Box 1

Did you gather the site information necessary to proceed through the flow chart?

Yes

No or Unsure

Box 2

Prior to using the flow chart, gather the following preliminary information.

  • Conduct site review
  • Define performance goal

Conduct site review

PROCEED TO THE NEXT STEP

Box 3

  • New and redevelopment projects: Retain on site a volume of 1.1 inches from impervious surfaces
  • Linear projects: Retain on site the larger of 1.1 inches from all new or 0.55 inches from all new and fully reconstructed impervious surfaces

PROCEED TO THE FIRST QUESTION

Links

Box 4

Does project create one acre or more of new and/or fully reconstructed impervious surfaces?

PREVIOUS QUESTION and ANSWER: The previous question] defined the performance goals.

Box 5

MIDS PERFORMANCE GOAL DOES NOT APPLY
The project creates less than 1 acre of impervious surface.

Box 6

Is the project linear?

image of a linear project
Example of a linear project

Yes

No

PREVIOUS QUESTION and ANSWER: Does project create one acre or more of new and/or fully reconstructed impervious surfaces? Answer - Yes