Information: NOTE: you have arrived at a step in the Design Sequence flow Chart. This flow chart is used to determine your performance goal. For more information see this link
image of Minimal Impact Design Standards logo
For more information on the Design Sequence Flow Chart see the following:
*Flexible treatment options
*MIDS flow chart
*List of boxes in flow chart

QUESTION:

Do any of the following conditions apply? (NOTE: If any condition applies, you do not need to answer the remaining questions.)

  • The site is located within a DWSMA, wellhead protection area, or within 200 feet of a drinking water well, and infiltration is not allowed by the LGU

Yes

  • Karst is present within 1000 feet of the site and the BMP cannot be relocated so that it is more than 1000 feet from karst

Yes

  • Shallow groundwater or shallow bedrock is present within 3 feet of the bottom of the BMP and the BMP cannot be relocated or raised in elevation to achieve a 3 foot or greater separation from bedrock or groundwater

Yes

  • Contaminated soil, contaminated groundwater, or hotspot runoff is present on the site and cannot be isolated or mitigated

Yes

  • Soils on the site have an infiltration rate of less than 0.2 inches per hour, the BMP cannot be relocated to areas with a higher infiltration rate, and the BMP cannot be sized to drain within 48 hours (24 hours in locations that are tributary to trout streams)

Yes

  • Soils on the site have an infiltration rate greater than 8 inches per hour, the BMP cannot be relocated to an area with an infiltration rate lower than 8 inches per hour, or the subgrade cannot be modified to slow the infiltration rate to less than 8 inches per hour

Yes


No