Wet swale construction inspection checklist.
Link to this table
To access an Excel version of form (for field use), click here.
Project: | ||
Location: | ||
Site Status: | ||
Date: | ||
Time: | ||
Inspector: | ||
Construction Sequence | Satisfactory / Unsatisfactory | Comments |
---|---|---|
1. Pre-Construction | ||
Pre-construction meeting | ||
Runoff diverted (Note type of bypass) | ||
Facility area cleared | ||
Project benchmark near site | ||
Facility location staked out | ||
Temporary erosion and sediment protection properly installed | ||
2. Excavation | ||
Size, location, and inverts per plans | ||
Side slopes stable | ||
Lateral slopes completely level | ||
Longitudinal slopes within design range | ||
Groundwater/bedrock verified | ||
Stockpile location not adjacent to excavation area and stabilized with vegetation and/ or silt fence | ||
Verify stockpile is not eroding | ||
3. Structural Components | ||
Outlets installed pre plans | ||
Pretreatment devices installed per plans | ||
Soil bed composition and texture conforms to specifications | ||
Inlets installed per plans | ||
4. Vegetation | ||
For native wet swales, plants and materials ordered 6 months prior to construction | ||
For native wet swales, construction planned to allow for adequate planting and establishment of plant community | ||
Complies with planting specs | ||
Topsoil complies with specs in composition and placement | ||
Soil properly stabilized for permanent erosion control | ||
5. Final Inspection | ||
Project: | ||
Dimensions per plans | ||
Check dams operational | ||
Pre-treatment operational | ||
Inlet/outlet operational | ||
Effective stand of vegetation stabilized per specifications | ||
Construction generated sediments removed | ||
Contributing watershed stabilized before flow is diverted to the practice | ||
Comments: | ||
Actions to be taken: |