(Created page with "<font size=3>'''Stormwater pond cost estimate worksheet.'''</font size><br> Link to this table <table class="sortable"> <tr> <td>...") |
m |
||
Line 124: | Line 124: | ||
<tr> | <tr> | ||
<td>Sod - above vegetative bench</td> | <td>Sod - above vegetative bench</td> | ||
− | <td>square | + | <td>square yard</td> |
<td> </td> | <td> </td> | ||
<td>$4.50</td> | <td>$4.50</td> | ||
Line 233: | Line 233: | ||
<tr> | <tr> | ||
<td>Gate / valve operation</td> | <td>Gate / valve operation</td> | ||
− | <td>per | + | <td>per visit</td> |
<td> </td> | <td> </td> | ||
<td>$125.00</td> | <td>$125.00</td> | ||
Line 240: | Line 240: | ||
<tr> | <tr> | ||
<td>Inspection</td> | <td>Inspection</td> | ||
− | <td>per | + | <td>per visit</td> |
<td> </td> | <td> </td> | ||
<td>$125.00</td> | <td>$125.00</td> |
Stormwater pond cost estimate worksheet.
Link to this table
Project Title | ||||
Owner | ||||
Location | ||||
Project Number | ||||
Date | ||||
Description | Units | Quantity | Unit Cost | Total Estimated Price |
---|---|---|---|---|
Site Preparation | ||||
Tree removal - up to 12" diameter | each | $350.00 | $0.00 | |
Clear and grub brush | square yard | $1.50 | $0.00 | |
Tree protection - temp. fence | lineal foot | $3.00 | $0.00 | |
Topsoil - 6" depth, salvage on site | square yard | $4.50 | $0.00 | |
Site Formation | ||||
Excavation - 8' depth | square yard | $10.00 | $0.00 | |
Grading | square yard | $1.50 | $0.00 | |
Hauling off-site - 8' depth | square yard | $10.00 | $0.00 | |
Structural Components | ||||
Inlet structure | each | $2,000.00 | $0.00 | |
Overflow structure | each | $3,500.00 | $0.00 | |
Site Restoration | ||||
Sod - above vegetative bench | square yard | $4.50 | $0.00 | |
Soil preparation | square yard | $5.00 | $0.00 | |
Seeding - vegetative bench | square yard | $0.50 | $0.00 | |
Mulch | square yard | $2.00 | $0.00 | |
Subtotal | $0.00 | |||
10% Contingencies | $0.00 | |||
Subtotal | $0.00 | |||
Apply MN Location Factor | $0.00 | |||
TAL CONSTRUCTION COST | $0.00 | |||
Annual Operation and Maintenance | ||||
Debris removal | per visit | $100.00 | $0.00 | |
Remove invasive plants | per visit | $500.00 | $0.00 | |
Replant wetland vegetation | per plant | $10.00 | $0.00 | |
Repair erosion | square yard | $75.00 | $0.00 | |
Sediment removal and disposal | cubic yard | $10.00 | $0.00 | |
Mow | per visitt | $150.00 | $0.00 | |
Gate / valve operation | per visit | $125.00 | $0.00 | |
Inspection | per visit | $125.00 | $0.00 | |
Subtotal | $0.00 | |||
Apply MN Location Factor | $0.00 | |||
TOTAL ANNUAL O&M COST | $0.00 | |||
Minnesota Location Factors | ||||
Bemidji | 0.963 | |||
Brainerd | 1.003 | |||
Detroit Lakes | 0.962 | |||
Duluth | 0.991 | |||
Mankato | 0.990 | |||
Bemidji | 0.963 | |||
Minneapolis | 1.035 | |||
Rochester | 0.983 | |||
St. Paul | 1.000 | |||
St. Cloud | 1.002 | |||
Thief River Falls | 1.042 | |||
Willmar | 0.961 | |||
Windom | 0.935 | |||
Note: Suggested unit costs are based on RS Means prices for Spring, 2005, then factored into an area basis based on typical design features for Constructed Wetlands BMPs. To be used for preliminary cost estimation