Technique |
Practice |
How it works |
When to apply |
Comments |
Pre-construction planning |
Site planning and grading |
Minimizes soil disturbance and unprotected exposure |
Planning |
Expose only as much as needed for immediate construction |
Sequencing |
Limits amount of soil exposed |
Planning |
Resource protection |
Forest conservation and water resource buffers |
Establishes protective zone around valued natural resources |
Early |
Buffer variable from a few feet to 100 feet depending uopn resource being protected and local regulations |
Perimeter control |
Access and egress control |
Minimizes transport of soil off-site |
Early |
Must be in place prior to commencement of construction activities |
Inlet protection |
Stops movement of soil into drainage collection system |
Early |
Slope stabilization |
Grade breaks |
Minimizes rill and gully erosion |
Early |
No unbroken slopes > 75 feet on 3:1 side slopes or greater |
Silt curtain |
Stops sediment from moving |
Early |
Runoff control |
Stabilize drainageways |
Minimizes increased erosion from channels |
All construction phases |
Possible to convert these into permanent open channel systems after construction |
Sediment control basins |
Collects sediment that erodes from site before it leaves site or impacts resource |
All construction phases |
Possible to convert these into post construction practices after construction |
Rapid stabilization of exposed soils |
Seeding and mulch |
Immediately established vegetative cover on exposed spoil |
All construction phases |
Apply seed as soils are exposed |
Blankets |
Provides extra protection for exposed oil or steep slopes |
All construction phases |
Apply blanket as exposed soil cover until plants established |
Inspection and maintenance |
Formalized I&M program |
Assures that BMPs are properly installed and operating in anticipated manner |
All construction phases |
Essential to proper BMP implementation |