The following terminology is used throughout this design section:
HIGHLY RECOMMENDED - Indicates design guidance that is extremely beneficial or necessary for proper functioning of the bioretention practice, but not specifically required by the MPCA CGP.
RECOMMENDED - Indicates design guidance that is helpful for bioretention practice performance but not critical to the design.
Before deciding to use a filtration device for stormwater management, it is helpful to consider several items that bear on the feasibility of using such a device at a given location. The following list of considerations will help in making an initial judgment as to whether or not a filtration device is the appropriate BMP for the site.
For purposes of this guidance, it is assumed that the definition of a stormwater pond includes a stormwater filtration system.
It is HIGHLY RECOMMENDED that a flow splitter or diversion structure be provided to divert the Vwq to media filters and allow larger flows to bypass the practice. Where a flow splitter is not used, it is HIGHLY RECOMMENDED that contributing drainage areas be limited to approximately 0.5 acres and an overflow be provided within the practice to pass part of the Vwq to a stabilized watercourse or storm drain. It is also HIGHLY RECOMMENDED that overflow associated with the Vp10 or Vp100 storm (depending on local drainage criteria) be controlled such that velocities are non-erosive at the outlet point to prevent downstream slope erosion. Weirs are common overflow systems within media filters. It is HIGHLY RECOMMENDED that the flow splitter be designed such that 75 percent of the Vwq can enter the treatment system prior to flow bypass occurring at the flow splitter. The overflow weir between the sedimentation and filtration chambers may be adjusted to be lower in elevation than the flow splitter weir to minimize bypass of the filter system prior to inflow filling the 75 percent Vwq storage.
It is HIGHLY RECOMMENDED that media filters be equipped with a minimum 8 inches diameter underdrain in a 1 foot gravel bed. Increasing the diameter of the underdrain makes freezing less likely. The porous gravel bed prevents standing water in the system by promoting drainage. Gravel is also less susceptible to frost heaving than finer grained media. It is also HIGHLY RECOMMENDED that a permeable filter fabric be placed between the underdrain and gravel layer but not extend laterally from the pipe more than two feet on either side
Dry or wet pre-treatment is REQUIRED prior to media filter treatment pre-treatment volume equivalent to at least 25 percent of the computed Vwq is HIGHLY RECOMMENDED). The typical method is a sedimentation basin with a RECOMMENDED minimum length to width ratio of 2:1. The Camp-Hazen equation is used to compute the target surface area for media filters requiring full sedimentation for pre-treatment (WSDE, 1992).
The RECOMMENDED pre-treatment for vegetative filters is a level spreader that allows coarse sediment to settle and evenly distributes flow across the full width of the filter.
The RECOMMENDED pre-treatment for media / vegetative filters such as dry swales is to install plunge pools where concentrated flows enter and to place level spreaders where lateral flows enter.
Additional pre-treatment]] measures include filter strips and street / parking lot sweeping. Street / parking lot sweeping may be considered pre-treatment in the case of a parking lot island or other area where spatial limitations make structural pre-treatment measures unfeasible.
When using media filters to treat runoff from potential stormwater hotspots (PSHs), particularly in sensitive watersheds, it is HIGHLY RECOMMENDED that additional practices be incorporated as partial treatment during the winter when the filter bed may be frozen.
The following guidelines are applicable to the actual treatment area of a filtration facility:
It is REQUIRED that impervious area construction be completed and pervious areas established with dense and healthy vegetation (see Minnesota plant lists) prior to introduction of stormwater into a filtration practice.
Surface filters can have a grass cover to aid in pollutant adsorption. The grass should be capable of withstanding frequent periods of inundation and drought.
Additional information on safety for construction sites is available from OSHA.
The following steps outline a recommended design procedure for media filters. Except where indicated, procedures are consistent with requirements for compliance with the MPCA Permit for new construction.
Make a preliminary judgment as to whether site conditions are appropriate for the use of a surface or perimeter sand filter, and identify the function of the filter in the overall treatment system.
Once the Physical Suitability Evaluation is complete, apply the better site design principles in sizing and locating the filtration practice(s) on the development site. Given the drainage area, select the appropriate filtration practice for the first iteration of the design process.
Note: Information collected during the Physical Suitability Evaluation (see Step 2) should be used to explore the potential for multiple filtration practices versus relying on a single facility. The use of smaller filtration practices dispersed around a development is usually more sustainable than a single regional facility that is more likely to have maintenance problems (Source: Wisconsin Department of Natural Resources Conservation Practice Standards, 2004).
Calculate the Water Quality Volume (Vwq), Channel Protection Volume (Vcp), Overbank Flood Protection Volume (Vp10), and the Extreme Flood Volume (Vp100) where applicable.
If part of the overall Vwq is to be treated by other BMPs, subtract that portion from the Vwq to determine the part of the Vwq to be treated by the filter. See the Unified sizing criteria section for Details.
The peak rate of discharge for water quality design storm is needed for sizing of off-line diversion structures. See the Unified sizing criteria section for details.
A flow regulator (or flow splitter diversion structure) should be supplied to divert the Vwq to the sand filter facility. This is generally accomplished by setting the bypass weir within the diversion to the elevation of the water quality volume within the practice. Please refer to the adjustable diversion detail found in the Computer-aided design and drafting (CAD/CADD) drawings section.
Size low flow orifice, weir, or other device to pass Qwq.
The filter area is sized using the following equation (based on Darcy’s Law)
\(A_f = (V_{wq}) (d_f) / (k) (h_f + d_f) (t_f)\)
Where:
Set preliminary dimensions of filtration basin chamber. The following guidelines are HIGHLY RECOMMENDED.
Sedimentation chamber size is dictated by volume requirements, maximum ponding depth, and the particle settling ability. It is HIGHLY RECOMMENDED that the sedimentation chamber be sized to at least 25 percent of the computed Vwq for surface sand filters and 50% for perimeter sand filters and have a length-to-width ratio of 2:1.
The Camp-Hazen equation is used to compute the surface area based on particle settling
\(A_s = (Q_o/w) * ln (1-E)\)
where:
assuming:
Then, for I < 75 percent the equation reduces to
\(As = (0.066) (V_{wq})\)
or for I ≥ 75 percent
\(As = (0.0081) (V_{wq})\)
where:
Use the table below to set the preliminary surface area of the settling chamber. Select the type of filter, imperviousness of the drainage area, and maximum ponding depth.
Settling chamber surface area for sand filters and perimeter sand filters.
Link to this table
Maximum Ponding Depth (feet) | |||
---|---|---|---|
Impervious | ≥ 75% | (0.25 Vwq) / Dmax | (0.25 Vwq) / Dmax |
< 75% | (0.25 Vwq) / Dmax | 0.066 Vwq | |
Perimeter Sand Filter | Maximum Ponding Depth (feet) | ||
<7.5 | 8 to 10 | ||
Impervious | ≥ 75% | (0.5 Vwq) / Dmax | (0.5 Vwq) / Dmax |
< 75% | (0.25 Vwq) / Dmax | 0.066 Vwq |
\(V_{min} = 0.75 * V_{wq}\)
\(V_{min} = 0.75 * V_{wq} = V_s + V_f + V_{ftemp}\)
This table shows sand material specifications.
Link to this table
Parameter | specification | Size | Notes |
---|---|---|---|
Sand | clean AASHTO M-6 or ASTM C-33 concrete sand | 0.02” to 0.04” | Sand substitutions such as Diabase and Graystone #10 are not acceptable. No calcium carbonated or dolomitic sand substitutions are acceptable. Rock dust cannot be substituted for sand. |
Underdrain Gravel | AASHTO M-43 | 1.5” to 3.5” | |
Geotextile Fabric (if required) |
ASTM D-4833 (puncture strength - 125 lb.) ASTM D-1117 (Mullen Burst Strength - 400 psi) ASTM D-4632 (Tensile Strength - 300 lb.) |
0.08” thick equivalent opening size of #80 sieve | Must maintain 125 gpm per sq. ft. flow rate. Note: a 4” pea gravel layer may be substituted for geotextiles meant to separate sand filter layers. |
Impermeable Liner (if required) |
ASTM D-4833 (thickness) ASTM D-412 (tensile strength 1,100 lb., elongation 200%) ASTM D-624 (Tear resistance - 150 lb./in) ASTM D-471 (water adsorption: +8 to -2% mass) |
30 mil thickness | Liner to be ultraviolet resistant. A geotextile fabric should be used to protect the liner from puncture. |
Under-drain Piping | ASTM D-1785 or AASHTO M-278 | minimum 4” rigid schedule 40 PVC | 3/8” perf. @ 6” on center, 4 holes per row; minimum of 3” washed #57 stone over pipes; not necessary underneath pipes |
Surface sand filter:
Perimeter sand filter:
Follow the design procedures identified in the section on Unified sizing criteria to determine the volume control and peak discharge requirements for water quality, recharge (not required), channel protection, overbank flood and extreme storm. Adapt these values to local regulations, if any exist.
Model the proposed development scenario using a surface water model appropriate for the hydrologic and hydraulic design considerations specific to the site (see also the section on stormwater modeling). This includes defining the parameters of the filtration practice defined above: pond elevation and area (defines the pond volume), filtration rate and method of application (effective filtration area), and outlet structure and/or flow diversion information. The results of this analysis can be used to determine whether or not the proposed design meets the applicable requirements. If not, the design will have to be re-evaluated.
Additional flows that cannot be infiltrated or filtered in 48 hours should be routed to bypass the system through a stabilized discharge point. This criterion was established to provide the following: wet-dry cycling between rainfall events; unsuitable mosquito breeding habitat; suitable habitat for vegetation; aerobic conditions; and storage for back-to-back precipitation events.
The period of inundation is defined as the time from the high water level in the practice to 3 to 6 inches above the invert of the outlet structure or drain tile or bottom of the facility. It is assumed that this range is less than 1/5 the bounce in the filtration practice.
See Major design elements section for guidance on preparing vegetation and landscaping management plan.
See Operation and maintenance section for guidance on preparing an O&M plan.
See Cost considerations section for guidance on preparing a cost estimate that includes both construction and maintenance costs.
The following steps outline a recommended design procedure for vegetative filters in compliance with the MPCA Permit for new construction. Design recommendations beyond those specifically required by the permit are also included and marked accordingly.
Make a preliminary judgment as to whether site conditions are appropriate for the use of a vegetative filter, and identify the function of the filter in the overall treatment system
A. Consider basic issues for initial suitability screening, including:
B. Determine how the vegetative filter will fit into the overall stormwater treatment system
A. Determine whether the vegetative filter must comply with the MPCA Permit.
B. Check with local officials, watershed organizations, and other agencies to determine if there are any additional restrictions and/or surface water or watershed requirements that may apply.
Once the physical suitability evaluation is complete, it is HIGHLY RECOMMENDED that the better site design principles be applied in sizing and locating the filtration practice(s) on the development site. Given the drainage area, select the appropriate filtration practice for the first iteration of the design process.
Note: Information collected during the physical suitability evaluation (see Step 1) should be used to explore the potential for multiple filtration practices versus relying on a single facility. The use of smaller filtration practices dispersed around a development is usually more sustainable that a single regional facility that is more likely to have maintenance problems (Source: Wisconsin Department of Natural Resources Conservation Practice Standards, 2004)
Calculate the Water Quality Volume (Vwq), Channel Protection Volume (Vcp), Overbank Flood Protection Volume (Vp10), and the Extreme Flood Volume (Vp100).
If the vegetative filter is being designed to meet the requirements of the MPCA Permit, the REQUIRED treatment volume is the water quality volume of 1 inch of runoff from the new impervious surfaces created from the project. If part of the overall Vwq is to be treated by other BMPs, subtract that portion from the Vwq to determine the part of the Vwq to be treated by the filter.
For filter strips, compute the following design parameters:
a. Calculate the maximum discharge loading per foot of filter strip width
\( q = (0.00236/n)Y^{1.67}S^{0.5} \)
Where:
b. Use a recommended hydrologic model to compute Qwq
c. Minimum Filter Width (in feet) = Qwq / q
Where:
One alternative is a level spreader that allows coarse sediment to settle and evenly distributes flow across the full width of the filter. Pre-treatment could be provided with plunge pools where concentrated flows enter and with level spreaders where lateral flows enter. Additional pre-treatment measures include filter strips and street/parking lot sweeping. Street/parking lot sweeping may be considered pre-treatment in the case of a parking lot island or other area where spatial limitations make structural pre-treatment measures unfeasible.
Storage volume created for pre-treatment counts toward the total Vwq requirement, and should be subtracted from the Vwq for subsequent calculations.
Wet and dry swales:
If the system is on-line, channels should be sized to convey runoff from the overbank flood event (Vp10) safely with a minimum of 6 inches of freeboard and without damage to adjacent property. The peak velocity for the 2-year storm must be nonerosive for the soil and vegetative cover provided.
The channel and under-drain excavation should be limited to the width and depth specified in the design. The bottom of the excavated trench shall not be loaded in a way that causes soil compaction, and scarified prior to placement of gravel and permeable soil. The sides of the channel shall be trimmed of all large roots. The sidewalls shall be uniform with no voids and scarified prior to backfilling.
Wet and Dry Swales: Checkdams
Filter Strips: Berms
Dry swale: The bed of the dry swale consists of a permeable soil layer of at least 30 inches in depth, above an 8-inch diameter perforated PVC pipe (AASHTO M 252) longitudinal under-drain in a 12-inch gravel layer. The soil media should have an infiltration rate of at least 0.5 feet per day (fpd) with a maximum of 1.5 fpd and contain a high level of organic material to facilitate pollutant removal. A permeable filter fabric is placed between the gravel layer and the overlying soil. Dry swale channels are sized to store and filter the entire Vwq and allow for full filtering through the permeable soil layer.
Check for erosive velocities and modify design as appropriate based on local conveyance regulations. Provide 6 inches of freeboard.
Design control to pass Vwq in 48 hours.
Inlets to swales must be provided with energy dissipaters such as riprap or geotextile reinforcement. Pre-treatment of runoff in both a dry and wet swale system is typically provided by a sediment forebay located at the inlet. Enhanced swale systems that receive direct concentrated runoff may have a 6-inch drop to a pea gravel diaphragm flow spreader at the upstream end of the control. A pea gravel diaphragm and gentle side slopes should be provided along the top of channels to provide pre-treatment for lateral sheet flows. The under-drain system should discharge to the storm drainage infrastructure or a stable outfall. For a wet swale, do not use an under-drain system.
Follow the design procedures identified in the Unified Sizing Criteria section of the Manual to determine the volume control and peak discharge requirements for water quality, recharge (not required), channel protection, overbank flood and extreme storm.
Model the proposed development scenario using a surface water model appropriate for the hydrologic and hydraulic design considerations specific to the site. This includes defining the parameters of the filtration practice defined above: pond elevation and area (defines the pond volume), filtration rate and method of application (effective filtration area), and outlet structure and/or flow diversion information. The results of this analysis can be used to determine whether or not the proposed design meets the applicable requirements. If not, the design will have to be re-evaluated.
A. Volume Filtration systems shall be sufficient to filter a water quality volume of 1 inch of runoff from the new impervious surfaces created by the project. If this criterion is not met,increase the storage volume of the filtration practice or treat excess water quality volume (Vwq) in an upstream or downstream BMP (see Step 5).
B. Period of Inundation
Filtration practices shall discharge through the soil or filter media in 48 hours or less. Additional flows that cannot be infiltrated or filtered in 48 hours should be routed to bypass the system through a stabilized discharge point. This criterion was established to provide the following: wet-dry cycling between rainfall events; unsuitable mosquito breeding habitat; suitable habitat for vegetation; aerobic conditions; and storage for back-to-back precipitation events. The period of inundation is defined as the time from the high water level in the practice to 3 to 6 inches above the invert of the outlet structure or drain tile or bottom of the facility. It is assumed that this range is less than 1/5 the bounce in the filtration practice.A landscaping plan for a dry or wet swale should be prepared to indicate how the enhanced swale system will be stabilized and established with vegetation. Landscape design should specify proper grass species and wetland plants based on specific site, soils and hydric conditions present along the channel.
This table shows sand material specifications.
Link to this table
Parameter | specification | Size | Notes |
---|---|---|---|
Sand | clean AASHTO M-6 or ASTM C-33 concrete sand | 0.02” to 0.04” | Sand substitutions such as Diabase and Graystone #10 are not acceptable. No calcium carbonated or dolomitic sand substitutions are acceptable. Rock dust cannot be substituted for sand. |
Underdrain Gravel | AASHTO M-43 | 1.5” to 3.5” | |
Geotextile Fabric (if required) |
ASTM D-4833 (puncture strength - 125 lb.) ASTM D-1117 (Mullen Burst Strength - 400 psi) ASTM D-4632 (Tensile Strength - 300 lb.) |
0.08” thick equivalent opening size of #80 sieve | Must maintain 125 gpm per sq. ft. flow rate. Note: a 4” pea gravel layer may be substituted for geotextiles meant to separate sand filter layers. |
Impermeable Liner (if required) |
ASTM D-4833 (thickness) ASTM D-412 (tensile strength 1,100 lb., elongation 200%) ASTM D-624 (Tear resistance - 150 lb./in) ASTM D-471 (water adsorption: +8 to -2% mass) |
30 mil thickness | Liner to be ultraviolet resistant. A geotextile fabric should be used to protect the liner from puncture. |
Under-drain Piping | ASTM D-1785 or AASHTO M-278 | minimum 4” rigid schedule 40 PVC | 3/8” perf. @ 6” on center, 4 holes per row; minimum of 3” washed #57 stone over pipes; not necessary underneath pipes |
See Operation and Maintenance section for guidance on preparing an O&M plan.
See Cost Considerations section for guidance on preparing a cost estimate that includes both construction and maintenance costs.