Line 30: Line 30:
 
##Do not dump liquid wastes in storm sewers
 
##Do not dump liquid wastes in storm sewers
 
##Dispose of liquid wastes properly
 
##Dispose of liquid wastes properly
##*Remove and dispose of hardened concrete waste consistent with the handling of other construction wastes
+
##Remove and dispose of hardened concrete waste consistent with the handling of other construction wastes
 
#Locate any washout or cleanout activities as far away as possible from surface waters and stormwater inlets or conveyances, and, to the
 
#Locate any washout or cleanout activities as far away as possible from surface waters and stormwater inlets or conveyances, and, to the
 
extent practicable, designate areas to be used for these activities and conduct such activities only in these areas.
 
extent practicable, designate areas to be used for these activities and conduct such activities only in these areas.

Revision as of 21:05, 29 February 2016

Concrete, paint, stucco and other washout guidance

National Pollutant Discharge Elimination System/State Disposal System Construction Stormwater Permit requirements

Use this guidance for managing all liquid and solid wastes generated by washout operations (concrete, stucco, paint, form release oils, curing compounds, and other construction materials) related to construction activity on National Pollutant Discharge Elimination System/State Disposal System (NPDES/SDS) construction stormwater permitted sites. To protect water quality, the NPDES Construction Stormwater Permit requires best management practices (BMPs) for concrete and other washout wastes on construction sites.

Background

The chutes of concrete mixers and hoppers of concrete pumps are typically rinsed out after delivery of concrete. Tools, hand mixers and wheel barrows are also washed to prevent hardening. Hardened concrete is relatively benign. However, liquid concrete wash water is a caustic material due to a high pH and it contains hazardous metals such as chromium. These materials can leach into the ground and contaminate groundwater. The high pH can inhibit plant growth and harm aquatic life if the runoff migrates to a lake or stream. Solids from liquid waste that are improperly disposed of can clog storm drain pipes and cause flooding. In order to comply with the prohibition of discharging any materials other than treated stormwater, there must be a means to prevent the discharge of washout water from the cleanup of stucco, paint, form release oils, curing compounds, and other construction materials.

The Minnesota Pollution Control Agency (MPCA) believes that groundwater and surface water can be protected from liquid concrete and other washout wastes through proper use of BMPs at NPDES/SDS construction stormwater permitted sites. Installing washout facilities not only prevents pollution but also is a matter of good housekeeping at a construction site.

Washout at construction sites

Washout facilities are used to contain all concrete and liquid wash water generated by the construction activity. Liquid and solid washout wastes must be contained in a leak-proof container and cannot contact the ground. The washout containers should be covered to prevent exposure to rainfall and potential overflow.

Washout facilities should also be used for cleaning other cementitious (cement-like) construction materials from tools and equipment such as stucco, mortar, plaster and grout. Depositing the wash water into a container allows evaporation and hardening to occur for easier disposal and to prevent runoff of liquids.

While the Construction Stormwater Permit does not allow concrete chute rinse water to come into contact with the ground, the permit does allow the wasting, the end of the load of plastic structural concrete to come into contact with the ground. After drying, the remaining solids may be used as a fill material, a component in recycled aggregate or any other commercially useful application. Up to 0.5 cubic yards of concrete solids may be managed/buried on-site. If concrete solids are buried on-site, they should be at least two feet below the surface and must not be buried within three feet of the groundwater table. Quantities larger than 0.5 cubic yards of concrete solids must either be managed with the rest of the site’s solid wastes or obtain an approval from the MPCA’s solid waste program for other beneficial use options.

There are circumstances where concrete washout may be allowed onto a prepared compacted road bed. This allowance is intended for slip form paving type machines that cannot be readily moved off the paving area to a washout station. The area where wash water will flow onto must be compacted and will be paved over the next day. There must be a barrier of some type to keep the wash water on the compacted road bed until it dries. This allowance is not intended for truck washouts.

A concrete washout sign must be installed at each temporary washout facility to inform the site personnel to use the designated facilities. The facility should be located close to the concrete pouring or mixing operation and be easily accessible by concrete mix trucks. It is also important to locate the facility so that spills or overflows will be directed away from storm drain inlets, curb and gutters, water conveyances or surface waters. The facility will need to be inspected regularly for leaks, damage, or potential overflow and receive regular maintenance.

Washing of applicators and containers used for paint, concrete, or other materials

The permittee must comply with the prohibition of discharges other than stormwater (Part V.C) that includes the washout and cleanout of stucco, paint, concrete, form release oils, curing compounds, and other construction materials. The permittee must provide effective containment for all liquid and solid wastes generated by washout operations and provide an effective means to eliminate the discharge of these wastes to the site or receiving waters. To comply, the permittee should evaluate and incorporate methods in the Stormwater Pollution Prevention Plan to prevent these discharges such as:

  1. Direct all wash water into a leak-proof container or leak-proof pit. The container or pit must be designed so that no overflows can occur due to inadequate sizing or precipitation;
  2. Handle washout or cleanout wastes as follows:
    1. Do not dump liquid wastes in storm sewers
    2. Dispose of liquid wastes properly
    3. Remove and dispose of hardened concrete waste consistent with the handling of other construction wastes
  3. Locate any washout or cleanout activities as far away as possible from surface waters and stormwater inlets or conveyances, and, to the

extent practicable, designate areas to be used for these activities and conduct such activities only in these areas.

Best management practices

There are many BMP options for disposal of liquid and solid wastes from washout activities. Many ready mix trucks are now equipped with the ability to collect chute wash water and solids and return them to the concrete plant for recycling or re-use.