Sediment controls on linear utility projects

The following question and answer document provides answers to general questions about U.S. Environmental Protection Agency (EPA) National Pollutant Discharge Elimination System (NPDES) construction stormwater permitting program, and specific questions about various requirements in EPA’s 2012 Construction General Permit (CGP). This document incorporates questions and answers from the 2012 EPA document, “The 2012 EPA CGP: Answers to Common Questions” which was most recently updated on December 16, 2014. It is intended for use by operators of construction sites who are eligible for coverage and/or who are permitted under EPA’s 2012 CGP, or by interested members of the general public.

Part IV.C.2 of the general permit for construction activity requires that sediment control practices (e.g., filter berms, silt fences, temporary diversion dikes) must be established on all down gradient perimeters and must be in place before any upgradient land‐disturbing activities begin. The Minnesota Pollution Control Agency recognizes that in some areas where land disturbance is minimal, perimeter controls may not be practicable or, alternatively, not necessary in order to minimize sediment from reaching surface waters or stormwater conveyance systems. When designing sediment control practices, Part III.A.5.i allows consideration for the nature of stormwater runoff and run-on at the site including factors such as slope and site drainage features. In these cases, permittees must document the site characteristics in the project’s Stormwater Pollution Prevention Plan (SWPPP) and may proceed with construction activity in those areas without installing perimeter controls.

It is important to remember, permittees are ultimately responsible for any off-site impacts from construction activity that result or may result in discharges to waters of the state (Minn. R. 7050.0210). For this reason, permittees are encouraged to provide a contingency plan in the SWPPP that addresses the procedures for correcting the site in the event that sediment has left those areas where sediment control practices were not installed and is causing or has the potential to cause off site impacts to waters of the state or other sensitive areas.

To clarify this concept, the sediment control requirement only applies to perimeter areas of the construction site that receive stormwater from the earth-disturbing activity. If a portion of the construction site’s perimeter area does not receive stormwater from earth-disturbing activities, perimeter controls would not be required in that portion of the site. Therefore, perimeter controls would not be necessary in the perimeter area surrounding construction activities in areas of sites where no new earth-disturbing activities occur, which could include:

  • Pole sites where only overhead work is conducted.
  • Use of pre-existing access roads or pad areas where no expansion or below-grade improvements (e.g., no new earth disturbances) will occur.
  • Areas where vegetation is left in place but needs to be trimmed (e.g., mowing, weed-whacking, etc.) to allow temporary access (e.g., overland travel) or use of a site (e.g., wire stringing site). In such circumstances, the ground cover (i.e., grasses and other low-growing vegetation, such as mosses, ferns, vines, shrubs, herbaceous plants, and root mats that are planted or that naturally occur) is retained and no grading occurs.