Summary of specifications for materials under the pavement surface. For more information, see the footnote (1). Reference or links to any specific commercial product, process, or service by trade name, trademark, service mark, manufacturer, or otherwise does not constitute or imply endorsement, recommendation, or favoring by the Minnesota Pollution Control Agency.
Link to this table
Bedding/choker layer |
|
Washed free of fines |
Reservoir Layer |
|
Stone layer thickness based on the pavement structural and hydraulic requirements. Stonewashed and free of fines. Recommended minimum void ratio = 0.4. |
Underdrain (optional) | Use 4 to 6 inch diameter perforated PVC (AASHTO M-252) pipe or corrugated polyethylene pipe. Perforated pipe installed for the full length of the permeable pavement cell, and non-perforated pipe, as needed,connected to storm drainage system. | |
Filter Layer (optional) | Sand filter layeris separated from base above and native soils with geotextile. Sand layer typically ASTM C33 gradation, 6 to 12 inches thick. | The Filter Layer is REQUIRED if using the permeable pavement system to meet permit requirements. The sand layer may require a choker layer on surface to provide transition to base layerstone. |
Geotextile(optional) | Comply with AASHTO M-288 Standard Specification for Geotextile Specification for Highway Applications, drainage and separation applications, Class I or II. Porous asphalt industry recommends non-woven geotextile. | |
Impermeable Liner | Use a minimum 30mil PVC liner covered by 12 ounce/square yard non-woven geotextile. EPDM and HDPE liner material is also acceptable. | |
Observation Well | Use a perforated 4 to 6 inch vertical PVC pipe (AASHTO M-252) with a lockable cap, installedflush with the surface (or under pavers). |
1for additional information on materials referenced in this table (e.g. stone dimensions), see the following links: