(6 intermediate revisions by one other user not shown)
Line 1: Line 1:
{{alert|This section of the manual is being developed|alert-under-construction}}
 
 
 
==SECTION 8 EROSION PREVENTION PRACTICES==
 
==SECTION 8 EROSION PREVENTION PRACTICES==
  
Line 13: Line 11:
  
 
===8.4===
 
===8.4===
<big>Permittees must stabilize all exposed soil areas, including stockpiles. Stabilization must be initiated immediately to limit soil erosion when construction activity has permanently or temporarily ceased on any portion of the site and will not resume for a period exceeding 14 calendar days. Stabilization must be completed no later than 14 calendar days after the construction activity has ceased. Stabilization is not required on constructed base components of roads, parking lots and similar surfaces. Stabilization is not required on temporary stockpiles without significant silt, clay or organic components (e.g., clean aggregate stockpiles, demolition concrete stockpiles, sand stockpiles) but must provide sediment controls at the base of the stockpile.</big>
+
<big>Permittees must stabilize all exposed soil areas, including stockpiles. Stabilization must be [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.14 initiated immediately] to limit soil erosion when [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.6 construction activity] has permanently or temporarily ceased on any portion of the site and will not resume for a period exceeding 14 calendar days. Stabilization must be completed no later than 14 calendar days after the construction activity has ceased. Stabilization is not required on constructed base components of roads, parking lots and similar surfaces. Stabilization is not required on temporary stockpiles without significant silt, clay or organic components (e.g., clean aggregate stockpiles, demolition concrete stockpiles, sand stockpiles) but must provide [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.29 sediment controls] at the base of the stockpile.</big>
  
 
===8.5===
 
===8.5===
Line 19: Line 17:
  
 
===8.6===
 
===8.6===
<big>Permittees must stabilize the normal wetted perimeter of the last 200 linear feet of temporary or permanent drainage ditches or swales that drain water from the site within 24 hours after connecting to a surface water or property edge. Permittees must complete stabilization of remaining portions of temporary or permanent ditches or swales within 14 calendar days after connecting to a surface water or property edge and construction in that portion of the ditch temporarily or permanently ceases.</big>
+
<big>Permittees must stabilize the [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.18 normal wetted perimeter] of the last 200 linear feet of temporary or permanent drainage ditches or swales that drain water from the site within 24 hours after connecting to a surface water or property edge. Permittees must complete stabilization of remaining portions of temporary or permanent ditches or swales within 14 calendar days after connecting to a [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.34 surface water] or property edge and construction in that portion of the ditch temporarily or permanently ceases.</big>
  
 
===8.7===
 
===8.7===
Line 28: Line 26:
  
 
===8.9===
 
===8.9===
<big>Permittees must provide temporary or permanent energy dissipation at all pipe outlets within 24 hours after connection to a surface water or permanent stormwater treatment system.</big>
+
<big>Permittees must provide temporary or permanent [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_25_Definitions#25.8 energy dissipation] at all pipe outlets within 24 hours after connection to a surface water or permanent stormwater treatment system.</big>
  
 
===8.10===
 
===8.10===
<big>Permittees must not disturb more land (i.e., phasing) than can be effectively inspected and maintained in accordance with Section 11.</big>
+
<big>Permittees must not disturb more land (i.e., phasing) than can be effectively inspected and maintained in accordance with [https://stormwater.pca.state.mn.us/index.php?title=MN_CSW_Permit_Section_11_Inspections_and_Maintenance Section 11].</big>
 +
 
 +
<noinclude>
 +
[[Category:2018 Construction Stormwater General Permit]]
 +
</noinclude>

Revision as of 20:59, 28 September 2021

SECTION 8 EROSION PREVENTION PRACTICES

8.1

Erosion Prevention Practices.

8.2

Before work begins, permittees must delineate the location of areas not to be disturbed.

8.3

Permittees must minimize the need for disturbance of portions of the project with steep slopes. When steep slopes must be disturbed, permittees must use techniques such as phasing and stabilization practices designed for steep slopes (e.g., slope draining and terracing).

8.4

Permittees must stabilize all exposed soil areas, including stockpiles. Stabilization must be initiated immediately to limit soil erosion when construction activity has permanently or temporarily ceased on any portion of the site and will not resume for a period exceeding 14 calendar days. Stabilization must be completed no later than 14 calendar days after the construction activity has ceased. Stabilization is not required on constructed base components of roads, parking lots and similar surfaces. Stabilization is not required on temporary stockpiles without significant silt, clay or organic components (e.g., clean aggregate stockpiles, demolition concrete stockpiles, sand stockpiles) but must provide sediment controls at the base of the stockpile.

8.5

For Public Waters that the Minnesota DNR has promulgated "work in water restrictions" during specified fish spawning time frames, permittees must complete stabilization of all exposed soil areas within 200 feet of the water's edge, and that drain to these waters, within 24 hours during the restriction period.

8.6

Permittees must stabilize the normal wetted perimeter of the last 200 linear feet of temporary or permanent drainage ditches or swales that drain water from the site within 24 hours after connecting to a surface water or property edge. Permittees must complete stabilization of remaining portions of temporary or permanent ditches or swales within 14 calendar days after connecting to a surface water or property edge and construction in that portion of the ditch temporarily or permanently ceases.

8.7

Temporary or permanent ditches or swales being used as a sediment containment system during construction (with properly designed rock-ditch checks, bio rolls, silt dikes, etc.) do not need to be stabilized. Permittees must stabilize these areas within 24 hours after their use as a sediment containment system ceases.

8.8

Permittees must not use mulch, hydromulch, tackifier, polyacrylamide or similar erosion prevention practices within any portion of the normal wetted perimeter of a temporary or permanent drainage ditch or swale section with a continuous slope of greater than 2 percent.

8.9

Permittees must provide temporary or permanent energy dissipation at all pipe outlets within 24 hours after connection to a surface water or permanent stormwater treatment system.

8.10

Permittees must not disturb more land (i.e., phasing) than can be effectively inspected and maintained in accordance with Section 11.