Maintenance is necessary for a stormwater pond to operate as designed on a long-term basis. The pollutant removal, channel protection, and flood control capabilities of ponds will decrease if:
Pond maintenance activities range in terms of the level of effort and expertise required to perform them. Routine pond and wetland maintenance, such as mowing and removing debris or trash, is needed multiple times each year. Owners may consider an “adopt-a-pond” program in which properly trained citizen volunteers perform basic landscape maintenance activities (the City of Plymouth, for example, has instituted such a program). More significant maintenance such as removing accumulated sediment is needed less frequently, but requires more skilled labor and special equipment. Inspection and repair of critical structural features such as embankments and risers, needs to be performed by a qualified professional (e.g., structural engineer) that has experience in the construction, inspection, and repair of these features.
Implicit in the design guidance in the previous sections, many design elements of pond systems can minimize the maintenance burden and maintain pollutant removal efficiency. Key maintenance considerations are providing access for inspection and maintenance, and designing all outlets and the principal spillway to minimize clogging.
Stormwater ponds can be designed, constructed and maintained to minimize the likelihood of being desirable habitat for mosquito populations. Designs that incorporate constant inflows and outflows, habitat for natural predators, and constant permanent pool elevations limit the conditions typical of mosquito breeding habitat (see section on mosquito control).
The construction phase is another critical step where O&M issues can be minimized or avoided.
Inspections during construction are needed to ensure that the practice is built in accordance with the approved design standards and specifications. Detailed inspection checklists should be used that include sign-offs by qualified individuals at critical stages of construction, to ensure that the contractor’s interpretation of the plan is acceptable to the professional designer. An example construction phase inspection checklist is provided in the table below.
Stormwater pond/wetland - construction inspection checklist.
Link to this table
To access an Excel version of form (for field use), click here.
Project: | ||
Location: | ||
Site Status: | ||
Date: | ||
Time: | ||
Inspector: | ||
Construction Sequence | Satisfactory/Unsatisfactory | Comments |
---|---|---|
1. Pre-Construction/Materials and Equipment | ||
Pre-construction meeting | ||
Pipe and appurtenances on-site prior to construction and dimensions checked | ||
1. Material (including protective coating, if specified) | ||
2. Diameter | ||
3. Dimensions of metal riser or pre-cast concrete outlet structure | ||
4. Required dimensions between water control structures (orifices, weirs, etc.) are in accordance with approved plans | ||
5. Barrel stub for prefabricated pipe structures at proper angle for design barrel slope | ||
6. Number and dimensions of prefabricated antiseep collars | ||
7. Watertight connectors and gaskets | ||
8. Outlet drain valve | ||
Project benchmark near pond site | ||
Facility location staked out | ||
Equipment for temporary de-watering | ||
Temporary erosion and sediment control in place | ||
2. Subgrade Preparation | ||
Area beneath embankment stripped of all vegetation, topsoil, and organic matter | ||
3. Pipe Installation | ||
Method of installation detailed on plans | ||
A. Bed preparation | ||
Installation trench excavated with specified side slopes | ||
Stable, uniform, dry subgrade of relatively impervious material (If subgrade is wet, contractor shall have defined steps before proceeding with installation) | ||
Invert at proper elevation and grade | ||
B. Pipe placement | ||
Metal / plastic pipe | ||
1. Watertight connectors and gaskets properly installed | ||
2. Anti-seep collars properly spaced and having watertight connections to pipe | ||
3. Backfill placed and tamped by hand under “haunches” of pipe | ||
4. Remaining backfill placed in max. 8 inch lifts using small power tamping equipment until 2 feet cover over pipe is reached | ||
Concrete pipe | ||
1. Pipe set on blocks or concrete slab for pouring of low cradle | ||
2. Pipe installed with rubber gasket joints with no spalling in gasket interface area | ||
3. Excavation for lower half of anti-seep collar(s) with reinforcing steel set | ||
4. Entire area where anti-seep collar(s) will come in contact with pipe coated with mastic or other approved waterproof sealant | ||
5. Low cradle and bottom half of anti-seep collar installed as monolithic pour and of an approved mix | ||
6. Upper half of anti-seep collar(s) formed with reinforcing steel set | ||
7. Concrete for collar of an approved mix and vibrated into place (protected from freezing while curing, if necessary) | ||
8. Forms stripped and collar inspected for honeycomb prior to backfilling. Parge if necessary. | ||
C. Backfilling | ||
Fill placed in maximum 8 inch lifts | ||
Backfill taken minimum 2 feet above top of antiseep collar elevation before traversing with heavy equipment | ||
4. Riser / Outlet Structure Installation | ||
Riser located within embankment | ||
A. Metal riser | ||
Riser base excavated or formed on stable subgrade to design dimensions | ||
Set on blocks to design elevations and plumbed | ||
Reinforcing bars placed at right angles and projecting into sides of riser | ||
Concrete poured so as to fill inside of riser to invert of barrel | ||
B. Pre-cast concrete structurer | ||
Dry and stable subgrade | ||
Riser base set to design elevation | ||
If more than one section, no spalling in gasket interface area; gasket or approved caulking material placed securely | ||
Watertight and structurally sound collar or gasket joint where structure connects to pipe spillway | ||
C. Poured concrete structure | ||
Footing excavated or formed on stable subgrade, to design dimensions with reinforcing steel set | ||
Structure formed to design dimensions, with reinforcing steel set as per plan | ||
Concrete of an approved mix and vibrated into place (protected from freezing while curing, if necessary) | ||
Forms stripped & inspected for honeycomb prior to backfilling; parge if necessary | ||
5. Embankment Construction | ||
Fill material | ||
Compaction | ||
Embankment | ||
1. Fill placed in specified lifts and compacted with appropriate equipment | ||
2. Constructed to design cross-section, side slopes and top width | ||
3. Constructed to design elevation plus allowance for settlement | ||
6. Impounded Area Construction | ||
Excavated / graded to design contours and side slopes | ||
Inlet pipes have adequate outfall protection | ||
Forebay(s) constructed per plans | ||
Pond benches construction per plans | ||
7. Earth Emergency Spillway Construction | ||
Spillway located in cut or structurally stabilized with riprap, gabions, concrete, etc. | ||
Excavated to proper cross-section, side slopes and bottom width | ||
Entrance channel, crest, and exit channel constructed to design grades and elevations | ||
8. Outlet Protection | ||
A. End section | ||
Securely in place and properly backfilled | ||
B. Endwall | ||
Footing excavated or formed on stable subgrade, to design dimensions and reinforcing steel set, if specified | ||
Endwall formed to design dimensions with reinforcing steel set as per plan | ||
Concrete of an approved mix and vibrated into place (protected from freezing, if necessary) | ||
Forms stripped and structure inspected for honeycomb prior to backfilling; parge if necessary | ||
C. Riprap apron / channel | ||
Apron / channel excavated to design cross-section with proper transition to existing ground | ||
Filter fabric in place | ||
Stone sized as per plan and uniformly place at the thickness specified | ||
9. Vegetative Stabilization | ||
Approved seed mixture or sod | ||
Proper surface preparation and required soil mendments | ||
Excelsior mat or other stabilization, as per plan | ||
10. Miscellaneous | ||
Drain for ponds having a permanent pool | ||
Trash rack / anti-vortex device secured to outlet structure | ||
Trash protection for low flow pipes, orifices, etc. | ||
Fencing (when required) | ||
Access road | ||
Set aside for clean-out maintenance | ||
11. Stormwater Wetlands | ||
Adequate water balance | ||
Variety of depth zones present | ||
Approved pondscaping plan in place and budget for additional plantings | ||
Plants and materials ordered 6 months prior to construction | ||
Construction planned to allow for adequate planting and establishment of plant community (April-June planting window) | ||
12. Final Inspection | ||
Construction sediment removed from settling basin | ||
Contributing drainage area stabilized | ||
Vegetation established per specifications | ||
Inlet and outlet structures operational | ||
Comments: | ||
Actions to be Taken: |
It is Highly Recommended that the O&M plan include a provision to lower the level of the permanent pool in the late fall, to provide additional retention storage for snowmelt runoff and ensure that some permanent pool storage is available above the ice (the permanent pool should not be completely eliminated nor allowed to freeze through completely).
Some important post construction maintenance considerations are provided below. More detailed maintenance guidance can be found in the Pond and Wetland Maintenance Guidebook (CWP, 2004).