Summary of quantities - stormwater step pool case study.
Link to this table

Item Unit Quantity
Riprap 6 Cubic yard 12
Riprap 5 Cubic yard 37
Riprap 3 Cubic yard 41
Riprap 1 Cubic yard 37
Limestone blocks Each 26
Grout Longitudinal section 1
Natural stone boulders (12-18 inches) Cubic yard 15
Culvert removal Linear foot 75
Earth excavation Cubic yard 193
Seeding - floodplain mix Acre 0.21
Seeding - mesic savanna mix Acre 0.11
Turf seeding Acre 0.11
Bypass pumping Longitudinal section 1
Tree removal Each 8
Brush clearing Square yard 445
Silt fencing Linear foot 325
Erosion blanket - S-75 Square yard 1017
Erosion blanket - S-150 Square yard 533
Straw mulch Square yard 533
Temporary ditch/creek check - coir log Each 2
Construction entrance Longitudinal section 1