Green roof construction can be complex and involve many different trades working in a small space. A pre-construction meeting is recommended prior to beginning any construction on the roof to ensure construction sequencing will maximize efficiency and minimize conflicts between the various trades that need to access the roof. The meeting should include all green roof related installers and designers. Installers present at the meeting should include roofing, green roof, irrigation, leak detection, lightning protection, electrical, glaziers, mechanical, and general contractor, as well any others involved in the green roof project. Designers should include roofing consultant, green roof designer, irrigation designer, electrical and mechanical engineers as well any others involved in the green roof project.
 
Green roof construction can be complex and involve many different trades working in a small space. A pre-construction meeting is recommended prior to beginning any construction on the roof to ensure construction sequencing will maximize efficiency and minimize conflicts between the various trades that need to access the roof. The meeting should include all green roof related installers and designers. Installers present at the meeting should include roofing, green roof, irrigation, leak detection, lightning protection, electrical, glaziers, mechanical, and general contractor, as well any others involved in the green roof project. Designers should include roofing consultant, green roof designer, irrigation designer, electrical and mechanical engineers as well any others involved in the green roof project.
Line 11: Line 11:
 
*Whenever possible, install green roof only after there will be no more traffic by other trades, such as, for example, window installers or mechanical equipment installers.
 
*Whenever possible, install green roof only after there will be no more traffic by other trades, such as, for example, window installers or mechanical equipment installers.
  
 +
<noinclude>==Related pages==
 +
*[[Green roofs]]
 +
*[[Overview for green roofs]]
 +
*[[Types of green roofs]]
 +
*[[Design criteria for green roofs]]
 +
*[[Construction specifications for green roofs]]
 +
<!--*[[Construction observations for green roofs]]-->
 +
*[[Assessing the performance of green roofs]]
 +
*[[Operation and maintenance of green roofs]]
 +
<!--*[[Calculating credits for green roofs]]-->
 +
*[[Cost-benefit considerations for green roofs]]
 +
*[[Plant lists for green roofs]]
 +
<!--*[[Additional considerations for green roofs]]-->
 +
*[[Case studies for green roofs]]
 +
*[[Links for green roofs]]
 +
*[[References for green roofs]]
 +
*[[Supporting material for green roofs]]
 +
*[[Green roofs terminology and glossary]]
 +
*[[Green roof fact sheet]]
 +
*[[Requirements, recommendations and information for using green roofs as a BMP in the MIDS calculator]]</noinclude>
 +
 +
 
<noinclude>[[Category:Construction specifications]]</noinclude>
 
<noinclude>[[Category:Construction specifications]]</noinclude>

Revision as of 13:08, 22 August 2013

This site is currently undergoing final review. For more information, open this link.
The anticipated review period for this page is June through September 2013

Green roof construction can be complex and involve many different trades working in a small space. A pre-construction meeting is recommended prior to beginning any construction on the roof to ensure construction sequencing will maximize efficiency and minimize conflicts between the various trades that need to access the roof. The meeting should include all green roof related installers and designers. Installers present at the meeting should include roofing, green roof, irrigation, leak detection, lightning protection, electrical, glaziers, mechanical, and general contractor, as well any others involved in the green roof project. Designers should include roofing consultant, green roof designer, irrigation designer, electrical and mechanical engineers as well any others involved in the green roof project.

Key factors in determining construction sequencing include the following.

  • Do not begin installation until required submittals are approved.
  • Staging: stay within load limits throughout installation
  • Protect all materials on roof from wind and erosion at all times
  • Perform leak detection test after installation of membrane and again after all work on roof is done. If there is signficant construction traffic on the roof after leak detection, from green roof contractor or any other trades, leak detection shall be repeated.
  • Ensure there will be a means to keep vegetation watered during and after vegetation installation.
  • Whenever possible, install green roof only after there will be no more traffic by other trades, such as, for example, window installers or mechanical equipment installers.