m (2023) |
m (reformatted) |
||
Line 43: | Line 43: | ||
<big>Permittees must record all inspections and maintenance activities within 24 hours of being conducted and these records must be retained with the [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.33 SWPPP]. These records must include: | <big>Permittees must record all inspections and maintenance activities within 24 hours of being conducted and these records must be retained with the [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.33 SWPPP]. These records must include: | ||
− | + | <dl><dd>a. date and time of inspections; and </dl></dd> | |
− | + | <dl><dd>b. name of persons conducting inspections; and </dl></dd> | |
− | + | <dl><dd>c. accurate findings of inspections, including the specific location where corrective actions are needed; and </dl></dd> | |
− | + | <dl><dd>d. corrective actions taken (including dates, times, and party completing maintenance activities); and </dl></dd> | |
− | + | <dl><dd>e. date of all rainfall events greater than ½ inches in 24 hours, and the amount of rainfall for each event. Permittees must obtain rainfall amounts by either a properly maintained rain gauge installed onsite, a weather station that is within one (1) mile of your location, or a weather reporting system that provides site specific rainfall data from radar summaries; and </dl></dd> | |
− | + | <dl><dd>f. if permittees observe a discharge during the inspection, they must record and should photograph and describe the location of the discharge (i.e., color, odor, settled or suspended solids, oil sheen, and other obvious indicators of pollutants); and </dl></dd> | |
− | + | <dl><dd>g. any amendments to the SWPPP proposed as a result of the inspection must be documented as required in [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_6_SWPPP_Amendments Section 6] within seven (7) calendar days; and </dl></dd> | |
− | + | <dl><dd>h. all photographs of dewatering activities and documentation of nuisance conditions resulting from dewatering activities as described in section 10. </dl></dd> | |
</big> | </big> | ||
Inspections and Maintenance.
Permittees must ensure a trained person, as identified in item 21.2.b, will inspect the entire construction site at least once every seven (7) days during active construction and within 24 hours after a rainfall event greater than ½ inch in 24 hours.
Permittees must inspect and maintain all permanent stormwater treatment BMPs.
Permittees must inspect all erosion prevention and sediment control BMPs and Pollution Prevention Management Measures to ensure integrity and effectiveness. Permittees must repair, replace or supplement all nonfunctional BMPs with functional BMPs by the end of the next business day after discovery unless another time frame is specified in item 11.5 or 11.6. Permittees may take additional time if field conditions prevent access to the area.
During each inspection, permittees must inspect areas adjacent to the project surface waters, including drainage ditches and conveyance systems but not curb and gutter systems, for evidence of erosion and sediment deposition. Permittees must remove all deltas and sediment deposited in areas adjacent to the project, surface waters, including drainage ways, catch basins, and other drainage systems and restabilize the areas where sediment removal results in exposed soil. Permittees must complete removal and stabilization within seven (7) calendar days of discovery unless precluded by legal, regulatory, or physical access constraints. Permittees must use all reasonable efforts to obtain access. If precluded, removal and stabilization must take place within seven (7) days of obtaining access. Permittees are responsible for contacting all local, regional, state and federal authorities and receiving any applicable permits, prior to conducting any work in surface waters.
Permittees must inspect construction site vehicle exit locations, streets and curb and gutter systems within and adjacent to the project for sedimentation from erosion or tracked sediment from vehicles. Permittees must remove sediment from all paved surfaces within one (1) calendar day of discovery or, if applicable, within a shorter time to avoid a safety hazard to users of public streets.
Permittees must repair, replace or supplement all perimeter control devices when they become nonfunctional or the sediment reaches ½ of the height of the device.
Permittees must drain temporary and permanent sedimentation basins and remove the sediment when the depth of sediment collected in the basin reaches ½ the storage volume within 72 hours of discovery.
Permittee’s must inspect and photograph dewatering discharges at the beginning and at least once every 24 hours during operation. Dewatering discharges that only last for minutes, as opposed to hours and do not reach a surface water, do not require photographs or documentation
Permittees must ensure that at least one individual present on the site (or available to the project site in three (3) calendar days) is trained in the job duties described in item 21.2.b.
Permittees may adjust the inspection schedule described in item 11.2 as follows:
Permittees must record all inspections and maintenance activities within 24 hours of being conducted and these records must be retained with the SWPPP. These records must include:
This page was last edited on 7 August 2023, at 21:23.