Information: NOTE: you have arrived at a step in the Design Sequence flow chart. This flow chart is used to determine your performance goal. For more information see this link
image of Minimal Impact Design Standards logo
For more information on the Design Sequence Flow Chart see the following:
*Flexible treatment options
*MIDS flow chart
*List of steps in flow chart

QUESTION:

Is shallow groundwater or shallow bedrock present on site?

Yes

No

If you are unsure, we recommend you review the guidance for shallow groundwater in this manual. To retain your place in this flowchart, either open the shallow groundwater guidance page in a new tab (right click on the link and select Open Link in New Tab), use the back arrow after visiting the shallow groundwater guidance page, or use the Breadcrumbs at the top of the page.

PREVIOUS QUESTION and ANSWER:

  • Is karst present on the site?
    • Answer: No

or

  • Can a local unit of government (LGU) provide a higher level of engineering review to ensure a functioning system that prevents adverse impacts to groundwater?
    • Answer: Yes

or

  • Is BMP relocation onsite to a location without karst feasible?
    • Answer: Yes