<center><font size=3>'''Contractor bid averages for installation of three 29,000 gallon underground storage tanks'''</font size><br>
+
<font size=3>'''Contractor bid averages for installation of three 29,000 gallon underground storage tanks'''</font size><br>
  
Link to this [[Contractor bid averages for installation of three 29,000 gallon underground storage tanks|table]]</center>
+
Link to this [[Contractor bid averages for installation of three 29,000 gallon underground storage tanks|table]]
  
 
<table class="sortable">
 
<table class="sortable">

Revision as of 16:18, 6 December 2016

Contractor bid averages for installation of three 29,000 gallon underground storage tanks

Link to this table

BASE BID ITEM ESTIMATED QUANTITY UNIT UNIT PRICE AVERAGE TOTAL AVERAGE BID
Part 1 - General and Erosion Control
MOBILIZATION 1 LS 💲23,340 💲23,340
SEDIMENT CONTROL LOG -- INSTALL, MAINTENANCE AND REMOVAL 267 LF 💲5 💲1,335
TEMPORARY FENCE -- INSTALL AND REMOVAL 160 LF 💲8 💲1,280
STABILIZED CONSTRUCTION EXIT -- INSTALL, MAINTENANCE AND REMOVAL 1 LS 💲2,410 💲2,410
EROSION CONTROL BLANKET 424 SY $4 $1,696
STORM DRAIN INLET PROTECTION -- INSTALL, MAINTENANCE AND REMOVAL 2 EA 💲387 💲774
DUST CONTROL 10 HRS 💲121 💲1,210
Total Part 1 💲32,045
Part 2 - Removals
REMOVE EXISTING SEDIMENT CONTROL LOG OR SILT FENCE Total Part 2 268 LF 💲4 💲1,072
Total Part 2 💲1,072
Part 3 - Grading
COMMON EXCAVATION -- INCLUDES TANK TRENCH EXCAVATION AND FILL TO PROPOSED GRADE 1955 CY $9 $9
REMOVAL OF EXCAVATED MATERIAL 1389 CY $10 $13,890
AGGREGATE BACKFILL 1009 CY $41 $41,369
Total Part 3 💲72,854
Part 4 – Underground Storage Tank Components
RAINWATER HARVESTING TANK (120" DIA. X 50-FEET) 3 EA 💲77,639 💲232,917
CONSTRUCT DRAINAGE STRUCTURE 6 EA 💲1,153 💲6,918
CONCRETE, REINFORCED COLLAR (RISER MANHOLE CAP) 6 EA 💲1,085 💲6,510
CONCRETE, REINFORCED COLLAR (AT RISER CONNECTION TO TANK) 6 EA 💲1,248 💲7,488
INSTALL CASTING 6 EA 💲1,221 💲7,326
18" HDPE PIPE 115 LF 💲73 💲8,395
SOIL DENSITY COMPACTION TESTING 12 EA 💲430 💲5,160
Total Part 4 💲274,714
Part 5 – Site Restoration
RAPID STABILIZATION 0.42 AC 💲3,173 💲1,333
PERMANENT SEEDING 0.42 AC 💲6,336 💲2,661
TURF ESTABLISHMENT 1 EA 💲2,500 💲2,500
Total Part 5 💲6,494
Total Bid 💲386,590
PRICE PER TANK (3 – 29,000 gallon tanks) 💲129,060
PRICE PER TANK PER YEAR OVER 25 YEAR 💲5,162
PRICE PER GALLON 💲1.46
PRICE PER GALLON PER YEAR OVER 25 YEARS 💲0.06