Because exact maintenance requirements vary from roof to roof, we do not recommend developing maintenance specifications, but recommend developing example maintenance performance requirements, as described below.
Set the following requirements for, for example, 30 days after Substantial Completion, for roofs established using cuttings, pre-grown modules, or mats:
All areas that do not meet Performance Standards 30 days after installation shall be re-planted with original plant species and densities within 14 days of notification unless weather conditions are not suitable for planting as determined by Owner’s Representative.
Set the following requirements for, for example, 30 days after Substantial Completion, for roofs established using plugs, or pots:
All areas that do not meet Performance Standards 30 days after installation shall be re-planted with original plant species and densities within 14 days of notification unless weather conditions are not suitable for planting as determined by Owner’s Representative.
Set the following requirements for acceptance of maintenance:
Vegetation will be replaced with species and densities acceptable by Owner’s Representative anytime vegetated cover requirements are not met during the maintenance period.
This page was last edited on 7 February 2023, at 21:39.