Line 3: Line 3:
 
===Introduction and Project Purpose===
 
===Introduction and Project Purpose===
  
In this MIDS task, Barr was asked to summarize a typical range of low-impact development
+
In this MIDS task, Barr was asked to summarize a typical range of low-impact development stormwater management best management practices (BMPs) costs. Barr identified a range of typical construction and operating costs for eight1
stormwater management best management practices (BMPs) costs. Barr identified a range of
 
typical construction and operating costs for eight1
 
  
In order to develop a basis for estimating the life cycle costs of stormwater BMP implementation,
+
In order to develop a basis for estimating the life cycle costs of stormwater BMP implementation, readily available data from construction projects and other studies were examined. Barr project files and other public information were used to compile a list of project data that included cost and basic design information. Few data sets included maintenance or land costs. The data sources used vary considerably in where and when they occurred. A major element of this effort was to normalize the data for 2010 Minnesota costs.
readily available data from construction projects and other studies were examined. Barr project files
 
and other public information were used to compile a list of project data that included cost and basic
 
design information. Few data sets included maintenance or land costs. The data sources used vary
 
considerably in where and when they occurred. A major element of this effort was to normalize
 
the data for 2010 Minnesota costs.
 
  
In addition to summarizing construction cost data, the data was compared to available cost models
+
In addition to summarizing construction cost data, the data was compared to available cost models that have been developed by the U.S. Environmental Protection Agency (USEPA), the Minnesota Department of Transportation (MnDOT), and the University of North Carolina. This provided a method of benchmarking the data collected. Use of predictive models was also used for maintenance costs and land area requirements. Because of the paucity of data for maintenance costs and land area, these models provide the greatest source of information for developing life-cycle cost estimates.
that have been developed by the U.S. Environmental Protection Agency (USEPA), the Minnesota
 
Department of Transportation (MnDOT), and the University of North Carolina. This provided a
 
method of benchmarking the data collected. Use of predictive models was also used for maintenance
 
costs and land area requirements. Because of the paucity of data for maintenance costs and land area,
 
these models provide the greatest source of information for developing life-cycle cost estimates.
 
  
Land costs are not included in the life-cycle cost estimates. BMP land costs are dependent on
+
Land costs are not included in the life-cycle cost estimates. BMP land costs are dependent on parcel-specific land costs and land costs vary widely throughout the state and with zoning classification. Instead of including land costs with the BMP life-cycle cost estimates, Barr identified and summarized land requirements for the different structural BMP types. Land requirements depend not only on the size of the BMP, but also on the easement requirements of the permitting authority. Based on a review of the regulatory requirements and interviews with six Minnesota cities, Barr determined that the land area required for easements is a small component of the overall land area needed for each BMP type.
parcel-specific land costs and land costs vary widely throughout the state and with zoning
 
classification. Instead of including land costs with the BMP life-cycle cost estimates, Barr
 
identified and summarized land requirements for the different structural BMP types. Land
 
requirements depend not only on the size of the BMP, but also on the easement requirements of
 
the permitting authority. Based on a review of the regulatory requirements and interviews with six
 
Minnesota cities, Barr determined that the land area required for easements is a small component
 
of the overall land area needed for each BMP type.
 
  
Construction cost data were collected and evaluated for eight structural Best management Practices
+
Construction cost data were collected and evaluated for eight structural Best management Practices (BMPs) categories. These types are described in this section. Each BMP is described using generally accepted definitions found in the literature. The BMPs on which data were collected are consistent with these definitions; however, there may be some variation on the size of the BMPs compared to the typical size ranges included in the definitions below. Water quality treatment volumes are also discussed for each BMP. These water quality treatment volumes were used to compare BMP costs to one another.
(BMPs) categories. These types are described in this section. Each BMP is described using generally
 
accepted definitions found in the literature. The BMPs on which data were collected are consistent
 
with these definitions; however, there may be some variation on the size of the BMPs compared to
 
the typical size ranges included in the definitions below. Water quality treatment volumes are also
 
discussed for each BMP. These water quality treatment volumes were used to compare BMP costs to
 
one another.
 
  
 
===Bioretention Basin/Rainwater Garden without Drain Tile===
 
===Bioretention Basin/Rainwater Garden without Drain Tile===

Revision as of 15:37, 20 December 2017

Best Management Practices Construction Costs, Maintenance Costs, and Land Requirements

Introduction and Project Purpose

In this MIDS task, Barr was asked to summarize a typical range of low-impact development stormwater management best management practices (BMPs) costs. Barr identified a range of typical construction and operating costs for eight1

In order to develop a basis for estimating the life cycle costs of stormwater BMP implementation, readily available data from construction projects and other studies were examined. Barr project files and other public information were used to compile a list of project data that included cost and basic design information. Few data sets included maintenance or land costs. The data sources used vary considerably in where and when they occurred. A major element of this effort was to normalize the data for 2010 Minnesota costs.

In addition to summarizing construction cost data, the data was compared to available cost models that have been developed by the U.S. Environmental Protection Agency (USEPA), the Minnesota Department of Transportation (MnDOT), and the University of North Carolina. This provided a method of benchmarking the data collected. Use of predictive models was also used for maintenance costs and land area requirements. Because of the paucity of data for maintenance costs and land area, these models provide the greatest source of information for developing life-cycle cost estimates.

Land costs are not included in the life-cycle cost estimates. BMP land costs are dependent on parcel-specific land costs and land costs vary widely throughout the state and with zoning classification. Instead of including land costs with the BMP life-cycle cost estimates, Barr identified and summarized land requirements for the different structural BMP types. Land requirements depend not only on the size of the BMP, but also on the easement requirements of the permitting authority. Based on a review of the regulatory requirements and interviews with six Minnesota cities, Barr determined that the land area required for easements is a small component of the overall land area needed for each BMP type.

Construction cost data were collected and evaluated for eight structural Best management Practices (BMPs) categories. These types are described in this section. Each BMP is described using generally accepted definitions found in the literature. The BMPs on which data were collected are consistent with these definitions; however, there may be some variation on the size of the BMPs compared to the typical size ranges included in the definitions below. Water quality treatment volumes are also discussed for each BMP. These water quality treatment volumes were used to compare BMP costs to one another.

Bioretention Basin/Rainwater Garden without Drain Tile

A bioretention basin is a natural or constructed impoundment with permeable soils that captures, temporarily stores, and infiltrates the design volume of stormwater runoff within 48 hours (24 hours within a trout stream watershed). These facilities typically include vegetation. For the purposes of this study, the water quality treatment volume of a bioretention basin is considered to be the total holding capacity below the outlet or overflow elevation of the basin.

Biofiltration Basin/Rainwater Garden with Drain Tile

Biofiltration basins are nearly identical to bioretention basins. The only difference is the addition of a drain tile below the designed filtration media. Filtration basins are often used in areas of potential stormwater “hot-spots2," where groundwater recharge is undesirable, or areas with very low infiltration rates in the underlying soil. As with bioretention basins, the water quality treatment volume is considered the total holding capacity below the outlet or overflow elevation of the basin

Wet Detention Basin

These facilities capture a volume of runoff and retain that volume until it is displaced in part or in total by the next runoff event. Wet detention basins maintain a significant permanent pool of water between runoff events. Wet detention basins that conform to National Urban Runoff Pollution (NURP) criteria have permanent pools with average depths of four to ten feet and volumes below the normal pond outlet that are greater than or equal to the runoff from a 2.5-inch 24-hour storm over the entire contributing drainage area. These basins utilize gravity settling as the major pollutant removal mechanism but nutrient and organic removal can be achieved through aquatic vegetation and microorganism uptake. For the purposes of this study, the water quality treatment volume of a wet detention basin is considered to be the total holding capacity below the permanent pool (dead storage). Wet detention basins are not considered stormwater volume control devices.

Constructed Wetlands

Constructed wetlands are similar to wet detention basins, except they are shallower and the bottom is planted with wetland vegetation. Constructed wetlands remove pollutants through contact time with the permanent pool of water and vegetation uptake. Constructed wetlands typically require large areas to allow for adequate storage volumes and long flow paths. The Minnesota Stormwater Manual recommends that a minimum of 35% of the total wetland surface area should have a depth of 6 inches or less and 10% to 20% of the surface area should be a deep pool (1.5 to 6 foot depth). For the purposes of this study, the water quality treatment volume of a constructed wetland is estimated as the surface area of the wetland multiplied by 18 inches. This estimate is needed to develop a water quality treatment volume for many of the projects samples.

Infiltration Trench/Basin

An infiltration trench is a shallow excavated trench, typically 3 to 12 feet deep, that is backfilled with a coarse stone aggregate, allowing for the temporary storage of runoff in the void space of the material. Discharge of this stored runoff occurs through infiltration into the surrounding naturally permeable soil. Trenches are commonly used for drainage areas less than five acres in size.

An infiltration basin is a natural or constructed impoundment that captures, temporarily stores and infiltrates the design volume of water over several days. Infiltration basins are commonly used for drainage areas of 5 to 50 acres with land slopes that area less than 20 percent. Typical depths range from 2 to 12 feet, including bounce in the basin.

For the purposes of this study, the water quality treatment volume of an infiltration basin or trench is considered the total holding capacity below any outlet or overflow.

Underground Infiltration

In underground infiltration, storage tanks are either incorporated directly into or before the storm sewer system. If the storage systems are completely enclosed, stormwater is released at a controlled rate to a sewer system or open water course, and no stormwater volume is lost. If the storage systems

Privacy policy

Template:Footer