Check dam materials specifications.
Link to this table

Parameter Specification Size Note
Check dam (pressure treated) AWPA Standard C6 6” by 6” or 8” by 8” do not coat with creosote; embed at least 3’ into side slopes
Check Dam (natural wood) Black Locust, Red Mulberry, Cedars, Catalpa, White Oak, Chestnut Oak, Black Walnut 6” to 12” diameter; notch as necessary do not use the following, as these species have a predisposition towards rot: Ash, Beech, Birch, Elm, Hackberry, Hemlock, Hickories, Maples, Red and Black Oak, Pines, Poplar, Spruce, Sweetgum, Willow
Check dam (rock, rip rap) per local criteria Size per requirements based on 10-year design flow Not suitable for infiltration
Check dam (earth) Per local criteria Size per requirements based on 10-year design flow Use clayey soils with low permeability
Check dam (pre-cast concrete per pre-cast manufacturer Size per requirements based on 10-year design flow Testing of pre-cast concrete required:

28 day strength and slump test; all concrete design (cast-in-place or pre-cast) not using previously approved State or local standards requires design drawings sealed and approved by a licensed professional structural engineer.