Line 36: Line 36:
 
<sup>1</sup>an additional soil boring or pit should be completed for each additional 2,500 ft<sup>2</sup> above 12,500 ft<sup>2</sup><br>
 
<sup>1</sup>an additional soil boring or pit should be completed for each additional 2,500 ft<sup>2</sup> above 12,500 ft<sup>2</sup><br>
 
<sup>2</sup>an additional five permeameter tests should be completed for each additional 5,000 ft<sup>2</sup> above 15,000 ft<sup>2</sup></font size>
 
<sup>2</sup>an additional five permeameter tests should be completed for each additional 5,000 ft<sup>2</sup> above 15,000 ft<sup>2</sup></font size>
 
  
 
<noinclude>[[category:table]]</noinclude>
 
<noinclude>[[category:table]]</noinclude>

Revision as of 16:42, 13 February 2014

Recommended number of soil borings, pits and permeameter tests for bioretention design.
Link to this table

Surface area of stormwater control measure (BMP)(ft2) Borings Pits Permeameter tests
< 1000 1 1 5
1000 to 5000 2 2 10
5000 to 10000 3 3 15
>10000 41 41 202

1an additional soil boring or pit should be completed for each additional 2,500 ft2 above 12,500 ft2
2an additional five permeameter tests should be completed for each additional 5,000 ft2 above 15,000 ft2