if some volume reduction is achieved, any remainder of the one inch volume must be treated prior to discharge by methods such as the following:
The permanent stormwater management system chosen for the project must be designed and constructed according to the parameters listed in the permit.
The permittee must take action to stabilize exposed soils, including soil stockpiles, whenever it is known that land disturbing activity on any portion of the site will cease for 14 days or more. The stabilization must be initiated immediately and completed within 14 days. If the site has exposed soils that drain into a public water with Minnesota DNR “work in water restrictions” due to fish spawning time frames, the soils in that portion of the site that drain to and are within 200 feet of the water edge must be stabilized within 24 hours. Examples of soil stabilization include the following:
Other required erosion prevention practices:
Sediment control practices must minimize sediment from entering surface waters, curb and gutter systems, and storm sewer inlets. Regulated parties choose which practices are best for specific sites and practices must be installed according to permit timelines. Sediment controls to be used at the site include: Down gradient perimeter control established below the planned land disturbance and up gradient of vegetative buffers before work begins. Floating curtains are not an acceptable method of perimeter control near surface waters unless the work is on the shoreline or below the water line prohibiting the use of standard perimeter control and the floating curtain is located in the water as close to the shore as possible.
For sites within one mile of special or impaired waters, additional BMPs are required.
Additional BMPs are listed in Appendix A for the specific water of concern. Dependent upon the water listed these BMPs may include: