<center><font size=3>'''This table shows construction requirements: Compost blanket application'''.</font size><br>
Construction requirements: Compost blanket application'''.</font size><br>
 
 
Link to this [[Construction requirements: Compost blanket application|table]]</center>
 
Link to this [[Construction requirements: Compost blanket application|table]]</center>
  
Line 33: Line 32:
  
 
</table>
 
</table>
 +
 +
[[category:table]]

Revision as of 17:04, 14 February 2013

This table shows construction requirements: Compost blanket application.
Link to this table
Annual Rainfall/Flow Rate Total Precipitation & Rainfall Erosivity Index Application Rate For Vegetated* Compost Surface Mulch Application Rate For Unvegetated Compost Surface Mulch
Low 1-25”, 20-90 ½ - ¾ ” (12.5 mm – 19 mm) 1” – 1 ½” (25 mm – 37.5mm)
Average 26-50”, 91-200 ¾ - 1” (19 mm – 25 mm) 1 ½” – 2” (37 mm – 50 mm)
High 51” and above, 201 and above 1-2” (25 mm – 50 mm) 2-4” (50mm – 100mm)
*These lower application rates should only be used in conjunction with seeding, and for compost blankets applied during the prescribed planting season for the particular region.