Soil erosion and sediment runoff to waterways are significant problems in Minnesota. According to the Minnesota Pollution Control Agency (MPCA 2014), approximately 30 percent of the state’s rivers and streams are impaired by sediment. Poorly managed construction sites can be substantial sediment sources to these surface waters. Up to 100 tons of sediment per acre can be lost annually from unmanaged construction sites (EPA 1999). Regulations administered by the State of Minnesota through the construction stormwater permit program (MPCA 2013) seek to address these impacts by requiring

  1. carefully crafted sediment and erosion control plans designed to reduce polluted runoff;
  2. implementation and updating of the plan;
  3. operation and maintenance of runoff reduction measures until the site is stabilized; and
  4. significant penalties for negligence and willful violations.

This section provides general information on the process by which sediment is eroded from the land surface from rainfall events and the basic principles of erosion prevention and sediment control. Understanding this basic information and applying these principles in the field will reduce negative environmental impacts associated with erosion and sediment loss and help ensure compliance with Minnesota requirements and avoidance of violations and fines.

Construction site stormwater program compliance timeline

  • Evaluate and assess the construction site
    • Collect site information (size, slopes, soils, drainage patterns)
    • Identify sensitive areas – waters, vegetation, slopes, etc.
    • Produce map or drawing of the existing site
    • Create the final project design map or drawing
    • Characterize the sequence of major construction activities
    • Calculate area, infiltration, runoff, and drainage system sizing
  • Select site-specific erosion, sediment, and housekeeping controls
    • Review local and state permit requirements
    • Identify erosion prevention field practices and site locations
    • Select sediment control practices and field locations
    • Determine housekeeping and pollution prevention practices
    • Indicate location of best management practices (BMPs)
    • Prepare a plan for inspecting and maintaining BMPs
  • Complete permitting and notification tasks
    • Identify all contractors and subcontractors
    • Develop stormwater pollution prevention plan (SWPPP)
    • Submit Notice of Intent to MPCA
    • Apply for and obtain other local/state/federal permits
    • Familiarize contractors and others with SWPPP requirements
  • Construction and SWPPP implementation
    • Install stabilized exit and initial downgradient perimeter controls
    • Install and stabilize initial drainage system, traps, and basins
    • Proceed with phased clearing and grading work
    • Implement phased erosion/sediment BMPs as needed
    • Stabilize disturbed areas within 14 days or as required
    • Inspect and maintain BMPs, document activities
  • Final stabilization and permit termination
    • Stabilize all disturbed areas, slopes, and drainage systems
    • Remove waste and unused materials
    • Remove all temporary BMPs, stabilize BMP locations
    • File Notice of Termination and other required notices

Principles of erosion

Erosion is the dislodgement and movement of soil and rock by water, wind, or ice. Erosion is a natural process but can be greatly accelerated by human activity, such as clearing and grading of the land surface or disturbance of conveyance channels (Pitt et al. 2007). Erosion begins when particles of soil and rock break away, and continues as that material is transported by natural forces. Erosion caused by water can take many forms. Raindrop or splash erosion often leads to sheet erosion and the formation of small rills or creases in the landscape, which can enlarge into gullies if not addressed. Flowing water and the action of waves and ice along the unprotected edge of rivers, streams, and lakes can also cause channel or bank erosion.

Major factors affecting soil erosion from precipitation events include soil characteristics, climate, rainfall intensity and duration, topography, vegetation or other surface cover, and conservation management practices. These factors can be quantified and used to predict erosion rates. Over the past few decades, they have been incorporated into the Revised Universal Soil Loss Equation (RUSLE), which is used worldwide to evaluate, predict, and address erosion challenges on farms, mines, and construction sites (USDA 2012). Understanding RUSLE provides a basis for selecting erosion prevention measures related to surface disturbance.

RUSLE calculates average annual soil loss in tons/acre/year using the equation

A = R * K *LS *C *P

where,

A = average annual soil loss, in tons/acre/year
R = rainfall-runoff erosivity factor
K = soil erodibility factor
L = length of the slope factor
S = steepness of the slope factor
C = cover management factor
P = erosion control practice factor

A is expressed in the units selected for K and for the period selected for R (in common practice these are usually selected such that they compute A, soil loss, in U.S. tons per acre per year).

RUSLE factors are observable in the field and fairly simple to derive. The R and K variables are generally out of the hands of the construction site operator. Slope (S) and slope length (L) can sometimes be managed or impacted during the design phase of project development. Two RUSLE variables which can be controlled at active construction sites – the cover and practices factors (i.e., variables C and P) – are the focus of the erosion prevention measures. Erosion prevention practices, which mostly include soil preparation, vegetation, and the application of a mulch, blanket, mat, or other cover on bare soil, are the easiest, cheapest, and most effective approach for addressing runoff from construction sites. Sediment control – settling soil particles from temporarily ponded runoff water or filtering it using silt fencing or other materials –is more difficult, more expensive, and requires much more maintenance . Tables 1 and 2 provide additional information on how higher C factors in RUSLE – and lower P factors – are linked to increased erosion potential.

{{ALERT|The BWSR provides a free online calculator with many of the factor values preloaded. Link here.

Examples of RUSLE cover management factors for construction sites

Examples of RUSLE practice management factors for construction sites

Management practices at construction sites can be characterized as those intended to prevent erosion and those that control sediment loss from sheet runoff and concentrated flow discharges. Erosion prevention practices are generally those included in the “C and P” RUSLE factors, and also include planning approaches that can affect overall sediment losses from the site (see below). Sediment controls can be grouped as those that promote settling of soil particles or those that physically trap particles through filtration. Erosion prevention practices are preferred and are typically less expensive to implement compared to sediment control practices.

As noted above, planning and site management can also influence erosion and sediment transport on construction sites. Site-level prevention actions that can be implemented or controlled by the construction site operator include the following:

  • Planning approaches that minimize the size of the bare soil area and the length of time disturbed areas are exposed to the elements – especially for long, steep slopes and easily erodible soils.
  • Diverting or otherwise controlling the location and volume of run-on flows to the site from adjacent areas.
  • Keeping concentrated flows in ditches stabilized with vegetation, rock, or other material
  • Covering bare soil with vegetation, mulch, erosion control blankets, turf reinforcement mats, gravel, rock, plastic sheeting, soil binder chemicals, etc.

Site planning and erosion prevention measures are coupled with sediment control practices to prevent sediment laden discharges from construction sites. Sediment control practices focus on:

  • Physical filtration of sediment by trapping soil particles as water passes through a silt fence, drop inlet screen, fiber roll, etc.
  • Settling processes, that allow sediment to fall out of flows that are slowed and temporarily impounded in ponds, traps, or in small pools created by berms, silt fencing, inlet protection dikes, check dams, etc.

Site cover greatly influences erosion processes. Table 1 shows the percent reduction of soil loss – relative to a disturbed site with no surface cover practice – for the most commonly used soil covers, with the highest ratings associated with native undisturbed vegetation, a 90 percent cover of grass or sod, and hay mulch applied at the rate of two tons per acre. When developing a site’s erosion and sediment control plan, it is important to remember that large bare areas exposed to run-on and the elements will erode the most over time, especially where 1) rainfall is heavy, 2) soils are highly erodible, 3) slopes are long, and 4) slopes are steep. While construction managers typically have little control over these four factors, they are key inputs into decisions regarding what types of erosion prevention measures (which directly address cover management and erosion control practice factors) to employ. Other factors that influence the selection of erosion prevention are the proximity and type of nearby surface waters (rivers, lakes, streams, and wetlands), seasonal factors (rainy, freezing, etc.), the type of construction project (e.g., roadways, residential, commercial), and the construction setting (urban, suburban, rural, industrial).

When identified, assessed, and considered in an integrated manner, the factors listed above comprise a risk profile for your construction site. Crafting an erosion, sediment, and housekeeping plan that identifies and addresses risks represented by these factors through a carefully selected system of management practices will ensure minimal impacts to Minnesota’s waters and compliance with construction stormwater regulations.