As a part of the response to the Kohlman Lake TMDL (Total Maximum Daily Load) report, which calls for the reduction of phosphorus from both its watershed and the sediment in the lake bottom, the Maplewood Mall recently underwent a comprehensive redesign of its 35 acre parking lot. The four-phase construction process of this redesign took place between 2009 and 2012. This parking lot was designed by Barr Engineering Company on behalf of the Ramsey-Washington Metro Watershed District (who sponsored the project) and Simon Property Group (who owns Maplewood mall). This redesign was completed with the intent of capturing one inch of runoff from 90% of the parking lot area, while reducing at least 90% of the sediment load and 60% of the phosphorous load leaving the site.
To help meet the proposed stormwater goals, this project included 375 trees across the project site. Two hundred trees were placed in tree trenches and 175 trees were placed in rainwater gardens. This case study will focus on the planting methods for the trees planted within the tree trenches. Each tree placed in a tree trench was planted using a Stockholm Tree Trench Method for Stormwater.
The Stockholm Tree Trench Method uses angular granite rock to bear the load of the pavement profile and vehicular traffic above. The void space between the angular granite was filled with soil, which is washed into the angular granite and the soil does not need to be compacted to support loads. This non-compacted soil and remaining void space between the angular granite are then available for use by trees as both a growing medium and space for gaseous exchange to and from the roots.
Approximately 820 cubic feet of soil/angular granite and clear angular granite was provided per tree on average. The average installed cost per tree using this method was $18,000. This cost includes soil treatment and all other aspects of the tree trench installation such as storm sewers, asphalt pavement profile, concrete curb, tree grates, cages, etc. The trees received supplemental watering via 15 gallon capacity gator bags for the first two years of growth. Following the two-year establishment period, the trees will only receive water from above and below during rainfall events. At the time of the writing of this case study, October 2013, the planted trees are in good to excellent condition. When initially planted, the tree canopy covered less than 1 percent of the site, at 20 years growth, the trees are projected to cover 17 percent of the site with canopy.
The designer stated that in future work using similar planting techniques they would modify their maintenance protocol to include biannual fertilization at the tree root ball for the first two years of growth (per the advice from the street tree specialists in Stockholm, Sweden) and use larger capacity gator bags to better facilitate watering during the first two years of growth.
The stormwater goals of this project were as follows:
In 2011 and 2012, Barr Engineering Company worked with the Ramsey-Washington Metro Watershed District to develop a monitoring plan and to create an XPSWMM model to determine the reduction in runoff volume as a result of this project.
The following monitoring was planned for 2013:
At the time of writing of this case study, the analysis of the data was still being completed and the monitoring report had not been released.
For more information, see:
The Central Corridor LRT line is located within a highly-urbanized and heavily-paved corridor connecting downtown St. Paul and downtown Minneapolis. This corridor is made up of 111 acres of impervious surface. The stormwater runoff from the impervious surfaces ultimately drains to the Mississippi River via the municipal storm drain system and enters the Mississippi at fast speeds, carrying both sediment and pollutant loads. Portions of the river are impaired for turbidity, nutrients, and bacteria.
As this project is located within the jurisdiction of the Capitol Region Watershed District (CRWD), it was required to comply with the CRWDs rules for stormwater management. These rules require that the site capture and retain the first inch of rainfall on site, reducing the volume of stormwater.
Four different green infrastructure practices were used in conjunction to help meet the requirements outlined by CRWD, but this case study focus on the integrated tree trench systems. These systems stretch out along both sides of the corridor for over five miles of the LRT corridor. The tree trench systems are approximately 10 feet wide, with a 3 foot deep profile of CU structural soil and 1.5 feet of clear aggregate below that. These trenches provide approximately 792,000 cubic feet of CU structural soil in total for the project (approximately 634 cubic feet of CU structural soil per tree).
These tree trench systems are layered systems of trees, porous pavers, CU Structural Soil, drainage rock, and a 12" perforated PVC pipe that directs runoff from the street into the clear rock in the integrated tree trench systems. Where possible and appropriate, these systems are paired with existing soils with high infiltration rates. In addition to the structural components mentioned above, approximately 1,250 new trees have been planted within the integrated tree trenches. The total bid for the integrated tree trench system was $3.29 million (approximately $2,632 per tree). Please note that this bid was lump-sum and is likely low in regard to final costs. The engineer's estimate for the system was approximately $6.0 million (approximately $4,800 per tree).
The goals of the green infrastructure, including the integrated tree trench systems:
It is estimated that the green infrastructure practices will:
Monitoring is taking place along the integrated tree trench systems, which includes the following:
For more information, see:
http://www.metrocouncil.org/Transportation/Projects/Current-Projects/Central-Corridor.aspx
Project Description Planted in 1985, the Tryon Street Mall Trees are some of the oldest trees planted using suspended pavement. The pavement around the trees is held slightly above the soil by 3 foot tall underground pillars so that the soil under the pavement is not compacted beyond root-limiting densities by the pavement loads. In 2013, the willow oaks planted had an average diameter at breast height of 18 inches and an average height of 71 feet (Smiley, 2013). In addition to growing big trees, the system modeled a 10% reduction in peak flows (peak storm event) to the City’s stormwater system (EPA, no publication year given). As of 2013, almost 30 years after planting, the trees are flourishing (see Figures 12.15 and 12.16).
The MARQ2 project (Marquette Ave and 2nd Ave Busways) originated in response to the Minneapolis Ten Year Transportation Plan, to improve transit service by redefining lanes, lane widths, and sidewalk zones and widths. Stakeholders requested that healthy trees be part of the project.
To maximize the trees’ health, lifespan, as well as maximize stormwater and other ecological services, the designers maximized rootable soil volume for each tree using Silva Cells, a proprietary soil cell system that supports suspended pavement.
It is estimated that the average urban tree only survives about 13 years (Skierra and Moll 1992), not nearly long enough to be able to provide the ecological and stormwater treatment services that they are able to provide at maturity. A primary reason for the shortened lifespan of urban trees is inadequate soil volume. Soil cells are modular structures that provide uncompacted soil volumes under paved surfaces and can support up to HS20 loading (US Standard Bridge Loading), making it possible to provide urban trees with large soil volumes even in urban areas with little open space. The uncompacted soil volume in soil cells can also be used for stormwater treatment, creating a bioretention system under paved surfaces. Using structural cells with bioretention soil, stormwater becomes an asset as a way to water the trees. The trees in turn will help cleanse and abstract storm water runoff.
The trees and soil cells in this project collect runoff from the sidewalks along 2 of Minneapolis’ main downtown streets (Marquette and 2nd Avenues) through pervious pavers that drain into the underlying structural cells. One of the soil cell groups also collects roof runoff from adjacent building scuppers.
While the amount of runoff treated per tree varies from block to block and from tree to tree, on average, each tree pit collects runoff from about a 300 square foot watershed. With 167 trees, this adds up to an estimated 50,118 s.f., or 1.15 acres of sidewalk runoff captured. The loam soil in the structural cells therefore has enough capacity to capture runoff from a 1” rain event from 5 times as much impervious surface as it currently captures. In other words, the soil in the structural cells has capacity to capture 1” of rain from 5.75 acres of impervious surface.
The City of Minneapolis is reserving this extra soil stormwater holding and infiltration capacity for future routing of street runoff to the cells.
As trees grow larger, they will also contribute more and more to stormwater capture through interception and evapotranspiration.
Project Summary: This MnDOT overlook directs runoff from the access road to a center island/historic interpretive area through ADA curb cuts that also double up as stormwater curb cuts. Turf in the interpretive area is planted into an 80% sand/20% compost bioretention soil mix. Trees are planted into this area in MnDOT select topsoil borrow that extends to a 5 ft radius from each tree trunk. A 6” deep fine filter aggregate layer that spans under the bioretention soil and topsoil borrow provides for drainage to the underdrain, which is wrapped in coarse filter aggregate.
Project plans are attached, including a SWPPP plan, estimated quantities, and tree protection, and tree planting details.