m
Line 31: Line 31:
 
<td>Filter Layer (optional)</td>
 
<td>Filter Layer (optional)</td>
 
<td>Sand filter layeris separated from base above and native soils with geotextile. Sand layer typically [http://www.astm.org/ ASTM] C33 gradation, 6 to 12 inches thick.</td>
 
<td>Sand filter layeris separated from base above and native soils with geotextile. Sand layer typically [http://www.astm.org/ ASTM] C33 gradation, 6 to 12 inches thick.</td>
<td>The sand layer may require a choker layer on surface to provide transition to base layerstone.</td>
+
<td>The Filter Layer is REQUIRED if using the permeable pavement system to meet permit requirements. The sand layer may require a choker layer on surface to provide transition to base layerstone.</td>
 
</tr>
 
</tr>
 
<tr>
 
<tr>

Revision as of 13:19, 19 March 2018

Summary of specifications for materials under the pavement surface. For more information, see the footnote (1). Reference or links to any specific commercial product, process, or service by trade name, trademark, service mark, manufacturer, or otherwise does not constitute or imply endorsement, recommendation, or favoring by the Minnesota Pollution Control Agency.
Link to this table

Material
Specification
Notes
Bedding/choker layer
  • Pervious concrete: None
  • Porous asphalt: 1inch of AASHTO No. 57 stone
  • PICP: 2 inches of AASHTO No. 8 stone (MnDOT 3127FA-3)
Washed free of fines
Reservoir Layer
  • Pervious concrete: AASHTO No. 57 stone or per hydraulic design
  • Porous asphalt:AASHTO No. 2, 3, or 5 stone
  • PICP: 4 inches of AASHTO No. 57 base and AASHTO No.2, 3 or 4 stone subbase
Stone layer thickness based on the pavement structural and hydraulic requirements. Stonewashed and free of fines. Recommended minimum void ratio = 0.4.
Underdrain (optional) Use 4 to 6 inch diameter perforated PVC (AASHTO M-252) pipe or corrugated polyethylene pipe. Perforated pipe installed for the full length of the permeable pavement cell, and non-perforated pipe, as needed,connected to storm drainage system.
Filter Layer (optional) Sand filter layeris separated from base above and native soils with geotextile. Sand layer typically ASTM C33 gradation, 6 to 12 inches thick. The Filter Layer is REQUIRED if using the permeable pavement system to meet permit requirements. The sand layer may require a choker layer on surface to provide transition to base layerstone.
Geotextile(optional) Comply with AASHTO M-288 Standard Specification for Geotextile Specification for Highway Applications, drainage and separation applications, Class I or II. Porous asphalt industry recommends non-woven geotextile.
Impermeable Liner Use a minimum 30mil PVC liner covered by 12 ounce/square yard non-woven geotextile. EPDM and HDPE liner material is also acceptable.
Observation Well Use a perforated 4 to 6 inch vertical PVC pipe (AASHTO M-252) with a lockable cap, installedflush with the surface (or under pavers).

1for additional information on materials referenced in this table (e.g. stone dimensions), see the following links: