(8 intermediate revisions by 3 users not shown)
Line 5: Line 5:
 
==MS4 General Permit requirements for MCM 4==
 
==MS4 General Permit requirements for MCM 4==
 
The construction site stormwater runoff control program must include:
 
The construction site stormwater runoff control program must include:
:*A regulatory mechanism that establishes erosion, sediment, and waste controls as stringent as the [https://stormwater.pca.state.mn.us/index.php/Construction_stormwater_permit Construction Stormwater permit] requirements for construction sites.  
+
:*A regulatory mechanism that establishes erosion, sediment, and waste controls as stringent as the [https://stormwater.pca.state.mn.us/index.php?title=2018_Minnesota_Construction_Stormwater_Permit Construction Stormwater permit] requirements for construction sites.  
 
:*A [[site plan review procedure]] for conducting site plan reviews to ensure compliance with the construction stormwater runoff control regulatory mechanism.  
 
:*A [[site plan review procedure]] for conducting site plan reviews to ensure compliance with the construction stormwater runoff control regulatory mechanism.  
 
:*Written [[#Example Procedures|procedures]] for the receipt and consideration of reports of noncomplaince at construction sites received from the public.
 
:*Written [[#Example Procedures|procedures]] for the receipt and consideration of reports of noncomplaince at construction sites received from the public.
Line 22: Line 22:
 
*[https://stormwater.pca.state.mn.us/index.php?title=MS4_Staff_Site_Plan_Review_Guidance MPCA Site plan review guidance] - MPCA's guidance on what elements should be evaluated during a site plan review
 
*[https://stormwater.pca.state.mn.us/index.php?title=MS4_Staff_Site_Plan_Review_Guidance MPCA Site plan review guidance] - MPCA's guidance on what elements should be evaluated during a site plan review
 
*[https://www.cwp.org/updated-code-ordinance-worksheet-improving-local-development-regulations/ Code and Ordinance Worksheet for Improving Local Development Regulations] - The Center for Watershed Protection's handbook that has over twenty model development standards for designing sites to reduce impervious surfaces, conserve open space, reduce the impacts to stormwater, and save money
 
*[https://www.cwp.org/updated-code-ordinance-worksheet-improving-local-development-regulations/ Code and Ordinance Worksheet for Improving Local Development Regulations] - The Center for Watershed Protection's handbook that has over twenty model development standards for designing sites to reduce impervious surfaces, conserve open space, reduce the impacts to stormwater, and save money
*[[media:Timelines.xlsx|Timeframes listed in the Construction Stormwater Permit]] - MPCA's document containing all of the time frame considerations that are detailed in the [[Construction stormwater permit| Construction Stormwater Permit]]
+
*[[media:Wq-strm4-90.pdf|Timeframes listed in the Construction Stormwater Permit]] - MPCA's document containing all of the time frame considerations that are detailed in the [https://stormwater.pca.state.mn.us/index.php?title=2018_Minnesota_Construction_Stormwater_Permit Construction stormwater permit Construction Stormwater Permit]
 +
*[[media: Construction-Stormwater-Permit-Small Lot.pdf|10 Steps to Stormwater Pollution Prevention on Small Residential Construction Sites]] - MPCA's factsheet on the 10 Steps to Stormwater Pollution Prevention on Small Residential Construction Sites.
  
 
===Documentation and tracking templates===
 
===Documentation and tracking templates===
Line 36: Line 37:
 
*[[media:Construction Site Inspection Checklist - Prior Lake.docx|Construction site inspection checklist]] - City of Prior Lake's construction site inspection checklist
 
*[[media:Construction Site Inspection Checklist - Prior Lake.docx|Construction site inspection checklist]] - City of Prior Lake's construction site inspection checklist
 
*[[media:Construction Site Inspection Checklist - Rice Lake.docx|Construction site inspection checklist]] - City of Rice Lake's construction site inspection checklist
 
*[[media:Construction Site Inspection Checklist - Rice Lake.docx|Construction site inspection checklist]] - City of Rice Lake's construction site inspection checklist
 +
*[[media:Construction Site Inspection Checklist - Blue Earth County.docx|Construction site inspection checklist]] - Blue Earth County's construction site inspection checklist
 
*[https://www.pca.state.mn.us/sites/default/files/wq-strm2-47.pdf Site plan review checklist] - MPCA's site plan review checklist
 
*[https://www.pca.state.mn.us/sites/default/files/wq-strm2-47.pdf Site plan review checklist] - MPCA's site plan review checklist
 
*[[media:Site Plan Review Checklist - Rice Lake.docx|Site plan review checklist]] - City of Rice Lake's site plan review checklist
 
*[[media:Site Plan Review Checklist - Rice Lake.docx|Site plan review checklist]] - City of Rice Lake's site plan review checklist
Line 59: Line 61:
 
*[[media:CONSERVATION BUFFER Sign - Hutchinson.docx|Buffer reminder]] - City of Hutchinson's reminder to maintain a vegetative buffer at the water's edge
 
*[[media:CONSERVATION BUFFER Sign - Hutchinson.docx|Buffer reminder]] - City of Hutchinson's reminder to maintain a vegetative buffer at the water's edge
 
*[[media:2017 Builder Contractor Erosion Control Meeting - Big Lake.pdf| Contractor training]] - City of Big Lake's training for contractors conducting construction projects within the city
 
*[[media:2017 Builder Contractor Erosion Control Meeting - Big Lake.pdf| Contractor training]] - City of Big Lake's training for contractors conducting construction projects within the city
 +
*[[media:RCWD_&_Centerville_MS4_MCM_4_Pilot_Partnership.pdf|MCM 4 Pilot Agreement]] - PDF version of pilot agreement between Rice Creek Watershed District and the City of Centerville for MCM 4
 +
*[[media:RCWD_&_Centerville_MS4_MCM_4_Pilot_Partnership.docx|MCM 4 Pilot Agreement]] - Word version of pilot agreement between Rice Creek Watershed District and the City of Centerville for MCM 4

Revision as of 15:50, 20 September 2021

Construction site adjacent to water body

Introduction

Controlling sediment and other pollutants from construction sites is crucial to an effective stormwater management program. Minimum Control Measure (MCM) 4 of the MS4 General Permit requires permittees to have and enforce a construction site stormwater runoff control program to reduce the impacts of land disturbing activities to stormwater.

MS4 General Permit requirements for MCM 4

The construction site stormwater runoff control program must include:

  • A regulatory mechanism that establishes erosion, sediment, and waste controls as stringent as the Construction Stormwater permit requirements for construction sites.
  • A site plan review procedure for conducting site plan reviews to ensure compliance with the construction stormwater runoff control regulatory mechanism.
  • Written procedures for the receipt and consideration of reports of noncomplaince at construction sites received from the public.
  • Construction site inspection procedures for inspecting public and private construction sites. The procedures should include: procedures for identifying and prioritizing sites for inspections, the frequency of site inspections, the name or title of the person responsible for inspections, and a checklist or other written means to document site inspections.
  • Enforcement response procedures to compel compliance with the construction stormwater runoff control regulatory mechanism.
  • Documentation as described here.

Resources

Click on the blue links above in the "MS4 General Permit requirements" section to get more information and resources specific to those permit requirements. In addition, all resources related to MCM 4 are below.

Fact sheets and guidance documents

Fact sheets and guidance documents should provide background information and tips to inform your approach to implementing MCM 4 - Construction Site Stormwater Control.

Documentation and tracking templates

Documentation and tracking templates are examples that local stormwater staff are currently using to meet the MS4 General Permit requirements for MCM 4 - Construction Site Stormwater Control.

Checklists

Below are methods that local stormwater staff are currently using to meet the site inspection and site plan review documentation requirements in the MS4 General Permit for MCM 4 - Construction Site Stormwater Control.

Example Procedures

Example procedures are those that local stormwater staff are currently using to meet the MS4 General Permit requirements for MCM 4 - Construction Site Stormwater Control.

Model language

Fill in the blanks and adopt ordinance language that meets the regulatory mechanism requirements for MS4 General Permit requirements for MCM 4 - Construction Site Stormwater Control.

Other

Miscellaneous materials local stormwater staff are using.

  • Construction site good housekeeping reminder - City of Red Wing's tool to remind construction site owners/operators to maintain sites in compliance with their construction site stormwater runoff control regulatory mechanism
  • Construction site good housekeeping acknowledgement - City of Red Wing's tool to acknowledge and appreciate sites that are in compliance with their construction site stormwater runoff control regulatory mechanism
  • Notice of violation - City of Rice Lake's notice of violation
  • Buffer reminder - City of Hutchinson's reminder to maintain a vegetative buffer at the water's edge
  • Contractor training - City of Big Lake's training for contractors conducting construction projects within the city
  • MCM 4 Pilot Agreement - PDF version of pilot agreement between Rice Creek Watershed District and the City of Centerville for MCM 4
  • MCM 4 Pilot Agreement - Word version of pilot agreement between Rice Creek Watershed District and the City of Centerville for MCM 4